Office of Financial Management Washington State Major Project Status Report December 31, 2008 Agency Number: 140 Project Number: 04-1-689 School/Campus: Clark College Project Title: East County Satellite Bill Reference(s): 488-05-770 Contact name, phone number, email: Jim Green, Director of Plant Services (360) 992-2408, jgreen@clark.edu Agency: SBCTC Project Description: Construct an instructional facility at Clark College East County Satellite campus. Square feet: 68,542 gsf Scope changes: n/a Project Total Cost: Phase Predesign Design Construction Other (Approp/Non Approp) Total Biennium 2003-05 2005-07 2007-09 Appropriation AS3J AS5J AS7J Amount 300,000 2,392,000 27,091,900 29,783,900 MACC = 20,470,000 Schedule: Predesign Complete Start Design Bid Date Notice to Proceed 50% Complete Substantial Completion Final Acceptance Budget Schedule June 03 July 05 June 07 July 07 Feb 08 Nov 08 Jan 09 1 Actual/Forecast June 04 July 06 Nov 07 Dec 07 June 08 April 09 July 09 Variance (wks) 52 52 20 20 20 20 25 Project Status and discussion of Critical Path for Construction: Construction contract has been completed and closed out. Modifications requested by City have been completed. College classes began September 21, 2009, and building occupancy was at approximately 86% at opening. Building commissioning is ongoing. Contract Award History A/E Agreement Original Agreement Amendments Pending Changes Total Current Design Contingency $ $ $ $ $ $ Construction Contract (excl. sales tax) 1,515,277.00 Bid Award Amount $ 19,411,000.00 1,118,472.00 Change Orders $ 778,789.23 0.00 Pending Changes $ 2,633,749.00 Total $ 20,189,789.23 0.00 Current Construction 0.00 Contingency $ 1,941,100.00 Potential for Project Cost Overruns/Claims None identified at this time. Discussion of Project Quality East County Satellite will be a LEED silver building built to campus standards and will incorporate all architectural features outlined in the covenants and restrictions portion of the Purchase of Sale Agreement. Project Photographs 2 3 4