04-04-2016 Space Update

advertisement
University of North Florida
ADMINISTRATION & FINANCE
Departmental Status Report for Space Committee Meeting
Director:
Department:
Date:
Zak Ovadia
Campus Planning Design & Construction
April 04, 2016
SELECTED ACTIVE PROJECTS
NOTE ALL SCHEDULES ARE TENTATIVE
1. Arena Embellishment Feasibility Study: The project calls for Victus Advisors to conduct a
market analysis to see if there is sufficient demand for improving the facility. HKS Architects
will use the market analysis to generate concepts. Funding will be provided by donors and
sponsors.
Tentative Schedule:
Market Analysis
July 2015
Schematic Design
October 2015
Changes from last month:
Discussions are being held with
Administration and Finance, Alumni
Enhancement and Athletics to plan the
next steps. No Change.
2. Skinner-Jones Hall: Programming and Schematic Design: Programming, Schematic Design,
feasibility study to re-purpose this building. Program with other buildings having related
departments (Math, Engineering, Health, etc.).
Tentative Schedule:
RFQ for Consultants August 2013
Short List for interview September 2013
Programming
February 2014
Schematic Design
March 2015
Design Development Sept. 2015
Select CM
July 2015
Construction Docs.
February 2015
Construction
Phase I Utilities in Dec. 2015
Phase II Bldg. 4 and Addition Sept.
2016. Phase III Bldg. 3 May 2017
Changes from last month:
Construction Documents being
reviewed at 50% for an updated cost
estimate. Meetings were held with all
user groups to confirm that there are
no major changes contemplated.
3. Department of Sculpture Move to Building 6:
Changes from last month:
This contract was awarded to Warden
Construction. Work on site is
underway. Expected completion of
this phase is the end of March.
4. Master Plan 2015-2025: The Board of Trustees has adopted the Master Plan as presented.
Campus Planning sent a notice to all agencies of that fact.
5. Coggin Student Services in Bldg. 10: The project calls for the repurposing of the rat lab on the
first floor of Bldg. 10 into offices for the Coggin Student Services function.
Tentative Schedule:
Programming
Complete
RFQ for Consultants N/A
Schematic Design
Complete
Design Development Complete
Select CM
Complete
Construction Docs.
February 2016
Construction
April 2016
Changes from last month:
Construction drawings are complete.
Bids were received on March 23 from
4 bidders. Waiting on confirmation of
funding.
6. New NCAA Outdoor Swimming Pool: Design and Construction of an outdoor Olympic-size
pool and diving pool north of the existing Student Wellness Complex.
Tentative Schedule:
Programming
Complete
RFQ for Consultants Complete
Program Verification Complete
Schematic Design
Complete
Design Development September 2015
Select CM
TBD
Construction Docs.
TBD
Construction
TBD
Changes from last month:
Administration and Finance is
analyzing the first contract for
irregularities before reacting to the
new fee proposal. No change this
period.
7. Hodges Stadium Waterproofing Study: Engage a CM and a waterproofing specialist to study
feasible solutions to prevent water intrusion into the finished spaces..
Tentative Schedule:
Programming
TBD
RFQ for Consultants TBD
Program Verification TBD
Schematic Design
TBD
Design Development TBD
Select CM
TBD
Construction Docs.
TBD
Construction
TBD
Changes from last month:
Ajax Construction (CM) was asked to
submit a Pre-construction/Feasibility
analysis fee for consideration by
Administration and Finance. Bids for
the work is anticipated mid-April.
Download