Dear Resident,
Charlotte-Mecklenburg Storm Water Services held a public meeting
for the Eastburn Storm Drainage Improvement Project on
October 27, 2009 at Sharon Presbyterian Church.
•
The meeting presented general project information on Storm Water
Services and discussed the preliminary design plans for the Eastburn
project. Meeting highlights:
•
•
•
•
Mr. Anderson discussed the design efforts on the project since
planning. The geotechnical analysis has been completed,
project areas have been surveyed, and design options have been
considered. Utility design has also been completed for those
which need to be relocated.
An overview map of the proposed project improvements was
distributed for public meeting attendees for reference.
Mr. Anderson noted the project is currently in the real estate
phase. Four project easement types have been identified for
the project: storm drainage, sanitary sewer, permanent utility,
and temporary construction. For any property owner where
Engineering & Property Management
Storm Water Services Division
600 East Fourth Street
Charlotte, North Carolina 28202
Eastburn Project Update
HIGHLIGHTS FROM PUBLIC MEETING
•
construction is proposed, the owner should have received letters
showing the proposed easements.
The remaining project schedule was discussed. The Real Estate
Phase is expected to last 12 months. After completion, the
City will enter the bid phase, which can last up to five months.
Construction can last up to 24 months after a contractor is
selected.
Project updates will be mailed quarterly to keep citizens
informed of progress.
The meeting was opened for general questions. The citizens then
broke out into four smaller groups to ask individual property
questions.
For more information about this project or detailed meeting minutes,
please visit our website at http://stormwater.charmeck.org and click
on Storm Water Projects, Storm Water Projects again, then Eastburn.
If you have any questions about this project, please contact the
Project Manager, Matthew Anderson at manderson@charlottenc.gov
or 704-336-7923.
Download