Space Committee Meeting Minutes March 5, 2014 President’s Conference Room Members Present: Lance Taylor, Paul Mosley, Ann McCullen, Jay Coleman, Tom Serwatka (by phone) Support Staff Present: Zak Ovadia, John Yancey, Dan Endicott, John Hale, Mike McGuire, Mary Mory 1. Project Timelines 2. Housing Clubhouse - No issues and the project in on schedule. 3. Interfaith Chapel at the Sanctuary/Student Assembly Center - A technical review meeting was held. Another meeting will be held on March 13. The 50% construction documents are expected at that time. 4. Skinner-Jones Halls North and South - A kick-off meeting was held on January 17th. - Eight focus group meetings have been held and diagrams are currently being drafted. 5. Aquatic Center Re-Purposing - An advertisement for the selection of a construction management firm has been sent out. - The cost estimate is higher than expected. 6. Space in Building 10 for UPD Substation - Everett Malcolm reported that Room 1335 can serve well as a substation if a window can be installed in the door or the door can be replaced with a door with a window at a reasonable cost. - A meeting to determine options is planned for today. 7. Elevated Parking Deck - Perry-McCall has been selected as the construction management firm. - Technical review meetings are in progress. 8. New Aquatic Center - A kick-off meeting was held on February 13th. - Program verification and schematic design are in progress. - A meeting with the consultant is scheduled for next week. 9. Library Learning Commons - Akel Logan & Schafer has met with the interested parties (representatives from the Library, Graduate School and ITS) to determine their needs. - The next meeting is in the process of being scheduled. 10. Physical Facilities Warehouse - The drawings are complete. - The CM is advertising for bids which are due on March 21st. - The GMP is expected by the end of March and, if it is favorable, work will be scheduled. - Completion is expected by the end of July or early August. 11. Building 3, rooms 1301, 1302, 1321 and 1322 - The Honors program would like this space temporarily to create a conference room/meeting area. Student Conduct is also interested in the space. There is a possibility that both departments could use the space. - Discussion is in progress to move the testing center in building 2 to a better location. 12. Gender Neutral Restrooms - Campus Planning provided a list of gender neutral restrooms now available on campus. Student Affairs has requested that all renovations/new construction should include gender neutral restrooms in all buildings. Zak Ovadia noted that the building code now requires all new buildings to provide for gender neutral restrooms. They have also requested that existing buildings that do not have gender neutral restrooms be reviewed to see if there are restrooms that can be changed to gender neutral restrooms. 13. Storage for Drumline - The UNF Drumline has been storing their equipment in a ticket box office at Hodges Stadium for about 7 years and has recently been told it needs to be moved due to the renovation plans of the Athletics department. A new storage area needs to be identified for the Drumline, taking into account their location needs, near the stadium. The space also needs to be conditioned and about 200 sf. Zak Ovadia will look into a temporary solution of using a POD on the second floor of the building or somewhere on the grounds near the stadium. Fire Marshal approval would also have to be obtained if it is moved into the building.