Office of Financial Management Washington State Major Project Status Report June 2015

advertisement
Office of Financial Management
Washington State Major Project Status Report
June 2015
Agency Number: 699
Agency: SBCTC
Project Number: 30000126
School/Campus: Peninsula College
Project Title: Allied Health and Early Childhood Development Center
Bill Reference(s): ESSB5035.SL – Section 5118
Contact name, phone number, email:
David Wegener, Construction Manager, 360-417-7999, dwegener@pencol.edu
Project Description:
The Allied Health and Early Childhood Development Center project responds to regional
workforce demand by providing a state-of-the-art facility for the college's Allied Health
departments: nursing, medical assisting and community demand. The center also houses the early
childhood development programs which consist of early childhood education and childcare
facilities for toddlers and preschoolers (with the possibility of caring for infants if desired). The
building enables these programs to better serve the educational, economic, health and childcare
needs of the North Olympic Peninsula community.
The project is at 75% CD, the cost estimate is complete and constructability review is underway.
Square feet: 41,650 sf
Scope changes: With the possibility of a $3 million cut to the project budget the college and
design team undertook an aggressive review of all project elements. Maintaining program space
and functionality is a priority and has been preserved within these budget restraints. The college
is foregoing geo-thermal heating and cooling (a source used successfully on three prior college
projects) and eliminated a PV array that would provide hot water for the building.
In order to get the project underway sooner and take advantage of the summer schedule and
weather as well as the possibility of a more favorable bid climate, the college decided to bid this
project in two phases – demolition/utility infrastructure and construction.
Project Total Cost:
Phase
Predesign
Design
Construction
Other (Approp/Non Approp)
Total
Biennium
2013-15
2013-15
2015-17
Appropriation
S13
S13
TBD
Amount
(below)
$ 1,810,000
$26,868,000
$28,678,000
MACC = $18,550,290
1
Schedule:
Predesign Complete
Start Design
Phase I
Bid Date
Notice to Proceed
Substantial Completion
Final Acceptance
Phase II
Bid Date
Notice to Proceed
50% Complete
Substantial Completion
Final Acceptance
Budget Schedule
October 2013
January 2014
Actual/Forecast
February 2014
February 2014
Variance (wks)
3
1
June 2015
July 2015
November 2015
December 2015
June 2015 (F)
0
September 2015
October 2015
April 2016
December 2016
January 2017
Project Status and discussion of Critical Path for Construction:
Phase I of the project is due to bid in June 2015.
Contract Award History
A/E Agreement
Original Agreement
Amendments
Pending Changes
Total
Current Design
Contingency
Construction Contract (excl. sales tax)
Bid Award Amount $
Change Orders
$
Pending Changes
$___________
Total $
Current Construction
Contingency
$
$ 913,899
$ 458,830
$
$ 1,372,729
$0
Potential for Project Cost Overruns/Claims: The college and design team have worked very
hard to eliminate potential areas of concern on this project. Because of known poor soil conditions
on the campus, this project will utilize auger cast piles. The college has worked closely and
collaboratively with local regulatory agencies to address issues around wetlands and stormwater
management. As part of the Constructability Review team, a contractor has been consulted to
ensure the best possible transitions between Phase I and Phase II of this project.
Discussion of Project Quality: Peninsula College engages many faculty and staff in the
predesign/design process to ensure a very high quality and well-functioning facility. Working as a
team with the project architects, the college will continue to strive for an efficient, top quality
facility placing teaching and learning at its center.
Project Photographs (Attached):
Renderings attached.