Office of Financial Management Washington State Major Project Status Report December 31, 2009 Agency Number: 699 Agency: SBCTC Project Number: 08-2-413 School/Campus: Shoreline Community College Project Title: Professional Automotive Center Addition Shoreline Community College Bill Reference(s): Sec 903, Chapter 488, Laws of 2005 Contact name, phone number, email: Bob Roehl, 206-546-4514 broehl@shoreline.edu Project Description: (This is a matching funds project) In response to the training needs of the new car dealers in the Northwest, the college is expanding the Professional Automotive Training Center from the current 28,150 square feet to 50,065 square feet. This was initially proposed as a two-phase expansion, with the 21,915 square foot expansion to include training “Quads” to meet the needs of the automobile dealers, manufacturers, and students. With the two phases now combined into one project, the expansion enhances program delivery and improves teaching space. Square feet: 21,915 sf will be added to the existing 28,150 sf building, with the completed project being a 50,065 sf building. Scope changes: There have been several scope changes made to the project, which included an electrical upgrade to enhance service to the building now and into the future, modifications to the old concrete footings, new water valve, existing scupper modifications, added drop ceiling to one new classroom, asphalt paving patch, revised low voltage wiring, improved HVAC controls, fire alarm upgrade, and an improved concrete floor finish. Project Total Cost: Phase Biennium Appropriation Amount Privately funded Predesign Design Construction 2007-09 Other (Approp/Non Approp) 2005-07 (1,000,000)+Private (1,000,000) 2007-09 (1,000,000)+Private (1,000,000) Remaining costs will be funded through private donations and capital campaign by the Puget Sound Auto Dealers Association 2007-09 $502,000 $2,000,000 $2,000,000 $973,901 $511,135 $260,964 $4,200,000 Cost escalation Total 1 Schedule: Predesign Complete Start Design Bid Date Notice to Proceed 50% Complete Substantial Completion Final Acceptance Budget Schedule Actual/Forecast Variance (wks) Nov 05 May 07 Dec 07 Nov 08 Mar 09 Aug 09 Oct 09 Nov 05 July 07 Feb 09 Apr 09 Jul 09 Nov 09 Jan 10 0 wks +9 wks +56 wks +22 wks +17 wks +13 wks +13 wks Project Status and discussion of Critical Path for Construction: With substantial funding already secured, the phasing of the project is no longer necessary, nor advisable. The above schedule has been revised to reflect the merging of the two phases into one. It was decided to move back the bid date to February 2009, with the timing calculated to provide the most competitive bid process, which can secure the lowest price possible for the project. This strategy proved successful as the low bidder came in significantly under the original MACC estimate. The project was completed a few weeks ahead of schedule. The identified critical path items experienced no major problems. Contract Award History A/E Agreement Original Agreement Amendments Pending Changes Total Current Design Contingency Construction Contract (excl. sales tax) Bid Award Amount $2,169,461 Change Orders $ 489,370 Pending Changes $___1,960 Total $2,660,791 Current Construction Contingency $ $294,270 $359,907 $ $654,177 $ Potential for Project Cost Overruns/Claims There is currently a low probability for any cost overruns or claims resulting from this project. Discussion of Project Quality The project is not required to be built to LEED Silver standard, since the project will yield area additions to a building that was never designed to address energy performance or facility sustainability. The original building was donated to the College by the Shoreline College Foundation and the Puget Sound Automobile Dealers Association. It is the intent of this project to build the additional square footage in the spirit of LEED, using sustainable materials, implement energy efficient and sustainable building systems. The construction will meet or exceed all industry standards for this type of construction. Over time, as elements of the original building (that are not part of this current project) are replaced, the College intends to seek LEED EB (Existing Building) Silver standard certification. 2 Project Photographs (Attached) South Side of PATC – Office Area South side of PATC, Shop Area and Toyota Quad North Side of PATC – Factory Quads New Toyota Corporate Training Center New Training Bays for SCC’s Toyota T-TEN Program New Chrysler Training Quad – Currently in use 3