University of North Florida ADMINISTRATION & FINANCE Departmental Status Report for Space Committee Meeting Director: Department: Date: Zak Ovadia Campus Planning Design & Construction November 04, 2015 SELECTED ACTIVE PROJECTS NOTE ALL SCHEDULES ARE TENTATIVE 1. Field House for Basketball: Design and construction of basketball courts and general extensive renovations to the Aquatic Center to eliminate the pool. Tentative Schedule: Programming RFQ for Consultants Short-listing & Interv. Program Verification Schematic Design Design Development Select CM Construction Docs. Construction Changes from last month: TBD TBD November 2013 December 2013 February 2014 February 2014 March 2014 Complete Complete This project is now complete and is being used. Will be removed from the list. 2. Arena Embellishment Feasibility Study: The project calls for Victus Advisors to conduct a market analysis to see if there is sufficient demand for improving the facility. HKS Architects will use the market analysis to generate concepts for review with stake-holders. Tentative Schedule: Market Analysis Schematic Design Changes from last month: July 2015 October 2015 Conference was held on October for an update from consultants on progress. Next meeting scheduled for Tuesday November 3rd. 3. Skinner-Jones Hall: Programming and Schematic Design: Programming, Schematic Design, feasibility study to re-purpose this building. Program will other buildings having related departments (Math, Engineering, Health, etc). Tentative Schedule: Zak Ovadia RFQ for Consultants August 2013 Short List for interview September 2013 Programming February 2014 Schematic Design March 2015 Design Development Sept. 2015 1 Select CM Construction Docs. Construction Changes from last month: July 2015 February 2015 Phase I Utilities in Dec. 2015 Phase II Bldg. 4 and Addition Spring 2016. Phase III Bldg. 3 TBD A meeting with Administration, Provost and Deans was held on Tuesday the 20th of October to review phasing plans for the building and need to relocate departments to other locations. It appears that there is a plan in place that suits the colleges and allows them to continue offering courses. 4. Bldg 9 – Second Floor: Project is to create 2 temporary spaces for the Theater Group practice as well as for Nofa Dixon to layout the tiles for the next project. CPDC met with Jay Coleman in the space on August 4 to discuss scope of project. Changes from last month: Construction documents are out to bid. Bids received on October 30. 5. Athletic and Recreation Facilities: This project includes Soccer Fields, Tennis Courts, Sand Volleyball courts and a Javelin Throw. Consultants were advised that the project is in abeyance until UNF receives donor funds. Comprehensive Total Project Cost with phases was delivered to Shari Shuman. 6. Department of Sculpture Move to Building 6: Campus Planning has reviewed the bids. After extensive discussions with bidders, this contract was awarded to Warden Construction. 7. Master Plan 2015-20: The second round of Focus Group meetings were held on September 30 and October 1. Consultant finalizing reports. Campus Planning is arranging for Public Hearings before submitting the Master Plan to various agencies for review 8. Office of Academic Testing: This project entails the feasibility of relocating the OAT to Hicks Hall Work on preliminary layout documents completed. An Order of Magnitude Cost Estimate was received from Elkins Constructors. Total Project Cost worksheet was forwarded to VP for review with Department and potential Zak Ovadia 2 donors. Estimated Construction Cost of $688,464. No change this period. 9. Building 2 Interfaith Ministry Office Conversion: This project entails the feasibility of renovation space previously occupied by Academic Testing to house the Interfaith Ministry. A meeting was held with the requesting group and the consultants on September 29 to define the scope of the project. Consultant is working on cost estimate. 10. Student Union Renovations to Back Dining Area on Second Floor: This project entails the feasibility of renovation space previously designated as for dining. Student Government and Chartwells are conducting a survey to see what the students prefer to see in that space. 11. New NCAA Outdoor Swimming Pool: Design and Construction of an outdoor Olympic-size pool and diving pool north of the existing Student Wellness Complex. Tentative Schedule: Programming Complete RFQ for Consultants Complete Program Verification Complete Schematic Design Complete Design Development September 2015 Select CM TBD Construction Docs. TBD Construction TBD Changes from last month: Schematic Design package distributed to stakeholders in December 2014. Administration requested that the consultant reduce the scope of the project to just the pool and the pump house and complete the Design Development phase so we can get a cost estimate from a CM. Consultant’s fee proposal was revised and is now acceptable. Contract document is in the works. Zak Ovadia 3