09-05-2012 Space Update

advertisement
University of North Florida
ADMINISTRATION & FINANCE
Departmental Status Report for Space Committee Meeting
Director:
Department:
Date:
Zak Ovadia
Campus Planning Design & Construction
September 5th, 2012
I. SELECTED ACTIVE PROJECTS
NOTE ALL SCHEDULES ARE TENTATIVE
1.
Student Wellness & Sports Education Center Phase I: This project entails the
programming, design and construction of a Student Wellness and Sports Education
Center (Est. 116,000 GSF). Phase I in roughly 65,000 GSF.
Tentative Schedule:
Consultant Selection
Complete
Programming
Complete
RFQ for Design
Complete
Consultant Selection
Complete
Program Verification Complete
Schematic Design
Complete
Design Development Complete
Select CM
Complete
Const. Documents
Complete
Construction
Complete
Changes from last month:
Facility is complete and
operational. Building is
undergoing Post-occupancy
adjustments.
2.
Hayt Golf Learning Center – Women’s Locker Room & Lounge: Renovations to
two of the laboratories vacated by Biology to create a Lounge/Locker/Shower Rooms for
the Women’s Golf Team to address Title IX requirements.
Tentative Schedule:
Consultant Selection
Complete
Programming
Complete
Schematic Design
Complete
Design Development Complete
Const. Documents
Complete
Select GC
Complete
Construction
August 2012 to October 2012
Changes from last month:
Contract awarded to Warden
Construction. Expected
completion by the middle of
October.
Zak Ovadia
1
3.
Programming for Buildings 50, 3 and 4: This project entails the programming, of three
buildings for backfilling and restacking once the Biology Department moves to the new
Biological Sciences Building in 2012 as well as various renovations in Bldgs. 3, 4, and
50..
Tentative Schedule:
Consultant Selection
Complete
Programming
March 2011
Changes from last month:
Phys. Fac. has engaged an
HVAC consultant to look at
air balancing for Bldg. 3.
 Work at Bldg. 4 First
Floor started. Expected
completion end of
September.
 Estimate to prepare Bldg.
3 for Math was sent to
Barbara Hetrick.
 Electrical Work started to
relocate the CCEC
Machine Shop in Bldg. 50
4.
Northeast Connector Road and Lot 34 Upgrade:
Design and Build a new road connecting the Loop Road to the Round-about at Lot 18 and
paving of Lot 34 behind the Arena...
Tentative Schedule:
Consultant Selection
Complete
Programming
N/A
Program Verification N/A
Schematic Design
June 2011
Design Development July 2011
Const. Documents
September 2011
Select CM
Auld & White
Construction
Complete
Changes from last month:
Project is complete and
shuttle busses are running.
Waiting for delivery of 2
shelters.
Zak Ovadia
2
5.
Interfaith Sanctuary: Design and Construction of sanctuary building of approximately
6,500 square feet to serve as a venue for group events.
Tentative Schedule:
Feasibility Study of Sites underway
Programming
TBD
Conceptual Permitting TBD
RFQ for Consultants TBD
Short-listing & Interv. TBD
Program Verification TBD
Schematic Design
TBD
Design Development TBD
Construction Docs.
TBD
Construction
TBD
Changes from last month:
Information on utility costs
was forwarded to Shuman.
President has agreed to
proceed with a Design
Competition.
 Rules of the
Competition document
was distributed to the
committee for input.
6.
Religious Center at Holzendorf: Engage Civil Engineer to provide a feasibility study
and an order of magnitude cost for providing utility services to a grouping of four
buildings.
Tentative Schedule:
Feasibility Study of Sites underway
Programming
TBD
Conceptual Permitting TBD
RFQ for Consultants TBD
Short-listing & Interv. TBD
Program Verification TBD
Schematic Design
TBD
Design Development TBD
Construction Docs.
TBD
Construction
TBD
Changes from last month:
A report on utilities costs was
forwarded to Shuman.
Zak Ovadia
3
7.
New Food Service Facility and General Purpose Building: Design and Construction
of a replacement food service facility to replace Osprey Café. Preliminary needs call for
a three or four-story building.
Tentative Schedule:
Programming
August 2010
Conceptual Permitting TBD
RFQ for Consultants Completed
Short-listing & Interv. Completed
Program Verification Completed
Schematic Design
February, 2011
Design Development March 2011 – April 2011
Select CM
Complete
Construction Docs.
May 2011 – August 2011
Demolition
May 2011
Construction
July 2011 to November 2012
Changes from last month:
Osprey Dining facility was
completed and operational on
schedule. Work is now
concentrated on 3rd and 4th
floors.
8.
Development of Greek Village: This project entails the programming and completing a
feasibility study to develop 250-bed a Greek Village at Tech. Park
Tentative Schedule:
Consultant Selection
RFQ Released
Consultant Selection
TBD
Programming
Feasibility Study
Report Due
Changes from last month:
Zak Ovadia
TBD
TBD
TBD
Treanor Architects was
selected. First meeting was
held on July 30. The second
meeting on August 22nd
included an evening session
with Chapter Presidents.
4
9.
New Housing Clubhouse Building: Design and Construction of a new Clubhouse to
service the housing units in the core campus. Program calls for a 15,000 GSF building to
contain a Convenience Store/Grill, a Multi-purpose Room, a Laundry facility for 450
students, an R/A Graphics Room, a Game Room and a Mail Distribution area for 2,900
students.
Tentative Schedule:
Programming
Complete
RFQ for Consultants Complete
Short-listing & Interv. Complete
Program Verification Complete
Schematic Design
August 2012
Design Development September 2012
Select CM
October 2012
Construction Docs.
December 2012
Construction
April 2013
Changes from last month:
A meeting was held on August
23rd to finalize the floor plan
and the elevations. There is
currently a discussion on costs
and availability of funds.
Completed Projects:




Zak Ovadia
COE&HS Building with DRC, VCS, VCL and OCT
Science and Humanities Building (Biological Sciences)
Science & Engineering Building Remedial Work:
Housing Maintenance Building