Preliminary Summary of Work Scott Residence Hall Renovation & Addition Scott Residence Hall is an existing dormitory building on College Hill Drive at East Carolina University in Greenville NC. The building was built in 1962 and is mostly original with the exception of some minor renovations to the entry lobby and a gate and fence addition. It is a “U” shaped building with a landscaped courtyard in between the side wings. The rooms are accessed by exterior balconies that extend the full length and width of the building on the courtyard side. The building is four story cast-in-place concrete structure with flat slab floors and roof with double wythe masonry infill exterior walls. There is a partial basement with the remaining building being over a crawlspace. The windows are aluminum single glazed. This is a major renovation project that will encompass all portions of the building. All systems will be updated or replaced with the exception of the primary structure and the roof membrane. The construction will take place over the course of one school year including two summer breaks commencing May 2009. The building will be vacated during construction. The work can be summarized as follows. Demolition The interior of the building will be gutted including abatement of asbestos floor tile and pipe insulation. It is anticipated that lead paint exists in the building and any demolition or disturbances to the paint will have to be done in accordance with normal safety practices. All existing finishes (carpet, tile, etc.), doors, windows, interior walls (except primary suite demising walls), openings, finishes including tile wall and floor finishes, P, M, E and special system, equipment and built-in furnishings will be demolished. The building will essentially be “gutted” to a clean structural slab and walls. The exterior demolition includes demolishing the steel guard rails at the balconies, exterior doors, the courtyard entry gate and fence, some courtyard features and landscaping. Architectural The building will be renovated in its entirety. The interior will have new walls, doors, finishes, toilet fixtures and accessories, tile floor and walls, paint, carpet and VCT and all P, M, E and special systems customary in a complete building renovation. The building will be sprinkled. New thermally broken aluminum windows will be installed throughout the existing and new building. The existing exterior stairs and balconies will have extensive renovations including concrete restoration, new rails, supplemental supports and finishes. The existing roof is still covered by a warranty and will remain mostly intact. New penetrations and tie-ins will be designed to minimize disturbance to the existing roof. Additions will be constructed as well. New four-story toilet room addition towers will be built adjacent to each suite. The tower will be built of pre-cast structural concrete composite walls with a “thin-brick” veneer with a pre-cast concrete structural floor slab. The towers will consist primarily of toilet rooms and some vertical chases. A four-story residential suite addition will be built at the east end of the courtyard effectively enclosing the courtyard. This addition will have 17 four-room suites, two large public group toilet rooms and a large mechanical space at the basement level. A new elevator will be provided as part of this addition. This addition will also be built of pre-cast concrete composite walls with thin-brick veneer and structural concrete pre-cast slab. A new exterior egress stair and ramp addition will be constructed at the west end of the courtyard. The stair will serve five levels including the basement. A new elevator will be installed in an existing stair shaft to serve the existing basement level and the upper floors at the west end of the building. A new entry, front porch and monumental stairs will be built at the west side f the building to enhance the building entry and outdoor gathering space. The renovated area is approximately 75,782 s.f. of interior space. The balcony and exterior stair renovations total approximately 14,635 s.f. The new construction totals approximately 26,300 s.f. interior and 5,700 s.f. balcony and exterior stair. Site The site work includes renovations to the courtyard, yard area adjacent to the building and limited modifications to the parking and drive areas adjacent to the building. The courtyard will undergo renovations to some of the paved areas and modifications to the landscaping. The gate and fence at the east end of the building will be demolished to make way for the building addition. The west end of the courtyard will be modified to accommodate the new stair and elevator addition. New storm drainage will be provided. The parking at the east side of the building will be modified to accommodate the addition. Some parking will be demolished and the drive will be re-routed. New parking spaces will be incorporated off of the relocated drive. A new yard and entry will be built between the addition and the new drive. The parking at the west side of the building will be modified to accommodate the new porch and steps. College Hill Drive and the parking lot will be repaired after installation of the new steam lines. New landscaping will be provided throughout. P,M & E All existing P, M & E systems will be demolished and replaced including all existing steam piping, plumbing pipe, fixtures, controls and devices. New piping will be installed throughout the renovated and new portions of the building to distribute hot water for domestic heat, chilled water for cooling, and for hot and cold domestic water. A new steam to hot water converter will be installed in the mechanical room for building heat. New fan coil units will be installed in each residential room with a thermostat located in each room. Outside air will be ducted down from rooftop mounted package cooling unit to precondition the air. A new chiller will be provided in an existing, remote chiller enclosure as well as new buried chilled water lines serving the building. Toilet rooms will exhaust through the roof. A new buried steam main including expansion loops will be routed to Scott Hall from a new tie-in point across College Hill Drive. The steam main will require excavation in the street and parking areas. These paved areas will have to be fully restored to the original of better condition. New plumbing includes all new water and waste piping, vents, water heaters, fixtures, showers, sinks, toilets, mop sinks, etc throughout the building. New roof drain leaders will be installed from existing and new roof drains. The new sprinkler system will require new risers and fire hoe connections. A new buried fire line will be provided from the Jones Hall fire pump to serve this project. This will require excavation and repair of paved areas. New electrical will be provided throughout the building including power, telephone, data and video, controls, security and fire alarm. New switchboard, feeders and distribution panels will be provided. A new generator will be provided in a remote enclosure. New distribution feeders will be routed from the main electrical gear located in the main mechanical room to load centers in each suite. Branch circuitry will be installed in concealed and surface mounted raceway. Fire alarm and devices will be installed throughout the building. New interior and exterior lighting will be provided throughout.