Office of Financial Management Washington State Major Project Agency Number:

advertisement
Office of Financial Management
Washington State Major Project
Status Report: December 31, 2007
Agency Number:
Agency:
Project Number:
Project Title:
Bill Reference:
699
Walla Walla Community College
04-1-206, 04-1-211, GA Project Number 2003-128
Replace Health Science Facility
Chapter 26, Section 823, Laws of 2003 1st Special Session
Chapter 488, Section 802, Laws of 2005, Regular Session
Project Description:
Construct approximately 36,000 gross square feet of new space to replace current Health Science
and Performing Arts space. Current spaces were constructed in 1976 and 1977 as temporary
spaces, and no longer meet programmatic needs of health science, allied health or performing arts
programs.
Project Total Cost:
Phase
Predesign
Design
Construction*
Other (Approp/Non
Approp) Local Funds
COP Authority for land acquisition and
Construction
Private Funds
Other: 0.8% Sales Tax Grant (Port)
Total
Biennium
Appropriation
Amount
2003-2005
2003-2005
G66
G66
617,294
6,643,476
2005-2007
147
1,600,000
2005-2007
147
1,065,000
2005-2007
400,000
100,000
10,425,770
Schedule:
Predesign Complete
Start Design
Bid Date
Notice to Proceed
50% Complete
Substantial Completion
Final Acceptance
Budget Schedule
July 2002
August 2002
June 2003
July 2003
July 2004
July 2005
September 2005
1
Actual/Forecast
July 2002
August 2002
December 2005
March 2006
October 2006
June 2007
November 2007
Variance (wks)
0
0 wks
120 wks
132 wks
120 wks
100 wks
110 wks
Project Status and discussion of Critical Path for Construction:
Project was completed on September 10, 2007, and the building was dedicated on October 12,
2007.
Contract Award History
A/E Agreement
Original Agreement
Amendments
Pending Changes
Total
$
$
$
$
522,748.55
195,765.56
0.00
718,514.11
Current Design
Contingency
$
0.00
Construction Contract (excl. sales tax)
Bid Award Amount $ 8,039,300.00
Change Orders
$
93,210.00
Pending Changes
$
0.00
Total
$ 8,132,510.00
Current Construction
Contingency
$
0.00
Potential for Project Cost Overruns/Claims
Project is complete and all obligations have been satisfied. The lien-filing period has expired. No
claims filed.
Discussion of Project Quality
This building was designed to be extremely durable and long-lasting. Brick exteriors and very
durable interior finishes will ensure superior quality.
Classrooms, laboratories, and office spaces are designed to meet current and anticipated program
needs. Technology for improved delivery of instruction, including Interactive Television, has been
included.
The performing arts space features durable finishes and 305 high quality theater seats.
The overall quality of this project is excellent. Levernier Construction has put together an
outstanding group of sub-contractors and managed the project very well.
Warrantee issues are being addressed, but overall this was a successful project.
Progress Photographs (Attached)
2
West Face of Building
East Face of Building
3
Nursing Practice Lab
Computer Lab
4
Tiered Classroom
Lobby Staircase
5