Office of Financial Management Washington State Major Project Status Report

advertisement

Office of Financial Management

Washington State Major Project

Status Report

June 30 , 2008

Agency Number : 0699

Agency: Shoreline Community College

Project Number: 06-3-021

Project Title: Student Union Building Renovation (Pagoda Union Building)

Shoreline Community College

Bill Reference: Sec 903, Chapter 488, Laws of 2005

Contact: Bob Roehl 206 546-4514 broehl@shoreline.edu

Project Description: (This is an alternative financing project…COP)

The college has demolished the old 900 Building (Pagoda Student Union Building) to its foundation and is rebuilding to meet current and future demands for student programs and services. The new student union building will centralize student social program space.

The building will accommodate change, both as the college grows and as technology and programs evolve. The space is being designed as flexible and multi-purpose to allow for change without significant future cost. By adding an additional floor to the existing foundation, an increase of approximately 13,000 gross square feet will be realized.

The current Pagoda Union Building is approximately 39,000 gross square feet and that will increase to approximately 52,000 square.feet.

Project Total Cost:

Phase

Predesign

Design

Construction*

Biennium Appropriation Amount

2004-05 Local funds 170,200

2005-06

2006-07

Local funds 2,117,904

15,878,561

817,086 Other (contingency, equipment, artwork

Tax, contract admin, etc.)

Total

* MACC = Maximum Allowable Construction Cost

18,813,551

1

Schedule:

Predesign Complete

Budget Schedule

April 05

Actual/Forecast

April 05

Start Design

Bid Date

Notice to Proceed

50% Complete

April 05

Feb 06

April 06

Dec 06

April 05

May 06

June 06

January 07

Substantial Completion

Final Acceptance

Aug 07

Sept 07

April 08

Aug 08

Project Status and discussion of Critical Path for Construction:

Variance (wks)

0 wks

0 wks

+10 wks

+7 wks

+3 wks

+34 wks

+48 wks

Project’s initial bidding process was not successful, with only one bidder and that one being excessively high. After some design and scope changes the project was re-bid and

Berschauer Phillips Construction Company was the successful bidder. The COP was issued at the end of June 2006, with construction beginning in earnest on June 27 th

2006.

The excessive rain, snow in November and wind in December caused some delays. Latent conditions caused significant additional delays and the contractor has also accepted responsibility for some delay time. The campus was without a Student Union Building for about 21 months. The building was scheduled to open in Mid September 2007, in time for the 2007-08 academic year. However, due to delays in construction, the initial opening of the building actually occurred on April 2, 2008, with temporary occupancy permitted.

Currently, we are in the final stages, working with the City of Shoreline, to be permitted for permanent occupancy of the building. We anticipate this happening before August 1,

2008.

Contract Award History

A/E Agreement

Amendments

Pending Changes $ 0

Original Agreement $ 659,098

$ 1,105,337

Total

Current Design

Contingency

$ 1,764,475

Construction Contract (excl. sales tax)

Bid Award Amount $ 13,766,722

Change Orders

Pending Changes $ 0

Total

Current Construction

Contingency

$ 1,505,336

$ 15,272,008

$ 0

2

Potential for Project Cost Overruns/Claims

The construction schedule had to be modified throughout the project due to latent conditions, some scheduling issues in the work, and delays due to inclement weather. As a result, the project will incur some cost overrun claims.

Discussion of Project Quality

The project has been designed to implement sustainable practices, material uses and meet state energy code requirements. The construction will meet all industry standards for this type of construction. Several discoveries during demolition and preparation of the structure for fitting of new components reveal deteriorated utilities infrastructure (high voltage conduit) and installations from earlier projects that were poorly documented. These discoveries have revealed dangerous conditions, which required correction, and diverted project funding to correct.

Generally, the completed project quality was high. The final product has shown a few problem areas that are being addressed where feasible.

Project Photographs

3

4

Download