Space Committee Meeting MINUTES April 2, 2014

advertisement
Space Committee Meeting
MINUTES
April 2, 2014
Members Present:
Shari Shuman, Ann McCullen, Jay Coleman, Mauricio Gonzalez, Paul Mosley
Michael Kuczak, Joseph Turner
Support Staff Present: Zak Ovadia, Dan Endicott, John Hale, Elizabeth Jones, Everett Malcom,
Michael McGuire, Mary Mory, Tony Stevens, Angela Rivera
1.
Project Timelines
2.
Housing Clubhouse
- The finishes are going up. Substantial completion is scheduled for mid-April. A summer
B opening is currently planned.
3.
Interfaith Chapel at the Sanctuary/Student Assembly Center
- A Technical Review meeting of the drawings was held on March 13th. The drawings
have been revised and another meeting is tentatively scheduled with the committee on
April 10th.
- Some departments will need to move items being stored on the property before
construction begins which may not occur for two years.
4.
Skinner-Jones Halls North and South
- The focus group meetings have concluded and the consultant has provided bubble
diagrams. Both buildings are being considered as one project for the programming
phase.
5.
Aquatic Center Re-Purposing
- Eleven submissions were received from Construction Management Services. Three
companies have been selected for interviews. The development drawings are at 100%.
There will be a meeting on April 9th to review the plans.
6.
Space in Building 10 for UPD Substation
- UPD has decided not to use the space previously offered in Building 10. They
will use other common areas on campus.
7.
Elevated Parking Deck
- A recommendation was approved for Perry McCall as the construction manager.
One meeting has been held and the GMP is expected at the end of the month.
- A January opening is expected.
- The bat house near the garage will need to be relocated.
- The number of the new parking garage will be Parking Garage 44-A.
8.
New Aquatic Center
- A kick off meeting was held in February. A fee proposal was received from the
consultant April 1st and is currently being reviewed.
9.
Library Learning Commons
- Meetings with Library and ITS personnel have resulted in a consensus for the
location of the Help Desk inside the Library. Meetings to plan flexible learning
-
spaces are being arranged with Steelcase and Herman Miller within the next 2
weeks.
Joe Turner requested student involvement with the planning process. Joe was
directed to contact Len Roberson.
10.
Physical Facilities Warehouse
- John Hale updated the committee on the renovation plans for the warehouse.
Batson Cook received sub-bids which exceeded the $2M allowed under the
contract. Physical Facilities will now procure the work by prequalifying
contractors through an RFQ process and once responses have been received, they
will be short-listed. Those selected will be able to bid on the project. Responses
are due May 1st. Bids should be expected in June with substantial completion
being delayed until November. The academic units have been notified of the
delay.
11.
Building 3, rooms 1301, 1302, 1321 and 1322
- After walking through the area, it was decided that the space each group needs
does not interfere with each other’s needs. A permanent wall funded by Student
Affairs will need to be constructed.
12.
Gender Neutral Restrooms
- After reviewing other buildings, Zak Ovadia has identified additional buildings
which could benefit from having gender neutral restroom.
13.
Storage for Drumline
- Modifiable storage buildings were discussed as a possible storage solution.
Queries made by Zak Ovadia resulted in an approximate cost of $25,000 per 12½’
x20’ building. Discussions will continue.
- Dan Endicott noted that any storage unit placed inside the building would need to
be approved by the Fire Marshal.
- The decision was made to leave the drumline in the stadium for now.
Download