Director:
Department:
Date:
University of North Florida
ADMINISTRATION & FINANCE
Departmental Status Report for Space Committee Meeting
Zak Ovadia
Campus Planning Design & Construction
February 03, 2016
SELECTED ACTIVE PROJECTS
NOTE ALL SCHEDULES ARE TENTATIVE
1.
Arena Embellishment Feasibility Study: The project calls for Victus Advisors to conduct a market analysis to see if there is sufficient demand for improving the facility. HKS Architects will use the market analysis to generate concepts. Funding will be provided by donors and sponsors.
Tentative Schedule: Market Analysis
Schematic Design
Changes from last month:
July 2015
October 2015
Meetings were held on Tuesday
November 3 rd and December 15 to review findings and conceptual schematics . Discussions are being held with Administration and Finance,
Alumni Enhancement and Athletics to plan the next steps.
2.
Skinner-Jones Hall: Programming and Schematic Design: Programming, Schematic Design, feasibility study to re-purpose this building. Program with other buildings having related departments (Math, Engineering, Health, etc).
Tentative Schedule: RFQ for Consultants August 2013
Short List for interview September 2013
Programming February 2014
Schematic Design
Select CM
Construction
March 2015
Design Development Sept. 2015
July 2015
Construction Docs. February 2015
Phase I Utilities in Dec. 2015
Phase II Bldg. 4 and Addition Sept.
Changes from last month:
2016. Phase III Bldg. 3 May 2017
Bids were received by Ajax for the electrical infrastructure work over the winter holidays. Contract awarded and this small phase was completed during the winter holidays.
GMP estimate from AJAX shows a shortfall of about $1.0 Million to
complete all phases. Estimating continues to reduce that shortfall.
3.
Bldg 9 – Second Floor: Project is to create space for the Theater Group to practice.
Changes from last month: Bids received on October 30. Waiting for approval from AA to award the contract.
Academic Affairs has requested an Order of Magnitude estimate to build the stage.
4.
Athletic and Recreation Facilities: This project includes Soccer Fields, Tennis Courts, Sand
Volleyball courts and a Javelin Throw.
Changes from last month: Consultants were advised that the project is in abeyance until UNF receives donor funds. Comprehensive
Total Project Cost with phases was delivered to Shari Shuman.
Location of
Practice Soccer Field has changed from original location to north of Lot
18.
5.
Department of Sculpture Move to Building 6:
Changes from last month: Campus Planning has reviewed the bids.
After extensive discussions with bidders. This contract was awarded to
Warden Construction. Work on site is scheduled for mid-February.
6.
Master Plan 2015-2025: The second round of Focus Group meetings were held on September
30 and October 1. Consultant finalizing reports. Campus Planning is arranging for Public
Hearings on December 7 followed by various Agencies for review. Request for comments were sent to various public agencies for review of the Master Plan. Three responses were received as of January 20. Campus Planning will follow up with the rest of the agencies starting February 1 st .
7.
Coggin Student Services in Bldg. 10: The project calls for the repurposing of the rat lab on the first floor of Bldg. 10 into offices for the Coggin Student Services function.
Tentative Schedule: Programming
RFQ for Consultants
Complete
N/A
Schematic Design
Design Development
Select CM
Construction Docs.
Complete
Complete
January 2016
January 2016
Changes from last month:
Construction February 2016
Advanced Schematic Drawings were reviewed with the users on November
23. No changes to the concept were required. Consultant is now into the
Construction Document Phase.
8.
Office of Academic Testing: This project entails the feasibility of relocating the OAT to Hicks
Hall.
Changes from last month: Work on preliminary layout documents completed. An Order of Magnitude
Cost Estimate was received from Elkins
Constructors. Total Project Cost worksheet was forwarded to VP for review with Department and potential donors. Estimated Construction Cost of
$688,464. Refinement of the estimate is being requested to better define where the costs are earmarked.
9.
Building 2 Interfaith Ministry Office Conversion: This project entails the feasibility of renovation space previously occupied by Academic Testing to house the Interfaith Ministry.
Changes from last month: Meetings with users being held for approval of concept before producing
Design Development Documents. No
Change this Period.
10.
New NCAA Outdoor Swimming Pool : Design and Construction of an outdoor Olympic-size pool and diving pool north of the existing Student Wellness Complex.
Tentative Schedule: Programming
RFQ for Consultants
Complete
Complete
Program Verification Complete
Schematic Design Complete
Design Development September 2015
Select CM TBD
Construction Docs.
Construction
Changes from last month:
TBD
TBD
Schematic Design package distributed to stakeholders in December 2014.
Administration requested that the consultant reduce the scope of the project to just the pool and the pump house and complete the Design
Development phase so we can get a cost estimate from a CM. Consultant’s fee proposal was revised and is now acceptable. Contract document is in the works. Contract documents were entered into the iContract system .