63 AGENDA ITEM BACKGROUND TO: GOVERNING BOARD DATE October 8, 2012 FROM: PRESIDENT SUBJECT: Facilities Master Plan Project Status REASON FOR BOARD CONSIDERATION ENCLOSURE(S) ITEM NUMBER INFORMATION Page 1 of 5 D.2 BACKGROUND: Major Projects under Construction (see next page) Administrator Initiating Item: Joe Nugent Victoria Lewis Academic and Professional Matter If yes, Faculty Senate Agreement Senate President Signature Yes No Yes No Final Disposition 64 Major Projects under Construction Health and Wellness Project This project has been certified and closed effective August 18, 2012 with DSA. Current Status Update: The majority of the equipment for the building has been purchased and installed; however, there are additional items to be purchased. Building 300 Renovation This project has been certified and closed effective October 28, 2011 with DSA. Current Status Update: A majority of the equipment has been purchased and installed, including furniture and classroom computers; however, there are additional items to be purchased. Watsonville Green Technology Center The District and the City of Watsonville closed escrow on the purchase of the Watsonville Library on July 15, 2008. Since then, the college has demolished the building in order to construct a 14,000 sq. ft. Community Education Center. The District received a grant for $2.5 million from Economic Development Agency for the project, and the grant was augmented by $865,000 to help fund an upgrade to a Platinum Level LEED certified “green” building. The Division of State Architect (DSA) approved the plans in June o2010 and EDA approved the plans and specifications in July 2010. The project went to bid in August 2010. In October, 2010 the Board awarded the bid to Dilbeck and Sons and approved an augmentation to the budget of $517,000. A deductive change order for the value engineering items discussed at the October Board meeting was approved at the November Board Meeting. The District has received a generous donation from the Ley Family of $100,000 for construction to add back some of the items that were placed on hold. Current Status Update: This project is substantially complete with the exception of minor finishing touches as well as furniture and equipment. This project is ready to be submitted to DSA for approval. Staff is waiting for DSA approval of all change orders in order to submit for final certification from DSA for the construction phase of the project. Staff is also working with Economic Development Agency to receive the remaining grant funds and provide the necessary close out documentation for the project. The September 7, 2012 grand opening was well attended and received by the community. 65 Building 800 STEM Remodel: Building 800 will be fully remodeled. There are two funding sources for this project. There is a Federal Grant (STEM Grant) from the Department of Education in the amount of $1,952,530 to fund design and partial construction. Fund 47 bond was slated to fund $1,500,000 for the balance of the construction pending the engineer’s estimate. Current Status Update: Due to the increase in square footage to the project, the Engineer’s estimate revealed that the District should plan for a total construction cost of $3,354,294. This will require an additional $750,000 contribution from Bond funds and will bring the estimated total project cost to $4,202,530. This will allow for an additional 11,860 sq. ft. of space to be renovated and complete all necessary modifications to the entire 20,892 sq. ft. of the 800 building. A gift of $894,495 was received from the Peggy and Jack Baskin Foundation in August, 2012. $250,000 of the grant will be used to offset the additional construction costs of the project. The project is in the Construction Documents phase and plans and specifications were presented to DSA in June. Demolition is currently scheduled for the fall of 2012, construction fall 2012 through summer 2013 with classes to begin in fall 2013. 800 Bldg. Moves Phase I: Complete The 800 building moves were initiated in December and substantially complete in the beginning of February. This phase of the project required all administrative offices and categorical programs such as, Fast track to work, Student Job Placement, Puente and Cap to be relocated to SAC west and other programs and offices to be relocated. 800 Bldg. Moves Phase II: The DSPS (Disabled Student Programs & Services) and the Physics Department were relocated as part of the “800 Bldg. Moves Phase II” portion of the project. The overall budget for this portion of the work is $313,283 Measure D funds. The original project was $248,283, but was increased $65,000 in June 2012 in order to accommodate the additional moves. Awards of Informal Bids under the Uniform Construction Cost Accounting System (UCC): By adopting the Uniform Public Construction Cost Accounting System, the Board authorized the President or his/her designee to enter into agreements with low bidders using the informal bidding process with the provision that the successful awards would be presented to the Board as an information item. This system enables the District to 1) informally bid projects under $175,000 to prequalified contractors, 2) more efficiently and effectively manage small to medium sized projects, and 3) contract with local contractors who are deemed “qualified” bidders. Award of Bid: B13-03 AEC VAPA Bldg 5000 Boiler Replacement In the spring of 2012, a study was conducted to identify corrective measures related to the boiler systems in VAPA building 5000. This study and subsequent redesign was performed by Jim Young Engineering, Inc. which provided plans and specifications that were used to bid the work. The advertised Engineer’s estimate for this project was $170,000; therefore, this project was bid under the “Uniform Construction Cost Accounting System.” 