UNDER CONSTRUCTION E a s t b u r n STORM DRAINAGE IMPROVEMENT PROJECT Dear Resident: January 2013 Construction continues for Charlotte-Mecklenburg Storm Water Services’ Eastburn Storm Drainage Improvement Project. The large structure at Park South Drive next to the Marriott has been completed and the area has been backfilled. Work continues on Park South Executive Drive at the parking deck. The shoring contractor has had some equipment failure, but is planning weekend work to catch up. As soon as shoring is in place, Blythe Construction will begin installing pipe again. Milling of asphalt at the parking deck is scheduled to start soon, weather permitting. Work on the berm at the other end of the parking lot has begun. After completion of work at Park South Executive Drive, work continues upstream at Eastburn, Sunnybrook and Fairheath. The City would like to thank all residents for their patience and cooperation. For more information about this project, please visit our website to view project updates and exhibits at: http://stormwater.charmeck.org. Click on Storm Water Projects drop down menu in the green bar, then Active Projects and Eastburn. A large box is installed for double 72 inch reinforced concrete pipes at the Marriott. Engineering & Property Management Storm Water Services Division 600 East Fourth Street Charlotte, North Carolina 28202 Eastburn Project Update HIGHLIGHTS If you have any questions, please contact one of the following members: On-site Construction Inspector: Project Manager: Monty Bissette: 704-400-7788 Matthew Anderson: 704-336-7923 Email: mbissette@charlottenc.gov Email: manderson@charlottenc.gov Construction Supervisor: Gary Stansbury: 704-336-2667 E-mail: gstansbury@charlottenc.gov A construction inspector will be on site daily to address any questions or concerns. Please note efforts are taken to minimize disruption to nearby properties.