Space Committee Meeting MINUTES October 6, 2010 1. Project Timelines - Zak Ovadia gave an overview of the current planned projects on campus. - Proceeding with a program for a new dining facility. 2. JJ Daniel Hall (Building 1) - The last phase, which is the President’s Suite, which will start on October 8. The President’s Conference Room will be relocated to the first floor during renovation. - The Graduate School will be moving in on October 14. 3. Student Wellness and Sports Education - Fencing will be put up the last week of December with demolition of the current Dottie Dorian Center in January. 4. Science and Humanities Building - Under construction – currently framing the second floor. A bid package for the building envelope will be issued soon. - Project is over budget but confident adjustments can be made to meet the budget. 5. Education Building: DRC, OCT, Veterans Services and Leadership Institute Offices - 50% construction documents are currently being reviewed. - There were 28 submissions for Construction Manager. The committee will meet on October 15 and shortlist the firms. 6. Science & Engineering Remedial Work - The GMP was received at $3.2M. - The bid package to re-roof the building went out this week. - Work should start in mid-November. There should be no significant impact on inside activities. - Zak Ovadia will forward the renovation schedule to Deb Kaye in 2 weeks to determine any issues with classrooms. 7. Building 9 – 2nd Floor – History - General Counsel is currently reviewing an amendment from Elkins. - Mauricio Gonzalez will follow up on a dedicated classroom space requested by the ROTC. 8. Art & Design Building Program - A programming meeting will be scheduled within 2 weeks. 9. Environmental Center – Space in Building 1 - The Environmental Center has requested space in Building 1 (the former IR space on the 2nd floor). - Mark Workman motioned to approve the request. Lance Taylor seconded the motion – motion was approved. 10. Civic Council – UNF Hall - The Jacksonville Civic Council has requested space for one of their members, Don Shea, for two offices. He is being paid through a grant with ORSP. - Len Roberson motioned to approve 2 offices in the former Graduate School space in UNF Hall with a second by Mauricio Gonzalez. The motion passed. Completed Projects 1. Disability Resource Center - Expansion into CIRT Pending Issues 1. 2. 3. 4. 5. 6. 7. Carts and Cart Storage Expansion of Golfplex to Accommodate Women’s Locker/Lounge Area Building Construction Management – Request for New Building Room Space for OLLIE (Continuing Education) Sanctuary Building 10- CCB Expansion Campus Wide Master Plan