POINT-WISE COMPLIANCE OF STIPULATED ENVIRONMENTAL

advertisement
POINT-WISE COMPLIANCE OF STIPULATED ENVIRONMENTAL
CONDITIONS/ SAFEGUARDS IN THE
ENVIRONMENTAL CLEARANCE
LETTER NO. SEIAA/HR/2013/283
DATED 17thJune, 2013
Tata Center- Mixed Use Development Project,
Sector-72, Gurgaon, Haryana
Sl.
Conditions
Status of Compliance
No.
PART A – SPECIFIC CONDITIONS:
Construction Phase 1
“Consent to Establish” shall be obtained from Agreed. “Consent to Establish” has been
Haryana State Pollution Control Board under obtained from Haryana State Pollution
Air and Water Act and a copy shall be Control Board under Air and Water Act.
submitted to the SEIAA, Haryana before the Copy of the same had been submitted to
start of any construction work at site.
SEIAA, Haryana along with previous
compliances.
Copy of “Consent to
Establish” is enclosed as Annexure-I.
2
A first aid room as proposed in the project Agreed. A first aid room has been provided
report
shall
be
provided
both
during during the construction phase and same
construction and operation phase of the will be maintained during operation phase
project.
3
Adequate
of the project.
drinking
water
and
sanitary Agreed. Adequate drinking water and
facilities should be provided for construction sanitary facilities has been provided for
workers at the site. Provision should be made construction workers at site. Provisions are
for mobile toilets. Open defecation by there for mobile toilets. The safe disposal
laboures is strictly prohibited. The safe of waste-water and solid wastes generated
disposal of waste water and solid wastes during the construction phase is being
generated during the construction phase ensured.
should be ensured.
Page 1 of 23
4
All top soil excavated during construction Agreed. All the top soil excavated during
activities should be stored for use in the construction activities is being properly
horticulture/landscape development within the stored and will be utilized for the
project site.
horticulture/landscape development within
the site.
5
The project proponent shall ensure that the Agreed. Building material required during
building material required during construction construction phase has been properly stored
phase is properly stored within the project within the project area and construction
area and disposal of construction waste should waste has been used for site development
not create any adverse effect on the and land filling of the project site, it will
neighboring communities and should be not create any adverse effect on the
disposed of after taking necessary precautions neighboring communities.
for general safety and health aspects of
people, only in approved sites with the
approval of competent authority.
6
Construction spoils, including bituminous Agreed. Construction spoils will be used
material and other hazardous materials, must for site development and land filling of the
not be allowed to contaminate watercourses project site, other hazardous materials will
and dump sites for such material must be be disposed-off as per norms
secured so that they should not leach into the
ground water and any hazardous waste
generated during construction phase, should
be disposed off as per applicable rules and
norms with necessary approval of the Haryana
State Pollution Control Board.
7
The diesel generator sets to be used during Agreed. D.G sets used will be of low
construction phase should be of ultra-low sulphur diesel, conforming to Noise &
sulphur diesel type and should confirm to National Air Quality Standards.
Environment (Protection) Rules prescribed for
air and noise emission standards.
8
The diesel required for operating DG sets Agreed. The diesel required for operating
Page 2 of 23
shall be stored in underground tanks and if DG set will be stored in HDPEdrums and
required, clearance from Chief Controller of log
Explosives shall be taken.
books
will
be
managed
for
accountability. Storage will be within the
threshold limit hence clearance from chief
control of explosive is not required.
9
Ambient noise levels should confirm to the Agreed. Ambient noise and ambient air has
residential standards both during day and been
closely
monitored
during
the
night. Incremental pollution loads on the construction phase. Noise quality data
ambient air and noise quality should be monitored is enclosed as Annexure-II.
closely monitored during the construction
phase. Adequate measures should be taken to
reduce ambient air and noise level during
construction phase, so as to confirm to the
stipulated residential standards.
10
Fly ash should be used as building material in Agreed. Fly ash based material will be
the construction as per the provisions of Fly used.
Ash Notification of September 1999 and as
amended on 27th August 2003.
11
Storm water control and its re-use as CGWB Agreed. Storm water will be collected to
and BIS standards for various applications recharge the ground water, 08 RWH pits
should be ensured.
are proposed to be constructed within the
project site for this purpose.
12
Water demand during construction should be Agreed. Water demand during construction
reduced by use of pre-mixed concrete, curing will be reduced by use of pre-mixed
agents and other best practices.
concrete, curing agents and other best
practices.
