University of North Florida ADMINISTRATION & FINANCE Departmental Status Report for Space Committee Meeting Director: Department: Date: Zak Ovadia Campus Planning Design & Construction February 6th, 2013 I. SELECTED ACTIVE PROJECTS NOTE ALL SCHEDULES ARE TENTATIVE 1. Programming for Buildings 50, 3 and 4: This project entails the programming, of three buildings for backfilling and restacking once the Biology Department moves to the new Biological Sciences Building in 2012 as well as various renovations in Bldgs. 3, 4, and 50.. Tentative Schedule: Consultant Selection Complete Programming March 2011 Changes from last month: This project is complete and will be removed from the report. 2. Interfaith Sanctuary: Design and Construction of sanctuary building of approximately 6,500 square feet to serve as a venue for group events. Tentative Schedule: Feasibility Study of Sites underway Programming TBD Conceptual Permitting TBD RFQ for Consultants TBD Short-listing & Interv. TBD Program Verification TBD Schematic Design TBD Design Development TBD Construction Docs. TBD Construction TBD Changes from last month: President’s Mandatory Briefing was held November 1. Submissions received December 4th. Committee met on January 7th to shortlist – three selected. Committee convenes on February 8th to discuss the three before inviting consultants. 3. Religious Centers: Engage Civil Engineer to provide a feasibility study and an order of magnitude cost for providing utility services to a grouping of four buildings. Tentative Schedule: ON HOLD. 4. New Food Service Facility and General Purpose Building: Design and Construction of a replacement food service facility to replace Osprey Café. Preliminary needs call for a three or four-story building. Zak Ovadia 1 Tentative Schedule: Programming Conceptual Permitting RFQ for Consultants Short-listing & Interv. Program Verification Schematic Design Design Development Select CM Construction Docs. Demolition Construction Changes from last month: 5. Development of Greek Village: This project entails the programming and completing a feasibility study to develop 250-bed a Greek Village at Tech. Park Tentative Schedule: Consultant Selection RFQ Released Consultant Selection TBD Programming Feasibility Study Report Due Changes from last month: 6. August 2010 TBD Complete Complete Complete Complete Complete Complete Complete Complete Complete This project is now complete and will be removed from the report. TBD TBD December 2012 Committee meetings have been taking place regularly. Draft financial analysis was reviewed on November 27th. Final report is scheduled to be unveiled February 5th, 2013. New Housing Clubhouse Building: Design and Construction of a new Clubhouse to service the housing units in the core campus. Program calls for a 15,000 GSF building to contain a Convenience Store/Grill, a Multi-purpose Room, a Laundry facility for 450 students, an R/A Graphics Room, a Game Room and a Mail Distribution area for 2,900 students. Tentative Schedule: Programming Complete RFQ for Consultants Complete Short-listing & Interv. Complete Program Verification Complete Schematic Design August 2012 Design Development October 2012 Select CM January 2013 Construction Docs. Marchr 2013 Construction April 2013 to July 2014. Changes from last month: Project is currently in the Design Development Phase. CM firm AJAX was selected for this project. Completed Projects: Zak Ovadia 2 Zak Ovadia COE&HS Building with DRC, VCS, VCL and OCT Science and Humanities Building (Biological Sciences) Science & Engineering Building Remedial Work: Housing Maintenance Building Student Wellness Complex – Phase I Northeast Connector Road and Lot 34 Upgrade Hayt Golf Learning Center – Women’s Locker Room & Lounge 3