66 Bid proposals were received by the Purchasing Department on September 18, 2012 and five general contractors participated in the process providing bids to the District. A blind bid opening process was utilized for this bidding process. Of the five bidders, Mike Hinson Construction was lowest responsible bidder in the amount of $111,500 on the base bid. Alternate bid items were provided but will not be awarded. Bid Results: Contractor Name: Base Bid Amount Alternate Bid Item Total Bid Amount Michael Wolcott Const. Clarke Const., Inc. Avila Brothers, Inc. $123,646 $124,099 $132,791 $144,444 $111,500 $38,929 $56,702 $50,013 $44,444 $45,000 $162,575 $180,801 $182,804 $188,888 $156,500 Cen‐Con, Inc. Mike Hinson Const. Staff will contract directly with Siemens Controls in order to reduce the cost to the project and this will eliminate the need for the “add alternate.” Despite this reduction in cost to the project the overall budget will require an augmentation of $35,000. The lowest responsive bid proposal received by the District is from Mike Hinson Construction, in the amount of $111,500. 67 Facilities Master Plan Major Projects Through August 31, 2012 Projects In Process Health and Wellness Center and Sitework Planned Substantial Completion Estimated % Completion Date Spring 2011 99% Pending DSA approval Health and Wellness Equipment Spring 2011 98% Building 300 Renovation Equipment Watsonville Green Technology Center Fall 2010 90% Fall 2011 95% Watsonville GTC Equipment Building 800 Renovation Building 800 Moves VAPA Remediation Fall 2013 Summer 2012 Fall 2013 3% 98% 6% Smart Classrooms Campus Signage TBD DSA Closeout TBD Summer 2012 99% Total Projects in Process VAPA Construction Complete 100% VAPA Equipment Complete 100% Fall 2010 99% Completed Projects 10/2/2012 Paid to Date Encumbered to Date Balance (unencumbered) Contingency Change Orders to date Total Project % of Budget Paid to date 10,490,000 10,490,000 10,490,000 0 0 1,049,000 100.0% Measure C Measure D Project Sub-total 121,741 15,067,134 25,678,875 121,741 15,067,134 25,678,875 121,741 14,997,742 25,609,483 0 8,240 8,240 0 61,152 61,152 12,174 1,506,713 2,567,888 100.0% 99.5% 99.7% State Capital Outlay Funds 1,185,000 1,185,000 857,240 90,517 237,243 118,500 72.3% Measure D Project Sub-total Total Project State Capital Outlay Funds Measure D Project Sub-total Total Project EDA Funds Foundation Measure D Total Project 1,105,493 2,290,493 27,969,368 931,000 931,000 1,862,000 4,079,033 3,365,000 100,000 7,100,000 10,565,000 1,105,493 2,290,493 27,969,368 931,000 931,000 1,862,000 4,079,033 3,365,000 100,000 7,168,000 10,633,000 1,075,693 1,932,933 27,542,416 758,913 768,620 1,527,533 3,705,969 3,365,000 100,000 7,059,766 10,524,766 3,652 94,169 102,409 0 0 0 0 0 0 117,613 117,613 26,148 263,391 324,543 172,087 162,380 334,467 373,064 0 0 -9,379 -9,379 110,549 229,049 2,796,937 93,100 93,100 186,200 407,903 336,500 10,000 716,800 1,063,300 97.3% 84.4% 98.5% 81.5% 82.6% 82.0% 90.9% 100.0% 100.0% 98.5% 99.0% 400,000 437,000 127,708 153,152 156,140 43,700 STEM Grant Funds Measure D Total Project Measure D Total Project Measure C Measure D Total Project 1,952,530 1,500,000 3,452,530 248,283 248,283 1,915,130 845,605 2,760,735 1,952,530 2,250,000 4,202,530 313,283 313,283 1,915,130 845,605 2,760,735 237,854 24,792 262,647 285,928 285,928 251,844 180 252,024 94,345 165,481 259,826 10,308 10,308 896,681 0 896,681 1,620,331 2,059,727 3,680,058 17,047 17,047 766,605 845,425 1,612,030 195,253 225,000 420,253 31,328 31,328 191,513 84,561 276,074 Measure D 1,000,000 1,000,000 9,661 50,720 939,618 100,000 Measure D 243,587 323,587 198,998 66,050 58,540 32,359 61.5% Measure D Total Project Measure C Total Project 323,291 323,291 61,337 61,337 323,291 323,291 61,337 61,337 275,093 275,093 36,815 36,815 0 0 - 48,198 48,198 24,522 24,522 32,329 32,329 6,134 6,134 85.1% 85.1% 60.0% 60.0% Total Project 140,000 140,000 119,389 1,214 19,397 14,000 8,413 85.3% 1,657,973 7,243,776 5,224,316 1,074,510 83.0% 583,784 100.0% 100.0% 100.0% 96.7% 98.3% 99.9% Total 51,243,164 52,243,164 43,341,414 State Capital Outlay Funds 20,357,000 20,357,000 20,357,000 0 Measure C Measure D Project Sub-total 5,345,114 51,909,024 77,611,138 5,345,114 51,909,024 77,611,138 5,345,114 51,893,312 77,595,426 0 15,712 15,712 State Capital Outlay Funds 1,136,000 1,136,000 1,136,000 0 Measure D Project Sub-total Total Project 1,126,453 2,262,453 79,873,591 1,051,000 33 1,166,000 2,217,033 82,090,624 1,126,453 2,262,453 79,873,591 1,051,000 33 1,166,000 2,217,033 82,090,624 1,126,453 2,262,453 79,857,879 1,051,000 33 1,127,403 2,178,436 82,036,315 0 0 15,712 0 0 38,597 38,597 54,309 State Capital Outlay Funds Building 300 Renovation Adjusted Project Budget State Capital Outlay Funds Total Project Building 600 Remodel South Perimeter Road Funding Source Original Project Budget Measure C Measure D Project Sub-total 1 of 1 0 0 0 0 - 105,100 3 116,600 221,703 221,703 1,078,021 1,078,021 131,186 -152,600 9,490 9,490 12.2% 1.1% 6.2% 91.3% 91.3% 13.2% 0.0% 9.1% 1.0% 131,186 714,970