13
In view of the severe constrains in water Agreed. No ground water is extracted
supply augmentation in the region and during the construction as well as operation
sustainability
of
water
resources,
the phase. So, CGWB permission is not
developer will submit the NOC from CGWB required. However during construction
Page 3 of 23
specifying water extraction quantities and phase water is being supplied by HUDA
assurance
from
HUDA/utility
provider (Treated Water), permission letter from
indicating source of water supply and quantity HUDA is enclosed as Annexure-III.
of water with details of intended use of water Duringoperational
phase
HUDA
will
– potable and non-potable. Assurance is supply
water,
copy
of
enclosed
as
fresh
required for both construction and operation acknowledgement
is
stages separately. It shall be submitted to the Annexure-IV.
SEIAA and RO, MOEF, Chandigarh before
the start of construction.
14
Roof should meet prescriptive requirement as Agreed. During construction phase care
per Energy Conservation Building Code by will be taken that roof area meets Energy
using appropriate thermal insulation material.
Conservation Building Code requirement
by using appropriate thermal insulation
material to fulfill requirement.
15
Opaque
wall
should
meet
prescriptive Agreed. Material having appropriate R &
requirement as per Energy Conservation U value will be used to meet prescriptive
Building Code which is proposed to be requirement of opaque wall as per energy
mandatory for all air conditioned spaces while conservation building Code.
it is aspirational for non-air-conditioned
spaces
by
use
of
appropriate
thermal
insulation material to fulfill requirement.
16
The approval of the competent authority shall Agreed. The approval of the competent
be obtained for structural safety of the authority will be obtained for structural
building on account of earthquake, adequacy safety of the building on account of
of fire-fighting equipment, etc. as per earthquake,
adequacy
of
fire-fighting
National Building Code including protection equipment, etc. as per National Building
measures from lightening etc. If any forest Code including protection measures from
land is involved in the proposal site, clearance lightening etc. The project site does not fall
under Forest Conservation Act shall be under the Forest Conservation Act. Copy of
obtained from the competent authority.
17
forest NOC is enclosed as Annexure-V
Overexploited groundwater and impending Agreed.
Page 4 of 23
Ground
water
will
not
be
severe shortage of water supply in the region extracted. To recharge the ground water
requires the developers to redraw the water level of the area rain water harvesting has
and energy conservation plan. Developer shall been proposed in the project. The water
reduce the overall footprint of the proposed reuse/recycling and water efficiency/saving
development.
Project
proponent
shall measures are being incorporated within 3
incorporate water efficiency/savings measures months and before start of construction to
as well as water reuse/recycling within 3 SEIAA, Haryana and RO, MOEF, GOI,
months and before start of construction to the Chandigarh.
SEIAA, Haryana and RO, MOEF, GOI,
Chandigarh.
18
The project proponent shall construct 08 rain Agreed. 08 rain water harvesting pits for
water harvesting pits for recharging the recharging the ground water within the
ground water within the project premises. project premises will be constructed. Rain
Rain water harvesting pits shall be designed water harvesting pits
will be designed in
to make provisions for silting chamber and such a way that silt and floating material
removal of floating matter before entering will not enter in the ground water level..
harvesting pit. Maintenance budget and Maintenance
budget
and
persons
persons responsible for maintenance must be responsible for maintenance are being
provided. Care shall also be taken that provided and care will also be taken that
contaminated water do not enter any RWH contaminated water do not enter any RWH
pit.
pit.Storm water plan showing the RWH pit
location is enclosed as Annexure-VI.
19
The project proponent will provide minimum Agreed, permanent ladder will be provided
one hydraulic ladder for escape of people in instead of hydraulic ladder. As hydraulic
case of fire.
20
ladder can be provided upto only 12m.
The project proponent shall submit assurance Agreed. An application has been filed to
from the DHBVN for supply of 5016KVA of the Superintending Engineer of HVPNL
power supply before the start of the for power supply. The acknowledgment
construction. In no case project will be copy of the same is enclosed as Annexure
operational solely on generators without any VII.
power supply from any external power utility.
Page 5 of 23
21
Detail calculation of power load and ultimate Agreed. The total power requirement is
power load of the project shall be submitted to 5016 KVA that will be supplied by
DHBVN under intimation to SEIAA Haryana DHBVN.
The
detailed
power
load
before the start of the construction. Provisions calculation has been submitted to the
shall be made for electrical infrastructure in DHBVN. An application has been filed to
the project area.
the
Superintending
Engineer
NCR
Planning. The acknowledgment copy of the
same is enclosed as Annexure VII.
22
The project proponent shall obtain NOC from Agreed. An application has been filled to
the nearest fire station before start of the municipal
construction.
corporation
Gurgaon
for
obtaining the fire NOC. Acknowledgement
copy of the same is enclosed as Annexure
VIII
23
The project proponent shall not raise any Agreed. The project site does not contain
construction
in
the
natural
land any natural land depression nallah/ water
depression/Nallah/water course and shall course as well as no natural flow is
ensure that the natural flow from the obstructed by the project.
