Office of Financial Management Washington State Major Project Status Report June 2015 Agency Number: 699 Agency: SBCTC Project Number: 30000126 School/Campus: Peninsula College Project Title: Allied Health and Early Childhood Development Center Bill Reference(s): ESSB5035.SL – Section 5118 Contact name, phone number, email: David Wegener, Construction Manager, 360-417-7999, dwegener@pencol.edu Project Description: The Allied Health and Early Childhood Development Center project responds to regional workforce demand by providing a state-of-the-art facility for the college's Allied Health departments: nursing, medical assisting and community demand. The center also houses the early childhood development programs which consist of early childhood education and childcare facilities for toddlers and preschoolers (with the possibility of caring for infants if desired). The building enables these programs to better serve the educational, economic, health and childcare needs of the North Olympic Peninsula community. The project is at 75% CD, the cost estimate is complete and constructability review is underway. Square feet: 41,650 sf Scope changes: With the possibility of a $3 million cut to the project budget the college and design team undertook an aggressive review of all project elements. Maintaining program space and functionality is a priority and has been preserved within these budget restraints. The college is foregoing geo-thermal heating and cooling (a source used successfully on three prior college projects) and eliminated a PV array that would provide hot water for the building. In order to get the project underway sooner and take advantage of the summer schedule and weather as well as the possibility of a more favorable bid climate, the college decided to bid this project in two phases – demolition/utility infrastructure and construction. Project Total Cost: Phase Predesign Design Construction Other (Approp/Non Approp) Total Biennium 2013-15 2013-15 2015-17 Appropriation S13 S13 TBD Amount (below) $ 1,810,000 $26,868,000 $28,678,000 MACC = $18,550,290 1 Schedule: Predesign Complete Start Design Phase I Bid Date Notice to Proceed Substantial Completion Final Acceptance Phase II Bid Date Notice to Proceed 50% Complete Substantial Completion Final Acceptance Budget Schedule October 2013 January 2014 Actual/Forecast February 2014 February 2014 Variance (wks) 3 1 June 2015 July 2015 November 2015 December 2015 June 2015 (F) 0 September 2015 October 2015 April 2016 December 2016 January 2017 Project Status and discussion of Critical Path for Construction: Phase I of the project is due to bid in June 2015. Contract Award History A/E Agreement Original Agreement Amendments Pending Changes Total Current Design Contingency Construction Contract (excl. sales tax) Bid Award Amount $ Change Orders $ Pending Changes $___________ Total $ Current Construction Contingency $ $ 913,899 $ 458,830 $ $ 1,372,729 $0 Potential for Project Cost Overruns/Claims: The college and design team have worked very hard to eliminate potential areas of concern on this project. Because of known poor soil conditions on the campus, this project will utilize auger cast piles. The college has worked closely and collaboratively with local regulatory agencies to address issues around wetlands and stormwater management. As part of the Constructability Review team, a contractor has been consulted to ensure the best possible transitions between Phase I and Phase II of this project. Discussion of Project Quality: Peninsula College engages many faculty and staff in the predesign/design process to ensure a very high quality and well-functioning facility. Working as a team with the project architects, the college will continue to strive for an efficient, top quality facility placing teaching and learning at its center. Project Photographs (Attached): Renderings attached. 2