UNDER CONSTRUCTION E a s t b u r n STORM DRAINAGE IMPROVEMENT PROJECT Dear Resident: September 2012 Construction continues for Charlotte-Mecklenburg Storm Water Services’ Eastburn Storm Drainage Improvement Project. Work is 95% complete on Sunnybrook with trimming trees and seeding issues remaining. The work is expected to be complete in the next few weeks. The infrastructure on Park South Drive and Archdale is in place and driveways and sidewalks have been replaced. We expect to pour final asphalt on Park South by the end of October. There have been some holdups on South Executive Drive at the parking deck. Rock is constant and there are some shoring issues to be worked out, but we are about to finish the last run of 72” pipe. The existing pipe is being lined now and should be done by October 5. City staff continues to monitor all locations of the site and fix problems as they arise. Please feel free to contact site inspector with any questions you may have. The City would like to thank all residents for their patience and cooperation. For more information about this project, please visit our website to view project updates and exhibits at: http://stormwater. charmeck.org. Click on Storm Water Projects drop down menu in the green bar, then Active Projects and Eastburn. Contractors work at night to relocate a 6-inch water line avoiding disruption to area businesses. Engineering & Property Management Storm Water Services Division 600 East Fourth Street Charlotte, North Carolina 28202 Eastburn Project Update HIGHLIGHTS If you have any questions, please contact one of the following team members: Project Manager: On-site Construction Inspector: Matthew Anderson: 704-336-7923 Monty Bissette: 704-400-7788 Email: mbissette@charlottenc.gov Email: manderson@charlottenc.gov A construction inspector will be on site daily to address any questions or concerns. Please note efforts are taken to minimize disruption to nearby properties.