Nallah/water course is not obstructed.
24
The project proponent shall keep the plinth Agreed. The plinth level of the building
level of the building blocks sufficiently above blocks is being sufficiently above the level
the level of the approach road to the project as of
the
approach
road..
Section
and
per prescribed by-laws. Levels of the other Elevation plan are enclosed as Annexureareas in the projects shall also be kept suitably IX
so as to avoid flooding.
25
Construction shall be carried out so that Agreed. As it is a mixed use development
density of population does not exceed norms project so, population density kept as per
approved by Director General Town and the approved Building plan by Director
Country Department Haryana.
General Town and Country Department,
Haryana.
26
The project proponent shall submit an Agreed. Ground water is not used for the
affidavit with the declaration that ground construction activity. An affidavit has been
Page 6 of 23
water will not be used for construction and submitted to SEIAA, Haryana. Copy of the
only treated water should be used for same is enclosed as Annexure-X.
construction.
27
The project proponent shall not cut any Agreed. As the project site was a vacant
existing tree and project landscaping plan land so there was no need to cut the trees.
should be modified to include those trees in Plantation will be carried out around the
green area
periphery of plot & along internal road
preferably with local species.
28
The project proponent shall provide helipad Agreed Helipad facility will be provided
facility as required under NBC norms and for building having height more than 60m
shall seek permission of helipad from AAI as per NBC norms. NOc from avitation
accordingly.
department has been taken. Copy of AAI
NOC is enclosed as Annexure-XI.
29
The project proponent shall ensure that ECBC Agreed. ECBC norms for composite
norms for composite climate zone are met. In climate zone, water heating, pumping,
particular building envelope, HVAC services, lighting and electrical infrastructure are
water
heating,
pumping,
lighting
and being followed.
electrical infrastructure must meet ECBC
norms.
30
The project proponent shall provide 3m high Agreed. 3m high barricade around the
barricade around the project area, dust screen project area is being provided, dust screen
for every floor above the ground, proper for every floor above the ground, proper
sprinkling and covering of stored material to sprinkling and covering of stored material
restrict
dust
construction.
31
and
air
pollution
during to restrict dust and air pollution during
construction will be provided.
The project proponent shall construct a Agreed. Sedimentation basin constructed
sedimentation basin in the lower level of the to trap the pollutants and other wastes
project site to trap pollutant and other wastes during rains is being in lower level of the
during rains.
32
project site.
The project proponent shall provide proper Agreed. Proper roads of adequate width
Rasta of proper width and proper strength for will be provided in the project for
Page 7 of 23
his project before the start of construction.
movement of vehicle within the project
site. Site plan is enclosed as an AnnexureXII.
33
The project proponent shall provide all the Agreed. All the safety measures for the
safety measures for the workers during workers during construction phase of high
construction phase of high rise building.
34
rise building will be provided.
The project proponent shall ensure that the U- Agreed. Glass having U value less than
value of the glass is less than 3.177 and 3.177 & maximum solar heat gain to
maximum solar heat gain co-efficient is 0.25 efficient 0.25 Vertical Fenestration will be
for vertical fenestration.
35
The
project
permission
of
proponent
Municipal
used.
shall
submit Agreed. Mining approval is obtained from
Commissioner the assistant mining engineer, Gurgaon,
Gurgaon for disposal of excavated soil before Haryana. The copy of same is enclosed as
the start of construction.
36
Annexure-XIII.
The project proponent shall seek NOC from Agreed. NOC from Town and Country
Town and Country department regarding department regarding height of the building
height of the building allowed in the skyline allowed in the skyline of that city is being
of that city.
taken. Building plan approval from the
DTP is already obtained.
Operational phase a
“Consent to Operate” shall be obtained from Agreed. Permission will be obtained after
Haryana State Pollution Control Board under completion of construction work of the
Air and Water Act and a copy shall be project.
submitted to the SEIAA, Haryana.
b
The STP shall be installed for the treatment of Agreed. The Sewage Treatment Plant
the sewage to the prescribed standards (STP) will be installed for the treatment of
including odour and treated effluent will be the sewage to be prescribed standards
recycled. The installation of STP should be including odor and treated effluent shall be
certified by an independent expert and a recycled to achieve zero exit discharge.
report in this regard should be submitted to Installation
of
STP
certified
by
an
the SEIAA, Haryana before the project is independent expert will be submitted to the
Page 8 of 23
commissioned
for
operation.
