Office of Financial Management Washington State Major Project Status Report Agency Number

advertisement
Office of Financial Management
Washington State Major Project Status Report
June 30, 2015
Agency Number: 699
Project Number: 20062699
School/Campus: Clover Park Technical College
Project Title:
Health Sciences Facility Construction
Bill Reference(s): 2011-13 Capital Budget
Agency: SBCTC
Project Description: The notice to proceed with construction of the 56,468 square-foot Health
Sciences Facility was issued on January 17, 2012. Construction was anticipated to be completed
in July 2013; however, the project is still not complete because the contractor has some
outstanding items to address.
The facility accommodates the rapidly growing health care programs to include Nursing,
Hemodialysis, Health Unit Coordinator, Materials Management/CS, Surgical Technology,
Medical Assistant, Medical Lab Technician, Medical Office Specialist, and Pharmacy
Technician. This state-of-the-art facility also provides space for new programs including
Registered Nurse, Histology Technician, as well as Chemistry and Anatomy and Physiology
labs.
Square feet: 56,468
Scope changes: One roof garden was converted to a classroom.
Project Total Cost:
Phase
Predesign
Design
Construction (& Redesign)
Other (Approp/Non Approp)
Total
MACC = $15,292,366
Biennium
2005-07
2007-09
2011-13, 2013-15
Appropriation
H53
112, K01
K01
Amount
$160,000
$1,709,143
$20,585,000
$22,454,143
Schedule:
Budget Schedule
(as currently
funded)
June 2006
December 2007
May - June 2011
Predesign Complete
Start Design
Bid
Notice to Proceed
50% Complete
Substantial Completion
Final Acceptance
June 2011
January 2013
Actual/Forecast
June 2007
January 2008
November 15,
2011
January 17, 2012
Dec. 15, 2012
December 2013
June 2014
Variance (wks)
52
4
22
31
48
Project Status and discussion of Critical Path for Construction:
The design process was completed on scheduled and the construction bid took place on
November 15, 2011. The construction contract was awarded on January 17, 2012.
Contract Award History
A/E Agreement
Original Agreement
(without tax)
Amendments
Pending Changes
Total
Current Design
Contingency
$1,287,374.40
Construction Contract (excl. sales tax)
Bid Award Amount $13,939,000.00
$ 1,147,877.74
$ ______.00
$ 2,435,252.14
$ 2,435,252.14
$
.00
Change Orders
$ 1,393,776.48
$___________
Pending Changes
Total $15,332,776.48
Current Construction $16,776,543.07 (tax)
Contingency
$ 1,524,791.47 (tax).
Potential for Project Cost Overruns/Claims
None at this time.
Discussion of Project Quality
The pre-design and the design are completed and the construction contract was awarded on January
17, 2012. The parking lot was available for the College’s use by the first day of fall quarter 2014.
Substantial completion was October 21, 2014. The anticipated final completion date is June 30,
2015.
Project Photographs
Related documents
Download