TITLE 6309.11 - CONTRACT ADMINISTRATION HANDBOOK
R6/PNW Supplement No. 6309.11-93-4
Effective June 28, 1993
POSTING NOTICE. Supplements to this handbook are numbered consecutively.
Check the last transmittal sheet received for this handbook to see that the above
supplement number is in sequence. If not, obtain intervening supplement(s) at once
from the Information Center. Do not post this supplement until the missing one(s)
is received and posted. After posting, place the transmittal at the front of the title
and retain until the first transmittal of the next calendar year is received.
The last R6/PNW Supplement to this handbook was 6309.11-93-3 (6309.11,20).
Document Name
Superseded New
(Number of sheets)
6309.11,30
2
Page Code
32.1--1 thru --3
2
32.11--1, --2
1
Digest:
33 - States requirements to sign off on Final Inspection for Vegetation Management
Projects.
/s/ John E. Lowe
/s/ Charles W. Philpot
JOHN E. LOWE
Regional Forester
CHARLES W. PHILPOT
Station Director
R6/PNW SUPPLEMENT 6309.11-93-4
EFFECTIVE 06/28/93
6309.11, 30
Page 2 of 2
FSH 6309.11 - CONTRACT ADMINISTRATION HANDBOOK
R6/PNW SUPPLEMENT 6309.11-93-4
EFFECTIVE 06/28/93
CHAPTER 30 - MEASUREMENT AND PAYMENTS
32 - PAYMENTS.
32.1 - Prompt Processing of Payment Estimate and Invoice. Payments for
reforestation and timber stand improvement work shall be prepared on Form R66320-39, or an approved computer-generated form. (See FSH 6509.11k, ServiceWide Finance and Accounting Handbook, Section 46.22a for definition of progress
and partial payment processing.)
33 - CERTIFICATE OF FINAL INSPECTION.
For Vegetation Management projects, Form R6-FS-2100-12, "Vegetation
Management Reporting Form," must be completed and forwarded to the
Contracting Officer (CO) as a part of the Final Inspection process. Each employee
must be listed individually on the form. The CO retains a copy and forwards
original to the Regional Office Forest Pest Management-Integrated Pest
Management Specialist. Note this form is required for all projects to manage
competing and unwanted vegetation, regardless of whether any accidents or
exposures occurred.
34 - FINAL PAYMENT AND RELEASE FROM CONTRACT.
A contract release shall be furnished by the contractor if required by the contract.