Tertiary SEIAA before start of operation stage of
treatment of waste water is mandatory. the mixed use project.
Plumbing plan
Discharge of treated sewage shall confirm to showing the STP location is enclosed as
norms and standards of HSPCB, Panchkula. Annexure-XIV.
Project Proponent shall implement such STP
technology which does not require filter
backwash.
c
Separation of the grey and black water should Agreed. Treatment of grey and black water
be done by the use of dual plumbing line. will be done. Dual plumbing plan and
Treatment
of
100%
grey
water
by water balance diagram are attached as
decentralized treatment should be done Annexure –XV.
ensuring that the re-circulated water should
have BOD maximum 10 mg/litre and the
recycled water will be used for flushing,
gardening and DG set cooling and running of
fountain in the water body to achieve zero exit
discharge.
d
For disinfection of the treated wastewater Agreed. For disinfection of the treated
ultra-violate radiation or ozonization process wastewater
should be used.
e
ultra-violet
radiation
or
ozonization process will be used.
The solid waste generated should be properly Agreed. The solid waste generated will be
collected and segregated. Bio-degradable properly collected and segregated. Biowaste shall be decomposed at site and degradable waste will be decomposed at
dry/inert solid waste should be disposed-off to site and dry/inert solid waste will be
approved sites for land filling after recovering disposed-off to approve sites for land
recyclable material.
f
filling after recovering recyclable material.
Diesel power generating sets proposed as D.G. Sets to be used for power back up are
source of back-up power for lifts, common of enclosed type and confirming to rules
area illumination and for domestic use should made under the Environment (Protection)
be enclosed type and conform to rules made Act, 1986. The D.G. sets are run on low
under the Environmental (Protection) Act, sulphur diesel.
Page 9 of 23
1986. The location of the DG sets should be
in the basement as promised by the project
proponent with appropriate stack height i.e
above the roof level as per the CPCB norms.
The diesel used for DG sets should be ultra
low sulphur diesel (0.05% sulphur), instead of
low sulphur diesel.
g
Ambient Noise level should be controlled to Agreed. Ambient Noise level is being
ensure that it does not exceed the prescribed controlled to ensure that it does not exceed
standards both within and at the boundary of the prescribed standards both within and at
the Proposed Residential Complex
the boundary of the Residential Complex.
A copy of ambient noise quality data is
enclosed as Annexure-II.
h
The project proponent should maintain at least Agreed. Project Proponent will provide
22% as green cover area for tree plantation 30% as a green area. Landscape plan is
especially all around the periphery of the enclosed as Annexure –XVI.
project and on the road sides preferably with
local species so as to provide protection
against particulars and noise. The 8% open
spaces inside the plot should be preferably
landscaped and covered with vegetation/grass,
herbs & shrubs. Only locally available plant
species shall be used.
i
The
project
proponent
shall
strive
to Agreed. Minimum water will be used in
minimum water in irrigation of landscape by irrigation of landscape by minimizing grass
minimizing grass area, using native variety, area, using native variety, xeriscaping and
xeriscaping
and
efficientirrigation
irrigation
only
transpiration data.
j
mulching,
system,
after
utilizing mulching,
scheduling system,
checking
utilizing
scheduling
efficient
irrigation.
irrigation
Treated
evapo- water will be used for the landscaping
purposes.
Rain water harvesting for roof run-off and Agreed. Rain water harvesting for roof
Page 10 of 23
surface, as per plan submitted should be run-off and surface, as per plan submitted
implemented. Before recharging the surface will be implemented. Before recharging the
run-off, pre-treatment through sedimentation surface
run-off,
pre-treatment
through
tanks must be done to remove suspended sedimentation tanks will be done to remove
matter, oil and grease. The bore well for suspended matter, oil and grease. The bore
rainwater recharging should be kept at least well for rainwater recharging will be kept
5m. above the highest ground water table. at least 5m above the highest ground water
Care shall be taken that contaminated water table. Rain water harvesting plan is
do not enter any RWH pit. The project enclosed as Annexure-VI.
proponent shall avoid RWH of first 10
minutes of rain fall. Roof top of the building
shall be without any toxic material or paint
which can contaminate rain water. Wire mess
and filters should be used wherever required.
k
The ground water level and its quality should The ground water level and its quality is
be monitored regularly in consultation with being monitored in consultation with
Central Ground Water Authority.
l
Central Ground Water Authority.
There should be no traffic congestion near the Agreed. There is no traffic congestion near
entry and exit points from the roads adjoining the entry and exit points from the roads
the proposed project site. Parking should be adjoining the project site. Parking will be
fully internalized and no space should be fully internalized and no public space will
utilized.
be utilized. A traffic plan is enclosed as
Annexure-XVII.
m
A report on the energy conservation measures Agreed.
