Office of Financial Management Washington State Major Project Status Report: June 30, 2008 Agency Number: Agency: Project Number: Project Title: Bill Reference: Contact: 140 Clark College 06-1-302 Central Gaiser Renovation 488-05-812 Jim Green, Director of Plant Services 360-992-2408, jgreen@clark.edu Project Description: Remodel the central portion of Gaiser Hall that houses Student Development Services. Square Feet: Scope of Change: 27,345 gsf n/a Project Total Cost: Phase Predesign Design Construction* Other (COP/Non Approp) Other (COP/Non Approp) Biennium 2003-05 2003-05 2005-07 2005-07 Various Appropriation 057 H12 357 H36 Various Total Amount 8,374,000 905.000 5,116,016 14,395,016 * MACC (revised) = $7,832,070 Schedule: Predesign Complete Start Design Bid Date Notice to Proceed 50% Complete Substantial Completion Final Acceptance Budget Schedule June 04 June 05 March 06 April 06 November, 06 May 07 July 07 Actual/Forecast June 04 October 05 July 06 September 06 August 07 March 08 April 08 Variance (wks) 0 wks 16 wks 12 wks 16 wks 30 wks 37 wks 33 wks Project Status and discussion of Critical Path for Construction: Construction has been completed, and is now in the closeout and warranty phase. The majority of the departments have been moved back into the new building. 1 Contract Award History: A/E Agreement Original Agreement Amendments Pending Changes Total Current Design Contingency $ $ $ $ $ $ 809,431* 381,456* 0 1,190,887* 0 0 Construction Contract (excl. sales tax) Bid Award Amount $ 10,681,414* Change Orders $ 492,648* Pending Changes $ 18,000 Total $ 11,192,062* Current Construction $ 0 Contingency $ 100,000 * Includes North Parking Lot (required by City of Vancouver) and Gaiser Renovation Contracts Potential for Project Cost Overruns/Claims: Construction cost is higher than the original MACC and the project estimate. There were some additional costs due to latent conditions because much of the building dates back to the 1950’s. In addition, costs were incurred because the construction phasing was to be disrupted to support relocation of personnel in the building to minimize impact to students. Discussion of Project Quality: The project will be built to campus standards and applicable codes. Project Photographs (Attached – see below): 2 3 4