04-04-2012 Space Update

advertisement
University of North Florida
ADMINISTRATION & FINANCE
Departmental Status Report for Space Committee Meeting
Director:
Department:
Date:
Zak Ovadia
Campus Planning Design & Construction
April 4th, 2012
I. SELECTED ACTIVE PROJECTS
NOTE ALL SCHEDULES ARE TENTATIVE
1.
Student Wellness & Sports Education Center Phase I: This project entails the
programming, design and construction of a Student Wellness and Sports Education
Center (Est. 116,000 GSF). Phase I in roughly 65,000 GSF.
Tentative Schedule:
Consultant Selection
Complete
Programming
Complete
RFQ for Design
Complete
Consultant Selection
Complete
Program Verification Complete
Schematic Design
Complete
Design Development Complete
Select CM
Complete
Const. Documents
Complete
Construction
January 2011 – MAY 2012.
Changes from last month:
Construction GMP is on target
at $16.4 Million. Project is on
schedule for May 2012. No
changes this month.
2.
Programming for Buildings 50, 3 and 4: This project entails the programming, of three
buildings for backfilling and restacking once the Biology Department moves to the new
Biological Sciences Building in 2012.
Tentative Schedule:
Consultant Selection
Complete
Programming
March 2011
Changes from last month:
No changes this month. Phys.
Fac. has engaged an HVAC
consultant to look at air
balancing for Bldg. 3.
Zak Ovadia
1
3.
Science and Humanities Building (Biological Sciences): It is anticipated that the
building will be roughly 118,000 GSF on three levels. The building will be located
adjacent to the Social Sciences Building (51).
Tentative Schedule:
Consultant Selection
Complete
Programming
Complete
Program Verification Complete
Schematic Design
Complete
Design Development Complete
Const. Documents
March 2010
Select CM
Complete
Construction
August 2010 to February 2012
Changes from last month:
The last sensitive equipment
has been moved. This project
is now complete and will be
removed from the list.
4.
Science & Engineering Building Remedial Work:
Corrective measures to mitigate building envelope deficiencies.
Tentative Schedule:
Consultant Selection
Complete
Programming
N/A
Program Verification N/A
Schematic Design
TBD
Design Development TBD
Const. Documents
September 2010
Select CM
Complete
Construction
Dec. 2010 – March 2012
Changes from last month:
No Changes from Last Month.
5.
Northeast Connector Roar and Lot 34 Upgrade:
Design and Build a new road connecting the Loop Road to the Round-about at Lot 18 and
paving of Lot 34 behind the Arena...
Tentative Schedule:
Consultant Selection
Complete
Programming
N/A
Program Verification N/A
Schematic Design
June 2011
Design Development July 2011
Const. Documents
September 2011
Select CM
Auld & White
Construction
December 2011 to May, 2012
Changes from last month:
Construction started in midDecember, 2011. No issues
from last month. Completion
of parking lot end of March,
Road at the end of April.
Zak Ovadia
2
6.
Sanctuary and Meditation Center: Design and Construction of sanctuary building of
approximately 3,500 square feet to serve as a venue for group meditation or events.
Tentative Schedule:
Feasibility Study of Sites underway
Programming
TBD
Conceptual Permitting TBD
RFQ for Consultants TBD
Short-listing & Interv. TBD
Program Verification TBD
Schematic Design
TBD
Design Development TBD
Construction Docs.
TBD
Construction
TBD
Changes from last month:
Combined with the religious
centers, a consultant has been
hired to investigate the
availability of utilities for
these buildings and cost to
extend them.
7.
New Food Service Facility and General Purpose Building: Design and Construction
of a replacement food service facility to replace Osprey Café. Preliminary needs call for
a three or four-story building.
Tentative Schedule:
Programming
August 2010
Conceptual Permitting TBD
RFQ for Consultants Completed
Short-listing & Interv. Completed
Program Verification Completed
Schematic Design
February, 2011
Design Development March 2011 – April 2011
Select CM
Complete
Construction Docs.
May 2011 – August 2011
Demolition
May 2011
Construction
July 2011 to August 2012
Changes from last month:
No Changes from Last Month.
The design for the third and
fourth floors has been
finalized and presented to the
VPs on March 7th. A GMP is
expected around the first
week of April. Substantial
Completion scheduled for
August 2012.
Zak Ovadia
3
8.
New Housing Maintenance Building: Design and Construction of a replacement
maintenance and storage facility for Housing. Program calls for a 14,000 GSF building
to accommodate all storage and maintenance needs for Housing operations.
Tentative Schedule:
Programming
Completed
Conceptual Permitting Completed
RFQ for Consultants Completed
Short-listing & Interv. Completed
Program Verification Completed
Schematic Design
Completed
Design Development Completed
Select CM
Completed
Construction Docs.
June 2011 – November 2011
Construction
December 2011 to August 2012
Changes from last month:
No Changes from Last Month.
Substantial Completion
scheduled for August 2012.
9.
Development of Greek Village: This project entails the programming and completing a
feasibility study to develop 250-bed a Greek Village at Tech. Park
Tentative Schedule:
Consultant Selection
RFQ Released
Consultant Selection
TBD
Programming
Feasibility Study
Report Due
Changes from last month:
TBD
TBD
TBD
New project added to list.
Completed Projects:

Zak Ovadia
COE&HS Building with DRC, VCS, VCL and OCT
4