A
conforming to energy conservation norms conservation
report
measures
on
the
energy
conforming
to
finalized by Bureau of Energy Efficiency energy conservation norms finalized by
should be prepared incorporating details about Bureau of Energy Efficiency is being
building materials & technology, R & U prepared
incorporating
details
about
Factors etc and submit to the SEIAA, Haryana building materials & technology, R & U
in three month time.
Factors etc has been submit to the SEIAA,
Haryana in three month time.
Page 11 of 23
n
Energy
conservation
measures
like Agreed. Energy conservation measures like
installation of LED for Lighting the areas installation of CFLs/TFLs for lighting the
outside the building should be integral part of areas outside the building is integral part of
the project design and should be in place the project design and shall be in place
before project commissioning. Use of solar before
project
commissioning.
Solar
panels must be adapted to the maximum lighting is proposed for open spaces and
energy conservation.
o
signage.
The project proponent shall use zero ozone Agreed. As it is a Mixed Use Development
depleting potential material in insulation, Project, all the material going to be use like
refrigeration, air-conditioning and adhesive. refrigeration, air-conditioning etc. are of
Project proponent shall also provide Halon non-ozone depleting.
free fire suppression system.
p
The solid waste generated should be properly Agreed. Solid waste generated will be
collected
and
segregated
as
per
the collected & segregated as per MSW rule,
requirement of the MSW Rules, 2000 and as 2000. Bio degradable waste will be
amended from time to time. The bio- composed by vermin-composting.
degradable waste should be composed by
vermin-composting at the site war marked
within the project area and dry/inert solid
waste should be disposed-off to the approved
sites
for
land-filling
after
recovering
recyclable material.
q
The provision of the solar water heating Agreed. As it is a Mixed Use Development
system shall be as per norms specified by Project, solar water heating system will be
HAREDA and shall be made operational in used as per norms by HAREDA.
each building block.
r
The traffic plan and the parking plan proposed Agreed.
The
traffic
plan
is
being
by the project proponent should be adhered to meticulously adhered to with further scope
meticulously with further scope of additional of
additional
parking
for
future
parking for future requirement. There should requirement. Parking is being completely
be no traffic congestion near the entry and internalized and no public space is being
Page 12 of 23
exit points from the roads adjoining the utilized. Care is being taken to ensure that
proposed project site. Parking should be fully there will be no traffic congestion at the
internalized and no public space should be entry and exit points.
used.
s
The project shall be operationalized only Agreed.
The
project
shall
be
when HUDA/public authority will provide operationalized only when HUDA/public
domestic water supply system in the areas.
authority will provide domestic water
supply system in the areas.
t
Operation and maintenance of STP, solid Agreed. Operation and maintenance of
waste
management
and
electrical STP,
solid
waste
management
and
Infrastructure, pollution control measures electrical Infrastructure, pollution control
shall be ensured even after the completion of measures will be ensured even after the
sale.
u
completion of sale.
Different type of waste should be disposed-off Agreed. MSW will be disposed off as per
as per provisions of municipal solid waste, provisions of municipal solid waste made
biomedical waste, hazardous waste, e-waste, under Environment Protection Act, 1986.
batteries
&
Environment
plastic
rules
Protection
made
under Negligible quantity of hazardous waste, e-
Act,
1986. waste, and plastic waste generated will be
Particularly E-Waste and Battery waste shall disposed off as per hazardous waste, ebe disposed of as per existing E-waste waste, batteries & plastic rules made under
Management
Rules
2011
Management
Rules
2001.
and
Batteries Environment Protection Act, 1986.
The
project
proponent should maintain a collection center
for E-Waste and it should be disposed of to
only
registered
and
authorized
dismantler/recycler.
v
Standards for discharging of environmental Agreed. Standards for discharging of
pollutants as enshrined in various schedules of environmental pollutants as enshrined in
rules 3 of Environment Protection Rules 1986 various
shall be strictly complied with.
Page 13 of 23
schedules
of
rules
3
of
Environment Protection Rules 1986 will be
strictly complied with.
w
Water
supply
be
metered
to
different Agreed. Water supply will be metered to
residential units and different utilities.
x
different units and different utilities.
