05-11-2016 Space Update

advertisement
University of North Florida
ADMINISTRATION & FINANCE
Departmental Status Report for Space Committee Meeting
Director:
Department:
Date:
Zak Ovadia
Campus Planning Design & Construction
May 11, 2016
SELECTED ACTIVE PROJECTS
NOTE ALL SCHEDULES ARE TENTATIVE
1. Skinner-Jones Hall: Programming and Schematic Design: Programming, Schematic Design,
feasibility study to re-purpose this building. Program with other buildings having related
departments (Math, Engineering, Health, etc.).
Tentative Schedule:
RFQ for Consultants August 2013
Short List for interview September 2013
Programming
February 2014
Schematic Design
March 2015
Design Development Sept. 2015
Select CM
July 2015
Construction Docs.
February 2015
Construction
Phase I Utilities in Dec. 2015
Phase II Bldg. 4 and Addition Sept.
2016. Phase III Bldg. 3 May 2017
Changes from last month:
Construction Documents were
reviewed at 50% for an updated cost
estimate. Meetings were held with all
user groups to confirm that there are no
major changes contemplated. Current
construction estimate is below the $25
Million limit.
2. Department of Sculpture Move to Building 6:
Changes from last month:
Project Completed
3. Coggin Student Services in Bldg. 10: The project calls for the repurposing of the rat lab on the
first floor of Bldg. 10 into offices for the Coggin Student Services function.
Tentative Schedule:
Programming
Complete
RFQ for Consultants N/A
Schematic Design
Complete
Design Development Complete
Select CM
Complete
Construction Docs.
February 2016
Construction
April 2016
Changes from last month:
Construction drawings are complete.
Bids were received on March 23 from
4 bidders. Funding availability was
confirmed and PO has been issued.
Construction will need to be
completed before the Fall Semester.
4. New NCAA Outdoor Swimming Pool: Design and Construction of an outdoor Olympic-size
pool and diving pool north of the existing Student Wellness Complex.
Tentative Schedule:
Programming
Complete
RFQ for Consultants Complete
Program Verification Complete
Schematic Design
Complete
Design Development September 2015
Select CM
TBD
Construction Docs.
TBD
Construction
TBD
Changes from last month:
Administration and Finance is analyzing
the first contract for irregularities before
reacting to the new fee proposal. No
change this period.
5. Hodges Stadium Waterproofing Study: Engage a CM and a waterproofing specialist to study
feasible solutions to prevent water intrusion into the finished spaces..
Tentative Schedule:
Construction
May – July 2016
Changes from last month:
Ajax Construction mobilized May 2nd.
Work will continue through July.
6. Arena Bridge Demolition: This project entails the demolition of the damaged bridge between
the Arena and the Parking structure. Demolition will include the ceremonial stairs at the plaza.
Changes from last month:
A settlement was reached with the
insurance carrier. Elkins GMP
proposal has been accepted and work
will start June 11th. Completion is
scheduled for August 4th.