02-06-2013 Space Committee Project Update

advertisement
University of North Florida
ADMINISTRATION & FINANCE
Departmental Status Report for Space Committee Meeting
Director:
Department:
Date:
Zak Ovadia
Campus Planning Design & Construction
February 6th, 2013
I. SELECTED ACTIVE PROJECTS
NOTE ALL SCHEDULES ARE TENTATIVE
1.
Programming for Buildings 50, 3 and 4: This project entails the programming, of three
buildings for backfilling and restacking once the Biology Department moves to the new
Biological Sciences Building in 2012 as well as various renovations in Bldgs. 3, 4, and
50..
Tentative Schedule:
Consultant Selection
Complete
Programming
March 2011
Changes from last month:
This project is complete and
will be removed from the
report.
2.
Interfaith Sanctuary: Design and Construction of sanctuary building of approximately
6,500 square feet to serve as a venue for group events.
Tentative Schedule:
Feasibility Study of Sites underway
Programming
TBD
Conceptual Permitting TBD
RFQ for Consultants TBD
Short-listing & Interv. TBD
Program Verification TBD
Schematic Design
TBD
Design Development TBD
Construction Docs.
TBD
Construction
TBD
Changes from last month:
President’s Mandatory Briefing
was held November 1.
Submissions received
December 4th. Committee met
on January 7th to shortlist –
three selected. Committee
convenes on February 8th to
discuss the three before
inviting consultants.
3.
Religious Centers: Engage Civil Engineer to provide a feasibility study and an order of
magnitude cost for providing utility services to a grouping of four buildings.
Tentative Schedule:
ON HOLD.
4.
New Food Service Facility and General Purpose Building: Design and Construction
of a replacement food service facility to replace Osprey Café. Preliminary needs call for
a three or four-story building.
Zak Ovadia
1
Tentative Schedule:
Programming
Conceptual Permitting
RFQ for Consultants
Short-listing & Interv.
Program Verification
Schematic Design
Design Development
Select CM
Construction Docs.
Demolition
Construction
Changes from last month:
5.
Development of Greek Village: This project entails the programming and completing a
feasibility study to develop 250-bed a Greek Village at Tech. Park
Tentative Schedule:
Consultant Selection
RFQ Released
Consultant Selection
TBD
Programming
Feasibility Study
Report Due
Changes from last month:
6.
August 2010
TBD
Complete
Complete
Complete
Complete
Complete
Complete
Complete
Complete
Complete
This project is now complete
and will be removed from the
report.
TBD
TBD
December 2012
Committee meetings have
been taking place regularly.
Draft financial analysis was
reviewed on November 27th.
Final report is scheduled to be
unveiled February 5th, 2013.
New Housing Clubhouse Building: Design and Construction of a new Clubhouse to
service the housing units in the core campus. Program calls for a 15,000 GSF building to
contain a Convenience Store/Grill, a Multi-purpose Room, a Laundry facility for 450
students, an R/A Graphics Room, a Game Room and a Mail Distribution area for 2,900
students.
Tentative Schedule:
Programming
Complete
RFQ for Consultants Complete
Short-listing & Interv. Complete
Program Verification Complete
Schematic Design
August 2012
Design Development October 2012
Select CM
January 2013
Construction Docs.
Marchr 2013
Construction
April 2013 to July 2014.
Changes from last month:
Project is currently in the
Design Development Phase.
CM firm AJAX was selected
for this project.
Completed Projects:
Zak Ovadia
2







Zak Ovadia
COE&HS Building with DRC, VCS, VCL and OCT
Science and Humanities Building (Biological Sciences)
Science & Engineering Building Remedial Work:
Housing Maintenance Building
Student Wellness Complex – Phase I
Northeast Connector Road and Lot 34 Upgrade
Hayt Golf Learning Center – Women’s Locker Room & Lounge