The project proponent shall ensure that the Agreed. Stack height of DG sets are kept 6
stack height of DG sets is as per the CPCB mtrs above the roof level as per the CPCB
guide lines and also ensure that the emission guide lines and also ensured that the
standards of noise and air are within the emission standards of noise and air are
CPCB prescribed limits. Noise and Emission within the CPCB prescribed limits.
level of DG sets are greater than 800KVA
shall be as per CBCB latest standards for high
capacity DG sets.
y
All electric supply exceeding 100amp, 3- Agreed. All electric supply exceeding
phase shall maintain the power factor between 100amp, 3-phase will be maintain the
0.98 lag to 1 at the point of connection.
power factor between 0.98 lag to 1 at the
point of connection.
z
The project proponent shall use only treated Agreed. Instead of fresh water for DG
water instead of fresh water for HVAC and cooling, treated water will be used.
DG cooling. The project proponent shall use Evaporative cooling technology and double
evaporative cooling technology and double stage cooling system is being used for
stage cooling system for HVAC in order to HVAC
reduce
water
consumption.
in
order
to
reduce
water
Further consumption. Maximum treated water will
temperature, relative humidity during summer be used for various processes instead of
and winter session should be kept at optimal fresh
water
level. Variable speed drive, best co-efficient consumption.
of performance, as well as optimal integrated
point load value and minimum outside fresh
air supply may be resorted for conservation of
power and water. Coil type cooling DG sets
shall be used for saving cooling water
consumption for water cooled DG sets.
Page 14 of 23
to
reduce
the
water
PART-B GENERAL CONDITIONS :-
i
The project proponent should ensure the Agreed. All safeguards mentioned in the
commitments made in Form-1, Form-1A, application are being implemented during
EIA/EMP and other documents submitted to the
construction
phase
and
will
be
the SEIAA for protection of environment and implemented during the operation phase.
proposed
environmental
safeguards
are
complied with in letter and spirit. In case of
contradiction between two or more documents
on any point, the most environmentally
friendly commitment on the point shall be
taken as commitment by project proponent.
ii
Six monthly compliance reports should be Agreed. Six monthly compliance report is
submitted to the Haryana State Pollution being submitted to the Haryana State
Control Board and Regional Office, MoEF, Pollution Control Board and Regional
GOT, Northern Region, Chandigarh and a Office, MoEF, GOI, Northern Region,
copy to the SEIAA Panchkula, Haryana.
iii
Chandigarh, Haryana.
Noise , STP outlet and stack emission shall be Agreed. Noise, STP outlet and stack
monitored
daily.
Other
environmental emission will be monitored daily. Other
parameters shall be monitored on monthly environmental
parameters
will
be
basis. After every 3 months the project monitored on monthly basis. After every 3
proponent shall conduct environmental audit months
environmental
audit
will
be
and shall take corrective measure, if required, conducted and corrective measure will be
without delay.
iv
taken, if required, without delay.
The SEIAA, Haryana reserves the right to add Agreed. The SEIAA, Haryana reserves the
additional safeguard measures subsequently, right to add additional safeguard measures
if found necessary. Environmental Clearance subsequently,
if
found
necessary.
granted will be revoked if it is found that false Environmental Clearance granted will be
information has been given for getting revoked if it is found that false information
approval of this project. SEIAA reserves the has been given for getting approval of this
Page 15 of 23
right to revoke the clearance if conditions project. SEIAA reserves the right to revoke
stipulated are not
implemented to
the the clearance if conditions stipulated are
satisfaction of SEIAA/MOEF.
not implemented to the satisfaction of
SEIAA/MOEF.
v
The project proponent shall not violate any No judicial order/ pronouncements issued
judicial orders/pronouncements issued by any by the Hon’ble Supreme Court/High Courts
Court/Tribunal.
vi
to the developers.
All other statutory clearances such as the Agreed.
All
the
required
applicable
approvals for storage of diesel from Chief clearances have been taken from the
Controller of Explosives, Fire Department, respective authority.
Civil
Aviation
Conservation
Act,
Department,
1980
and
Forest Forest NOC is enclosed as Annexure-V
Wildlife AAI NOC is enclosed as Annexure-X
(Protection) Act. 1972, Forest Act, 1927, NOC from Chief Controller of Explosive
PLPA 1900, etc. shall be obtained, as shall be taken at the appropriate stage.
applicable by project proponents from the
respective authorities prior to construction of
the project.
vii
The project proponent should inform the Agreed. A copy of advertisement has been
public that the project has be accorded advertised in two local newspapers.
Environment Clearance by the SEIAA and
copies of the clearance letter are available
with the Haryana State Pollution Control
Board & SEIAA. This should be advertised
within 7 days from the date of issue of
clearance
letter at
least
in
two local
newspapers that are widely circulated in the
region and the copy of the same be forwarded
to SEIAA Haryana. A copy of Environment
Clearance collections shall also be put on
project
Page 16 of 23
proponent’s
website
for
public
awareness.
viii
Any appeal
against
this
Environmental Agreed.
