Space Committee Meeting MINUTES January 7, 2015 Members Present: Shari Shuman, Jay Coleman, Tom Serwatka, Joe Turner, Paul Mosley Support Staff Present: Zak Ovadia, Albert Colom, Dan Endicott, Wallace Harris, Mary Mory, Elizabeth Jones, Mike McGuire, Lance Taylor, Dawn Knipe, Vince Smyth 1. Project Timelines - Student Assembly Building A meeting was held with consultants before Christmas. Construction documents are 85% complete and there are no issues that need to be addressed. - Athletics and Recreation Facilities JBC was asked to perform a feasibility study for adding 2 soccer fields, tennis courts, 5 sand volleyball courts and a javelin throw area. A cost analysis was submitted in December. 2. Skinner-Jones Halls North and South - The consultant provided two options for this project to include Building 50. - The preferred proposal leaves Chemistry and Physics in Building 50 and move Engineering to Building 4 - Building 3 will remain essentially the same. Building 4 will have an addition built. - The consultant has been asked to provide a new floor plan design which is expected in a week. - Additional fume hoods and vents will be added to Building 50. 3. Fieldhouse (Aquatic Center Re-Purposing) - Construction was started on the inside on December 1st. All of the demolition is complete and the pool is currently being filled in with dirt. - The project is currently on schedule with no issues. - The anticipated completion date is September 2015. 4. Elevated Parking Deck - This project was completed in mid-December and it is currently being used. 5. New Aquatic Center - The consultant presented the schematic design on December 4th to the stake holders. - The cost is still an issue and the consultant has been charged with obtaining reliable cost estimates from contractors 6. Library Learning Commons - The second floor carpeting is in progress. The first floor carpeting has been completed. Electrical and data cabling is underway. Some furniture has been delivered. - Completion is scheduled for the end of March 2015. 7. Campus Maintenance Facility - All of the staff and equipment have been moved in and the building is being used. 8. Math Emporium - Construction documents have been completed. - Surplus tables and chairs have been identified for the space when it is ready. - The Math department would like the space ready by Fall 2015. 9. Arena Bridge Enhancement - Zak Ovadia will give a presentation of the concept for the Arena bridge enhancement at the next meeting. 10. Building 6 (The Annex) - Many of the sculpture pieces of equipment have been moved to the building but areas for an induction furnace, wood collection system and a welding booth exhaust system need to be designed and implemented. - The Mechanical Engineering students have moved in. - The parking spaces in the back of the building will be used largely for deliveries.