Office of Financial Management Washington State Major Project Status Report: December 31, 2007 Agency Number: Agency: Project Number: Project Title: Bill Reference: 699 Walla Walla Community College 02-2-686, GA Project Number 2002-91 Basic Skills and Computer Lab Addition Chapter 26, Section 779, Laws of 2003 1st Special Session Project Description: Construct approximately 17,322 gross square feet of new space and remodel approximately 19,828 square feet gross at the primary campus in Walla Walla. This will result in approximately 5,100 square feet of computer labs, 2,400 square feet of science lab and related space, 7,250 square feet for Basic Skills instruction, and approximately 9,225 square feet for Art instruction. Project Total Cost: Phase Biennium Appropriation Amount Predesign 2001-2003 E37 36,300 Design 2003-2005 G24 573,000 Construction* 2005-2007 H03 6,569,000 Minor Project* 2005-2007 H37 600,400 Facility Repairs* 2005-2007 H14 683,600 Asbestos and Emergency Repair* 2005-2007 H12 186,000 Local Funds* 2006-2007 147 400,000 Other (Approp/Non Approp) Total 9,048,300 *Estimated Construction Costs including tax and contingency = $7,856,147 *The minor project and HVAC Repairs have been included in the project. Schedule: Predesign Complete Start Design Bid Date Notice to Proceed 50% Complete Substantial Completion Final Acceptance Budget Schedule July 2003 August 2003 August 2005 September 2005 May 2006 January 2007 February 2007 1 Actual/Forecast July 2003 August 2003 June 28, 2006 August 1, 2006 February 2007 July 2007 November 2007 Variance (wks) 0 0 wks 46 wks 46 wks 32 wks 30 wks 39 wks Project Status and discussion of Critical Path for Construction: Project was completed on October 29, 2007. Contract Award History A/E Agreement Original Agreement Amendments Pending Changes Total $ $ $ $ 658,645 205,891 0 864,536 Current Design Contingency $ 0 Construction Contract (excl. sales tax) Bid Award Amount $ 7,233,413 Change Orders $ 45,186 Pending Changes $ 0 Total $ 7,278,599 Current Construction Contingency $ 0 Potential for Project Cost Overruns/Claims Project is completed. Retainage is scheduled for release in January 2008. No claims filed Discussion of Project Quality The project quality was superior. A local Walla Walla Contractor, Opp and Siebold, was the general. Their project management was excellent and they have put together a top notch team of project administrators and sub-contractors. This project was very challenging due to most of the activity going on in close proximity of classroom, laboratory, and office space. Job site activity and coordination with occupants was excellent. Warrantee issues have been taken care of quickly and professionally. Students, staff and faculty love their new space. Project Photographs (Attached) 2 West Entrance Basic Skills Classroom 3 Classroom Art Classroom 4 Hallway and Vending/Recycle Area Offices 5