Any
appeal
against
this
Clearance shall lie with the National Green Environmental Clearance shall lie with the
Tribunal, if preferred within a period of 30 National Green Tribunal, if preferred
days as prescribed under Section 16 of the within a period of 30 days as prescribed
National Green Tribunal Act, 2010.
under section 16 of the National Green
Tribunal Act, 2010.
ix
The project proponent shall put in place Agreed. The project proponent shall put in
Corporate Environment Policy as mentioned place Corporate Environment Policy as
in MOEF, GOI, ON No. J-11013/41/2006-IA mentioned in MOEF, GOI, ON No. JII (I) dated 26.04.12 within 3 months period. 11013/41/2006-IA II (I) dated 26.04.12
Latest Corporate Environment Policy should within 3 months period. Latest Corporate
be submitted to SEIAA within 3 months of Environment Policy should be submitted to
issuance of this letter.
SEIAA within 3 months of issuance of this
letter.
x
The
fund
ear-marked
for
environment Agreed.
The
fund
ear-marked
for
protection measures should be kept in environment protection measures is being
separate account and should not be diverted kept in separate account and will not be
for other purposes and year wise expenditure diverted for other purposes and year wise
shall be reported to the SEIAA/RO MoEF expenditure
will
GOI under rules prescribed for Environment SEIAA/RO
MoEF
Audit.
xi
be
reported
GOI
under
to
the
rules
prescribed for Environment Audit.
The project proponent shall obtain NOC Agreed. Application has already given to
under Aravalli Notification from CEC of the District Collector, Gurgaon, Haryana
Hon’ble Supreme court regarding coverage for taking clearance of Forest and Aravalli
under Aravalli Notification before start of Acknowledgment copy is enclosed as
construction.
xii
Annexure-V.
The project proponent shall ensure that no Agreed. It is being ensured that no vehicle
vehicle during construction/operation phase during construction/operation phase enter
enter the project premises without valid the
Page 17 of 23
project
premises
without
valid
‘Pollution Under Control’ certificate from ‘Pollution Under Control’ certificate from
competent Authority.
competent Authority.
B) COMPLIANCE TO ENVIRONMENTAL IMPACT ASSESSMENT GUIDANCE
MANUAL 2010 OF MoEF
S. No. Points as per EIA Guidance Manual
Status of Compliance
A.
Air Environment
1.
Wind erosion is a serious problem in areas Windbreaks and shelterbelts will be
where the ground is virtually bare and devoid provided to reduce wind erosion during
of vegetation. Vegetation methods are found to the construction phase.
be most effective in the form of windbreaks
and shelterbelts.
2.
Sprinkling of water and fine spray from Sprinkling will be provided during the
nozzles to suppress the dust.
3.
construction phase.
On-Road-Inspection should be done for black All the machineries used at site having
smoke generating machinery.
highest standard and of reputed make and
will be compiled with emission & noise
standards.
4.
Promotion of use of cleaner fuel should be Ultra low sulphur diesel (ULSD) (sulphur
done.
content less than 0.05%) wil be use for
running
of
DG
sets,
vehicles
and
construction machineries.
5.
All DG sets should comply emission norms The DG sets used in such a way that it
notified by MoEF.
will comply with the emission norms
notified by MoEF.
Page 18 of 23
S. No. Points as per EIA Guidance Manual
6.
Vehicles having pollution under
Status of Compliance
control It will be ensured that all the vehicles used
certificate may be allowed to ply.
for construction activities having valid
Pollution Under Check (PUC) certificates.
The vehicles without valid Pollution
Under Check (PUC) certificate is not
permitted at project site.
7.
Use of covering sheet to prevent dust Covering sheet will be use to prevent dust
dispersion at buildings and infrastructure sites, dispersion during the construction phase.
which are being constructed.
8.
Use of covering sheets should be done for Covering sheets will be use on trucks to
trucks to prevent dust dispersion from the prevent dust dispersion from the trucks.
trucks, implemented by district offices.
9.
Paving is a more permanent solution to dust During construction, access road has been
control, suitable for longer duration projects. covered with gravels to prevent dust
High cost is the major drawback to paving.
10.
emission.
Reducing the speed of a vehicle to 20 kmph Speed of the vehicles has beenrestricted
can reduce emissions by a large extent. Speed by erecting speed bumps at regular
bumps are commonly used to ensure speed intervals at project site and proper signage
reduction. In cases where speed reduction will be
provided for guided vehicular
cannot effectively reduce fugitive dust, it may movement and speed restrictions.
be necessary to divert traffic to nearby paved
areas.
11.
