University of North Florida ADMINISTRATION & FINANCE Departmental Status Report for Space Committee Meeting Director: Department: Date: Zak Ovadia Campus Planning Design & Construction April 4th, 2012 I. SELECTED ACTIVE PROJECTS NOTE ALL SCHEDULES ARE TENTATIVE 1. Student Wellness & Sports Education Center Phase I: This project entails the programming, design and construction of a Student Wellness and Sports Education Center (Est. 116,000 GSF). Phase I in roughly 65,000 GSF. Tentative Schedule: Consultant Selection Complete Programming Complete RFQ for Design Complete Consultant Selection Complete Program Verification Complete Schematic Design Complete Design Development Complete Select CM Complete Const. Documents Complete Construction January 2011 – MAY 2012. Changes from last month: Construction GMP is on target at $16.4 Million. Project is on schedule for May 2012. No changes this month. 2. Programming for Buildings 50, 3 and 4: This project entails the programming, of three buildings for backfilling and restacking once the Biology Department moves to the new Biological Sciences Building in 2012. Tentative Schedule: Consultant Selection Complete Programming March 2011 Changes from last month: No changes this month. Phys. Fac. has engaged an HVAC consultant to look at air balancing for Bldg. 3. Zak Ovadia 1 3. Science and Humanities Building (Biological Sciences): It is anticipated that the building will be roughly 118,000 GSF on three levels. The building will be located adjacent to the Social Sciences Building (51). Tentative Schedule: Consultant Selection Complete Programming Complete Program Verification Complete Schematic Design Complete Design Development Complete Const. Documents March 2010 Select CM Complete Construction August 2010 to February 2012 Changes from last month: The last sensitive equipment has been moved. This project is now complete and will be removed from the list. 4. Science & Engineering Building Remedial Work: Corrective measures to mitigate building envelope deficiencies. Tentative Schedule: Consultant Selection Complete Programming N/A Program Verification N/A Schematic Design TBD Design Development TBD Const. Documents September 2010 Select CM Complete Construction Dec. 2010 – March 2012 Changes from last month: No Changes from Last Month. 5. Northeast Connector Roar and Lot 34 Upgrade: Design and Build a new road connecting the Loop Road to the Round-about at Lot 18 and paving of Lot 34 behind the Arena... Tentative Schedule: Consultant Selection Complete Programming N/A Program Verification N/A Schematic Design June 2011 Design Development July 2011 Const. Documents September 2011 Select CM Auld & White Construction December 2011 to May, 2012 Changes from last month: Construction started in midDecember, 2011. No issues from last month. Completion of parking lot end of March, Road at the end of April. Zak Ovadia 2 6. Sanctuary and Meditation Center: Design and Construction of sanctuary building of approximately 3,500 square feet to serve as a venue for group meditation or events. Tentative Schedule: Feasibility Study of Sites underway Programming TBD Conceptual Permitting TBD RFQ for Consultants TBD Short-listing & Interv. TBD Program Verification TBD Schematic Design TBD Design Development TBD Construction Docs. TBD Construction TBD Changes from last month: Combined with the religious centers, a consultant has been hired to investigate the availability of utilities for these buildings and cost to extend them. 7. New Food Service Facility and General Purpose Building: Design and Construction of a replacement food service facility to replace Osprey Café. Preliminary needs call for a three or four-story building. Tentative Schedule: Programming August 2010 Conceptual Permitting TBD RFQ for Consultants Completed Short-listing & Interv. Completed Program Verification Completed Schematic Design February, 2011 Design Development March 2011 – April 2011 Select CM Complete Construction Docs. May 2011 – August 2011 Demolition May 2011 Construction July 2011 to August 2012 Changes from last month: No Changes from Last Month. The design for the third and fourth floors has been finalized and presented to the VPs on March 7th. A GMP is expected around the first week of April. Substantial Completion scheduled for August 2012. Zak Ovadia 3 8. New Housing Maintenance Building: Design and Construction of a replacement maintenance and storage facility for Housing. Program calls for a 14,000 GSF building to accommodate all storage and maintenance needs for Housing operations. Tentative Schedule: Programming Completed Conceptual Permitting Completed RFQ for Consultants Completed Short-listing & Interv. Completed Program Verification Completed Schematic Design Completed Design Development Completed Select CM Completed Construction Docs. June 2011 – November 2011 Construction December 2011 to August 2012 Changes from last month: No Changes from Last Month. Substantial Completion scheduled for August 2012. 9. Development of Greek Village: This project entails the programming and completing a feasibility study to develop 250-bed a Greek Village at Tech. Park Tentative Schedule: Consultant Selection RFQ Released Consultant Selection TBD Programming Feasibility Study Report Due Changes from last month: TBD TBD TBD New project added to list. Completed Projects: Zak Ovadia COE&HS Building with DRC, VCS, VCL and OCT 4