111 AGENDA ITEM BACKGROUND TO: GOVERNING BOARD DATE February 11, 2013 FROM: PRESIDENT SUBJECT: Facilities Master Plan Project Status REASON FOR BOARD CONSIDERATION ENCLOSURE(S) ITEM NUMBER Page 1 of 4 INFORMATION D.3 BACKGROUND: Major Projects under Construction (see next page) Administrator Initiating Item: Joe Nugent Victoria Lewis Academic and Professional Matter If yes, Faculty Senate Agreement Senate President Signature Yes No Yes No Final Disposition 112 Major Projects under Construction Health and Wellness Project This project has been certified and closed effective August 18, 2012 with DSA. Current Status Update: The majority of the equipment for the building has been purchased and installed; however, there are additional items to be purchased. Building 300 Renovation This project has been certified and closed effective October 28, 2011 with DSA. Current Status Update: A majority of the equipment has been purchased and installed, including furniture and classroom computers; however, there are additional items to be purchased. Watsonville Green Technology Center This project is substantially complete and occupied as of fall 2012. The LEED certification process has also been completed and the Solari Green Technology Center is now officially LEED Platinum Certified with the U.S. Green Building Counsel. Current Status Update: This project is substantially complete with the exception of minor finishing touches as well as some remaining furniture and equipment. This project has been submitted to DSA for approval. Building 800 STEM Remodel: In 2012 Building 800 occupants were relocated and the building will be fully remodeled. Plans and specifications were approved by DSA in September 2012. Abatement of the building occurred in September and October 2012. Bid proposals for the renovation work were received on November 27, 2012. The contract for the renovation work has been awarded to Kent Construction of Gilroy, CA, in the amount of $3,491,895. The total project construction costs are estimated to be $5,495,702. There are three funding sources for the project: $1,952,530—federal Title III Science Technology Engineering and Mathematics (STEM) grant from the Department of Education to fund design and partial construction. $ 250,000—A gift of from the Peggy and Jack Baskin Foundation was received in the amount of 894,495 in August 2012. $250,000 of the gift will be used to offset the additional construction costs of the project. $3,293,172—Measure D bond. $5,495,702 Total estimated project costs 113 Current Status Update: A pre-construction meeting was held on December 19, 2012 and the general contractor, Kent Construction, commenced on the Demolition work mid December, 2012. The project is progressing per the schedule. Building 600 Bio/Chem Classroom Renovation Project: The Dental Hygiene Program previously occupied the west end of building 600 prior to relocating to the new Health Wellness Building in 2010. This space will be designated as Biology and Chemistry classroom and laboratory space and is currently in the program planning and design phase of the project. An engineer’s estimate of the construction cost is expected mid January and the project budget and schedule will be updated once the information is collected. Awards of Informal Bids under the Uniform Construction Cost Accounting System (UCC): By adopting the Uniform Public Construction Cost Accounting System, the Board authorized the President or his/her designee to enter into agreements with low bidders using the informal bidding process with the provision that the successful awards would be presented to the Board as an information item. This system enables the District to 1) informally bid projects under $175,000 to prequalified contractors, 2) more efficiently and effectively manage small to medium sized projects, and 3) contract with local contractors who are deemed “qualified” bidders. No informal bids have occurred during this reporting period. 114 Facilities Master Plan Major Projects Through December 31, 2012 Projects In Process Health and Wellness Equipment Building 300 Renovation Equipment Watsonville Green Technology Center Watsonville GTC Equipment Building 800 Renovation Planned Substantial Completion Date Spring 2011 Fall 2010 Fall 2011 Funding Source Original Adjusted Project Budget Project Budget Paid to Date Encumbered to Date Balance (unencumbered) Contingency Change Orders to date Paid + Enc as % of Proj Budget State Capital Outlay Funds 1,185,000 1,185,000 947,719 59,632 177,649 118,500 85% Measure D Total Project State Capital Outlay Funds Measure D Total Project EDA Funds Foundation Measure D Total Project 1,105,493 2,290,493 931,000 931,000 1,862,000 3,365,000 100,000 7,100,000 10,565,000 1,105,493 2,290,493 931,000 931,000 1,862,000 3,365,000 100,000 7,148,000 10,613,000 1,077,348 2,025,067 758,913 758,913 1,517,826 3,365,000 100,000 7,081,275 10,546,275 17,071 76,703 0 0 0 0 0 30,759 30,759 11,074 188,723 172,087 172,087 344,174 0 0 35,965 35,965 110,549 229,049 93,100 93,100 186,200 336,500 10,000 714,800 1,061,300 99% 92% 82% 82% 82% 100% 100% 99% 100% 400,000 437,000 259,887 77,845 99,267 43,700 77% 1,952,530 1,500,000 3,452,530 1,952,530 3,293,172 250,000 5,495,702 332,645 212,035 0 544,680 61,734 228,322 0 290,056 1,558,151 2,852,815 250,000 4,660,966 195,253 329,317 25,000 549,570 29,578 20% 13% 0% 15% 9,490 Spring 2013 Total Project Fall 2013 STEM Grant Funds Measure D Donation Total Project -152,600 29,578 VAPA Remediation Summer 2012 Fall 2013 Building 600 Remodel Fall 2013 Bond Measure D only 1,000,000 1,200,000 58,362 148,460 993,178 120,000 17% Smart Classrooms Fall 2013 Bond Measure D only 243,587 323,587 268,887 5,460 49,241 32,359 85% Campus Signage DSA Closeout TBD TBD Summer 2012 Bond Measure D only Bond Measure C only 323,291 61,337 323,291 61,337 275,093 47,393 0 0 48,198 13,944 32,329 6,134 85% 77% Total Project 140,000 140,000 119,844 3,853 16,304 14,000 8,413 88% Total 23,347,256 25,370,428 16,493,630 1,533,341 7,343,457 2,537,043 -105,119 71% State Capital Outlay Funds 10,490,000 10,490,000 10,490,000 0 0 Measure C Measure D Project Total State Capital Outlay Funds Measure C Measure D Project Sub-total State Capital Outlay Funds Measure D Project Sub-total Total Project 121,741 15,067,134 25,678,875 20,357,000 5,345,114 51,909,024 77,611,138 1,136,000 1,126,453 2,262,453 79,873,591 1,051,000 33 1,166,000 2,217,033 107,769,499 121,741 15,072,637 25,684,378 20,357,000 5,345,114 51,893,312 77,595,426 1,136,000 1,126,453 2,262,453 79,857,879 1,051,000 33 1,116,963 2,167,996 107,710,253 121,741 15,060,397 25,672,138 20,357,000 5,345,114 51,893,312 77,595,426 1,136,000 1,126,453 2,262,453 79,857,879 1,051,000 33 1,116,963 2,167,996 107,698,013 0 12,240 12,240 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1,078,021 100% 583,784 100% 131,186 1,792,991 100% 100% Building 800 Moves South Perimeter Road Total Projects in Process Bond Measure D only 248,283 313,283 298,567 10,730 3,986 31,328 Measure C Measure D Total Project 1,915,130 845,605 2,760,735 1,915,130 395,605 2,310,735 528,643 3,105 531,748 889,476 0 889,476 497,010 392,500 889,510 191,513 39,561 231,074 74% 1% 62% 99% Completed Projects Health and Wellness Center and Sitework VAPA Construction VAPA Equipment Spring 2011 Complete Complete State Capital Outlay Funds Building 300 Renovation Completed Projects Fall 2010 Measure C Measure D Project Total 3 of 5 0 0 0 0 0 0 0 12,240