Material storages/ warehouses-Care should be Construction material will be stored in
taken to keep all material storages adequately storage yard.
covered and contained so that they are not
exposed to situations where winds on site
could lead to dust/ particulate emissions.
Fabrics and plastics for covering piles of soils
and debris is an effective means to reduce
fugitive dust.
Page 19 of 23
S. No. Points as per EIA Guidance Manual
Status of Compliance
B.
Noise Environment
Setting up the barriers: National Building Code The site has been enclosed with barricade
2005 suggests that design solutions such as wall around the project boundary.
barrier blocks should be used to reduce The DG sets will be acoustic enclosed
external LA10 noise levels to at least 60- which conforms to the permissible noise
70dB(A) at any point 1.0 m from any inward standards notified by MOEF.
looking façade.
C.
Water Environment
1.
Curing water should be sprayed on concrete Curing chemical will be applied to reduce
structures; free flow of water should not be the water demand.
allowed for curing.
2.
After liberal curing on the first day, all To save water curing chemicals will be
concrete structures should be painted with painted.
curing chemical to save water. This will stop
daily water curing hence save water.
3.
Concrete structures should be covered with Sewage treated water will be sprayed on
thick cloth/gunny bags and then water should concrete structures. As well as to reduce
be sprayed on them. This would avoid water the demand concrete structure will be
rebound and will
ensure sustained and cover with thick cloth/gunny bags.
complete curing.
4.
Ponds should be made using cement and sand Ponds will be made using cement and
mortar to avoid water flowing away from the sand mortar to avoid water flowing away
flat surface while curing
5.
from the flat surface while curing.
Water ponding should be done on all sunken Water ponding will be done.
slabs; this would also highlight the importance
of having an impervious formwork.
(C)
COMPLIANCE TO
CONSTRUCTION
NGT
S. No. NGT Order dated 10.04.2015
Page 20 of 23
ORDER
DATED
10.04.2015
Status of Compliance
RELATED
TO
S. No. NGT Order dated 10.04.2015
1.
Status of Compliance
Every builder or owner shall put tarpaulin on Tarpaulin covers were provided around
scaffolding around the area of construction and the
area
of
construction,
wherever
the building. No person including builder, required. No construction materials such
owner
can
be
permitted
to
store
any as cement, sand and aggregates was stored
construction material particularly sand on any at site.
part of the street, roads in any colony.
2.
The construction material of any kind that is Construction material on site will be fully
stored in the site will be fully covered in all covered.
respects so that it does not disperse in the Air
in any form.
3.
All the construction material and debris shall The trucks carrying construction materials
be carried in the trucks or other vehicles which and debris will be suitably covered by
are fully covered and protected so as to ensure tarpaulin and plastic sheets.
that the construction debris or the construction
material does not get dispersed into the air or
atmosphere, in any form whatsoever.
4.
The dust emissions from the construction site Water sprinkling system will be provided
should be completely controlled and all to control the dust emission.
precautions taken in that behalf.
5.
The vehicles carrying construction material Vehicles carrying construction material
and construction debris of any kind should be and construction debris will be cleaned
cleaned before it is permitted to ply on the road before it permitted to ply on the road after
after unloading of such material.
6.
unloading of such material.
Every worker working on the construction site All health and safety measures of workers
and involved in loading, unloading and will be taken during construction period.
carriage
of
construction
material
and
construction debris shall be provided with
mask to prevent inhalation of dust particles.
Page 21 of 23
S. No. NGT Order dated 10.04.2015
7.
Status of Compliance
Every owner and or builder shall be under First aid facility has been provided at the
obligation to
provide
all
medical
help, construction site.
investigation and treatment to the workers
involved in the construction of building and
carry of construction material and debris
relatable to dust emission.
8.
It shall be the responsibility of every builder to Construction material and debris waste
transport construction material and debris will be disposed off to construction site,
waste to construction site, dumping site or any dumping site or any other place in
other place in accordance with rules and in accordance with rules and in terms of this
terms of this order.
9.
order.
All to take appropriate measures and to ensure Regular sprinkling of water will be carried
that the terms and conditions of the earlier out at site at the construction.
order and these orders should strictly comply
with by fixing sprinklers, creations of green air
barriers.
10.
11.
Compulsory use of wet jet in grinding and Wet jet in grinding and stone cutting will
stone cutting.
be used.
Wind breaking walls around construction site.
Wind breaking walls will be provided
around the construction site.
12.
All the builders who are building commercial, Green area will be developed as per
residential complexes which are covered under approved building plan.
the EIA Notification of 2006 shall provide
green belt around the building that they
construct. All Authorities shall ensure that such
green belts are in existence prior to issuance of
occupancy certificate.
Page 22 of 23
Page 23 of 23