University of North Florida ADMINISTRATION & FINANCE Departmental Status Report for Space Committee Meeting Director: Department: Date: Zak Ovadia Campus Planning Design & Construction June 04, 2014 I. SELECTED ACTIVE PROJECTS NOTE ALL SCHEDULES ARE TENTATIVE 1. Student Assembly Building (Sanctuary): Design and Construction of sanctuary building of approximately 6,500 square feet to serve as a venue for group events. Tentative Schedule: Programming TBD Conceptual Permitting TBD RFQ for Consultants Complete Short-listing & Interv. Complete Program Verification Complete Schematic Design August 2013 Design Development October 2013 Construction Docs. February 2014 Construction TBD Changes from last month: The Project Committee met on April 8 for final review. The technical committee met with George Androuin and his staff about lighting control. All seems to be acceptable. Construction Documents are about 40% complete. 2. New Housing Clubhouse Building: Design and Construction of a new Clubhouse to service the housing units in the core campus. Program calls for a 15,000 GSF building to contain a Convenience Store/Grill, a Multi-purpose Room, a Laundry facility for 450 students, an R/A Graphics Room, a Game Room and a Mail Distribution area for 2,900 students. Tentative Schedule: Programming Complete RFQ for Consultants Complete Short-listing & Interv. Complete Program Verification Complete Schematic Design August 2012 Design Development October 2012 Select CM January 2013 Construction Docs. March 2013 Construction May 2013 to July 2014. Changes from last month: Substantial Completion was achieved on April 18. Furniture is being delivered and set up. Zak Ovadia 1 3. Elevated Parking Deck: Feasibility, Design and Construction of a new elevated parking deck over part of an existing lot south of the FAC. Consultant tested the feasibility of adding additional parking levels to tie to the existing Fine Arts Garage. Program calls for a minimum of 170 stalls to serve the residential population. Currently the design provides over 550 stalls. Tentative Schedule: Programming August 2013 RFQ for Consultants Completed Short-listing & Interv. Completed Program Verification Completed Schematic Design Completed Design Development October 2013 Select CM January 2014 Construction Docs. March 2014 Construction Must be occupiable by January 2015 Changes from last month: Perry McCall submitted a GMP which was accepted. Mobilization has started. . 6. Aquatic Center Re-purposing for Basketball: Design and construction of basketball courts and general extensive renovations to the Aquatic Center to eliminate the pool. Tentative Schedule: Programming TBD RFQ for Consultants TBD Short-listing & Interv. November 2013 Program Verification December 2013 Schematic Design February 2014 Design Development February 2014 Select CM March 2014 Construction Docs. TBD Construction TBD Changes from last month: Three firms were invited to interview (Danis, Barton Malow, and Clancy & Theys). President endorsed the recommendation enter into agreement with Barton Malow. Zak Ovadia 2 7. New Outdoor Swimming Pool: Design and Construction of an outdoor Olympic-size pool and diving pool north of the existing Student Wellness Complex. Tentative Schedule: Programming TBD RFQ for Consultants TBD Short-listing & Interv. TBD Program Verification TBD Schematic Design TBD Design Development TBD Select CM TBD Construction Docs. TBD Construction TBD Changes from last month: A revised fee proposal was reviewed and accepted. Programming meeting with users is scheduled for June 4th. 8. Skinner-Jones Hall NORTH: Programming and Schematic Design: Programming, Schematic Design, Feasibility Study to re-purpose this building. Program will include Skinner-Jones Hall SOUTH as well as other buildings having related departments (Math, Engineering, Health, etc). Tentative Schedule: RFQ for Consultants August 2013 Short List for interview September 2013 Programming February 2014 Schematic Design TBD Design Development TBD Select CM TBD Construction Docs. TBD Construction TBD Changes from last month: Meetings with Focus Groups completed. Meeting with Steering Committee completed on May 2nd. Mtg. with Administration was held on May 16 to receive clearer directions on strategic plans for the buildings. Prime consultant was requested to start with the preliminary schematic diagrams for discussion with the focus groups. Zak Ovadia 3 7. Library Learning Commons: Reconfigure First and Second Floors to create a studentcentric learning commons. Co-locate the Help Desk from Bldg. 15, and remodel entry lobby. Tentative Schedule: Programming February 2014 Program Verification March 2014 Schematic Design March 2014 Design Development April 2014 Construction Docs. TBD Construction TBD Changes from last month: The committee met with Steelcase in late April and with Herman Miller in early May. Both vendors are preparing a furniture layout, scope of service and fee proposals. Committee members assembling Order of Magnitude Cost for the Project. 9. Religious Centers: Engage Civil Engineer to provide a feasibility study and an order of magnitude cost for providing utility services to a grouping of four buildings. Tentative Schedule: NO CHANGE. 10. Development of Greek Village: This project entails the programming and completing a feasibility study to develop 250-bed a Greek Village at Tech. Park Tentative Schedule: NO CHANGE. Zak Ovadia 4