12-05-2012 Space Project Update

advertisement
University of North Florida
ADMINISTRATION & FINANCE
Departmental Status Report for Space Committee Meeting
Director:
Department:
Date:
Zak Ovadia
Campus Planning Design & Construction
December 5th, 2012
I. SELECTED ACTIVE PROJECTS
NOTE ALL SCHEDULES ARE TENTATIVE
1.
Programming for Buildings 50, 3 and 4: This project entails the programming, of three
buildings for backfilling and restacking once the Biology Department moves to the new
Biological Sciences Building in 2012 as well as various renovations in Bldgs. 3, 4, and
50..
Tentative Schedule:
Consultant Selection
Complete
Programming
March 2011
Changes from last month:
 Demolition Work at Bldg.
4 First Floor completed.
Painting and Flooring
complete. Faculty has
moved in.
 Estimate to prepare Bldg. 3
for Math was sent to
Barbara Hetrick. No
Change.
 Electrical Work to
relocate the CCEC
Machine Shop in Bldg. 50
complete.
2.
Interfaith Sanctuary: Design and Construction of sanctuary building of approximately
6,500 square feet to serve as a venue for group events.
Tentative Schedule:
Feasibility Study of Sites underway
Programming
TBD
Conceptual Permitting TBD
RFQ for Consultants TBD
Short-listing & Interv. TBD
Program Verification TBD
Schematic Design
TBD
Design Development TBD
Construction Docs.
TBD
Construction
TBD
Changes from last month:
President’s Mandatory Briefing
was held November 1.
Submissions are due
December 4th. Committee is
scheduled to meet January 7th
to shortlist.
Zak Ovadia
1
3.
Religious Centers: Engage Civil Engineer to provide a feasibility study and an order of
magnitude cost for providing utility services to a grouping of four buildings.
Tentative Schedule:
ON HOLD.
4.
New Food Service Facility and General Purpose Building: Design and Construction
of a replacement food service facility to replace Osprey Café. Preliminary needs call for
a three or four-story building.
Tentative Schedule:
Programming
August 2010
Conceptual Permitting TBD
RFQ for Consultants Completed
Short-listing & Interv. Completed
Program Verification Completed
Schematic Design
February, 2011
Design Development March 2011 – April 2011
Select CM
Complete
Construction Docs.
May 2011 – August 2011
Demolition
May 2011
Construction
July 2011 to November 2012
Changes from last month:
No Change. Substantial
completion should occur on
December 3rd. Faculty
Enhancement and Campus
Planning will move mid to the
end of December
5.
Development of Greek Village: This project entails the programming and completing a
feasibility study to develop 250-bed a Greek Village at Tech. Park
Tentative Schedule:
Consultant Selection
RFQ Released
Consultant Selection
TBD
Programming
Feasibility Study
Report Due
Changes from last month:
Zak Ovadia
TBD
TBD
December 2012
Committee meetings have
been taking place regularly.
Draft financial analysis was
reviewed on November 27th.
Final report is scheduled to be
unveiled February 5th, 2013..
2
6.
New Housing Clubhouse Building: Design and Construction of a new Clubhouse to
service the housing units in the core campus. Program calls for a 15,000 GSF building to
contain a Convenience Store/Grill, a Multi-purpose Room, a Laundry facility for 450
students, an R/A Graphics Room, a Game Room and a Mail Distribution area for 2,900
students.
Tentative Schedule:
Programming
Complete
RFQ for Consultants Complete
Short-listing & Interv. Complete
Program Verification Complete
Schematic Design
August 2012
Design Development October 2012
Select CM
January 2013
Construction Docs.
Marchr 2012
Construction
April 2013 to July 2014.
Changes from last month:
Project is currently in the
Design Development Phase.
CM firms have been
shortlisted. Interviews
scheduled for January 10,
2013.
Completed Projects:







Zak Ovadia
COE&HS Building with DRC, VCS, VCL and OCT
Science and Humanities Building (Biological Sciences)
Science & Engineering Building Remedial Work:
Housing Maintenance Building
Student Wellness Complex – Phase I
Northeast Connector Road and Lot 34 Upgrade
Hayt Golf Learning Center – Women’s Locker Room & Lounge
3
Download