07-02-2014 Space Update

advertisement
University of North Florida
ADMINISTRATION & FINANCE
Departmental Status Report for Space Committee Meeting
Director:
Department:
Date:
Zak Ovadia
Campus Planning Design & Construction
July 02, 2014
I. SELECTED ACTIVE PROJECTS
NOTE ALL SCHEDULES ARE TENTATIVE
1.
Student Assembly Building (Sanctuary): Design and Construction of sanctuary
building of approximately 6,500 square feet to serve as a venue for group events.
Tentative Schedule:
Programming
TBD
Conceptual Permitting TBD
RFQ for Consultants Complete
Short-listing & Interv. Complete
Program Verification Complete
Schematic Design
August 2013
Design Development October 2013
Construction Docs.
February 2014
Construction
TBD
Changes from last month:
Construction Documents are
about 50% complete.
2.
Elevated Parking Deck: Feasibility, Design and Construction of a new elevated parking
deck over part of an existing lot south of the FAC. Consultant tested the feasibility of
adding additional parking levels to tie to the existing Fine Arts Garage. Program calls
for a minimum of 170 stalls to serve the residential population. Currently the design
provides over 550 stalls.
Tentative Schedule:
Programming
August 2013
RFQ for Consultants Completed
Short-listing & Interv. Completed
Program Verification Completed
Schematic Design
Completed
Design Development October 2013
Select CM
January 2014
Construction Docs.
March 2014
Construction
Must be occupiable by January
2015
Changes from last month:
Construction continues as
scheduled.
.
Zak Ovadia
1
6. Aquatic Center Re-purposing for Basketball: Design and construction of basketball
courts and general extensive renovations to the Aquatic Center to eliminate the pool.
Tentative Schedule:
Programming
TBD
RFQ for Consultants TBD
Short-listing & Interv. November 2013
Program Verification December 2013
Schematic Design
February 2014
Design Development February 2014
Select CM
March 2014
Construction Docs.
TBD
Construction
TBD
Changes from last month:
Barton Malow is working on
project schedule and will be
working on getting a GMP.
7. New Outdoor Swimming Pool: Design and Construction of an outdoor Olympic-size
pool and diving pool north of the existing Student Wellness Complex.
Tentative Schedule:
Programming
TBD
RFQ for Consultants TBD
Short-listing & Interv. TBD
Program Verification TBD
Schematic Design
TBD
Design Development TBD
Select CM
TBD
Construction Docs.
TBD
Construction
TBD
Changes from last month:
No changes this month.
Programming meeting with
users is scheduled for June
27th.
8. Skinner-Jones Hall NORTH: Programming and Schematic Design: Programming,
Schematic Design, Feasibility Study to re-purpose this building. Program will
include Skinner-Jones Hall SOUTH as well as other buildings having related
departments (Math, Engineering, Health, etc).
Tentative Schedule:
RFQ for Consultants August 2013
Short List for interview September 2013
Programming
February 2014
Schematic Design
TBD
Design Development TBD
Select CM
TBD
Construction Docs.
TBD
Construction
TBD
Changes from last month:
Prime consultant was requested
to start with the preliminary
schematic diagrams for
discussion with the focus
groups. Currently evaluating
Structural Evaluation Report.
Zak Ovadia
2
7. Library Learning Commons: Reconfigure First and Second Floors to create a studentcentric learning commons. Co-locate the Help Desk from Bldg. 15, and remodel
entry lobby.
Tentative Schedule:
Programming
February 2014
Program Verification March 2014
Schematic Design
March 2014
Design Development April 2014
Construction Docs.
underway
Construction
various phases
Changes from last month:
Budget Estimate was
submitted to the
administration and was
accepted. Purdue
representing Steelcase was
selected as the vendor for
furnishings. Elkins
Constructors is now on board.
Met with movers to strategize
various moves. Consultant
working with Electrical
Consultants and Purdue to
analyze impact on existing
power and data outlets. The
plan is to have the Commons
completed by January 2015.
9. Religious Centers: Engage Civil Engineer to provide a feasibility study and an order of
magnitude cost for providing utility services to a grouping of four buildings.
Tentative Schedule:
NO CHANGE.
10. Development of Greek Village: This project entails the programming and completing a
feasibility study to develop 250-bed a Greek Village at Tech. Park
Tentative Schedule:
NO CHANGE.
Zak Ovadia
3