07-03-2012 Space Update

advertisement
University of North Florida
ADMINISTRATION & FINANCE
Departmental Status Report for Space Committee Meeting
Director:
Department:
Date:
Zak Ovadia
Campus Planning Design & Construction
July 3rd, 2012
I. SELECTED ACTIVE PROJECTS
NOTE ALL SCHEDULES ARE TENTATIVE
1.
Student Wellness & Sports Education Center Phase I: This project entails the
programming, design and construction of a Student Wellness and Sports Education
Center (Est. 116,000 GSF). Phase I in roughly 65,000 GSF.
Tentative Schedule:
Consultant Selection
Complete
Programming
Complete
RFQ for Design
Complete
Consultant Selection
Complete
Program Verification Complete
Schematic Design
Complete
Design Development Complete
Select CM
Complete
Const. Documents
Complete
Construction
January 2011 – MAY 2012.
Changes from last month:
Construction GMP is on target
at $16.4 Million. Project is on
schedule for May 2012.
Substantial Completion was
achieved on June 14. Gilbane
is currently working on Punch
List. Equipment started to be
delivered and installed.
Furniture is expected at
various times.
2.
Programming for Buildings 50, 3 and 4: This project entails the programming, of three
buildings for backfilling and restacking once the Biology Department moves to the new
Biological Sciences Building in 2012.
Tentative Schedule:
Consultant Selection
Complete
Programming
March 2011
Changes from last month:
Phys. Fac. has engaged an
HVAC consultant to look at
air balancing for Bldg. 3. A
CPSR was received for minor
demolition on first floor of
Bldg. 4 for Engineering and
CCEC.
Zak Ovadia
1
3.
Hayt Golf Learning Center – Women’s Locker Room & Lounge: Renovations to
two of the laboratories vacated by Biology to create a Lounge/Locker/Shower Rooms for
the Women’s Golf Team to address Title IX requirements.
Tentative Schedule:
Consultant Selection
Complete
Programming
Complete
Schematic Design
Complete
Design Development Complete
Const. Documents
April 2012
Select GC
July 2012
Construction
August 2012 to December 2012
Changes from last month:
Construction Documents are
complete and are out for
bidding. Due to lack of
funding, project is being
phased.
4.
Northeast Connector Road and Lot 34 Upgrade:
Design and Build a new road connecting the Loop Road to the Round-about at Lot 18 and
paving of Lot 34 behind the Arena...
Tentative Schedule:
Consultant Selection
Complete
Programming
N/A
Program Verification N/A
Schematic Design
June 2011
Design Development July 2011
Const. Documents
September 2011
Select CM
Auld & White
Construction
December 2011 to May, 2012
Changes from last month:
Numerous drainage issues
were identified and are being
rectified. Road will likely be
opened for use around midJuly.
5.
Sanctuary and Meditation Center: Design and Construction of sanctuary building of
approximately 3,500 square feet to serve as a venue for group meditation or events.
Tentative Schedule:
Feasibility Study of Sites underway
Programming
TBD
Conceptual Permitting TBD
RFQ for Consultants TBD
Short-listing & Interv. TBD
Program Verification TBD
Schematic Design
TBD
Design Development TBD
Construction Docs.
TBD
Construction
TBD
Changes from last month:
No Changes since Last Period.
Combined with the religious
centers, a consultant has been
hired to investigate the
availability of utilities for these
buildings and cost to extend
them.
Zak Ovadia
2
6.
New Food Service Facility and General Purpose Building: Design and Construction
of a replacement food service facility to replace Osprey Café. Preliminary needs call for
a three or four-story building.
Tentative Schedule:
Programming
August 2010
Conceptual Permitting TBD
RFQ for Consultants Completed
Short-listing & Interv. Completed
Program Verification Completed
Schematic Design
February, 2011
Design Development March 2011 – April 2011
Select CM
Complete
Construction Docs.
May 2011 – August 2011
Demolition
May 2011
Construction
July 2011 to August 2012
Changes from last month:
No issues to report.
Construction is moving well.
Substantial Completion
scheduled for August 2012.
7.
New Housing Maintenance Building: Design and Construction of a replacement
maintenance and storage facility for Housing. Program calls for a 14,000 GSF building
to accommodate all storage and maintenance needs for Housing operations.
Tentative Schedule:
Programming
Completed
Conceptual Permitting Completed
RFQ for Consultants Completed
Short-listing & Interv. Completed
Program Verification Completed
Schematic Design
Completed
Design Development Completed
Select CM
Completed
Construction Docs.
June 2011 – November 2011
Construction
December 2011 to August 2012
Changes from last month:
The building is Substantially
Complete with the exception of
the landscaping. Furniture has
been delivered and occupants
are currently moving in.
Zak Ovadia
3
8.
Development of Greek Village: This project entails the programming and completing a
feasibility study to develop 250-bed a Greek Village at Tech. Park
Tentative Schedule:
Consultant Selection
RFQ Released
Consultant Selection
TBD
Programming
Feasibility Study
Report Due
Changes from last month:
9.
TBD
TBD
TBD
Selection Committee
interviewed three candidates
on June 1st. Recommendation
was forwarded to President
after deliberation by
Committee members.
Treanor Architects was
selected. First meeting is
being scheduled.
New Housing Clubhouse Building: Design and Construction of a new Clubhouse to
service the housing units in the core campus. Program calls for a 14,000 GSF building to
contain a Convenience Store/Grill, a Multi-purpose Room, a Laundry facility for 450
students, an R/A Graphics Room, a Game Room and a Mail Distribution area for 2,900
students.
Tentative Schedule:
Programming
Complete
RFQ for Consultants Complete
Short-listing & Interv. Complete
Program Verification June 2012
Schematic Design
July 2012
Design Development September 2012
Select CM
August 2012
Construction Docs.
December 2012
Construction
March 2012
Changes from last month:
Meetings with consultants are
taking place to define scope
and start Schematic Design.
Completed Projects:




Zak Ovadia
COE&HS Building with DRC, VCS, VCL and OCT
Science and Humanities Building (Biological Sciences)
Science & Engineering Building Remedial Work:
4