183 AGENDA ITEM BACKGROUND TO: GOVERNING BOARD DATE April 8, 2013 FROM: PRESIDENT SUBJECT: ENCLOSURE(S) Facilities Master Plan Project Status REASON FOR BOARD CONSIDERATION INFORMATION ITEM NUMBER Page 1 of 6 H.9 BACKGROUND: Major Projects under Construction (see next page) Administrator Initiating Item: Joe Nugent Victoria Lewis Academic and Professional Matter If yes, Faculty Senate Agreement Senate President Signature Yes No Yes No Final Disposition 184 Major Projects under Construction Arts Education Remediation Project. Several projects that encompass the remediation of the VAPA complex including but are not limited to repairs to the heating and venting systems, building leaks, door systems repairs and accessibility, music recital hall acoustics, sewer line repairs, theater storage and equipment fencing have been addressed and/or are in process. Health and Wellness Project This project has been certified and closed effective August 18, 2012 with DSA. Current Status Update: The majority of the equipment for the building has been purchased and installed; however, there are additional items to be purchased. Building 300 Renovation This project has been certified and closed effective October 28, 2011 with DSA. Current Status Update: A majority of the equipment has been purchased and installed, including furniture and classroom computers; however, there are additional items to be purchased. Watsonville Green Technology Center This project is substantially complete and occupied as of fall 2012. The LEED certification process has also been completed and the Solari Green Technology Center is now officially LEED Platinum Certified with the U.S. Green Building Counsel. Current Status Update: This project is substantially complete with the exception of minor finishing touches as well as some remaining furniture and equipment. This project has been certified by DSA. Building 800 STEM Remodel: Building 800 occupants were relocated in 2012 in order for the building to be fully remodeled. Plans and specifications were approved by DSA in September 2012. Abatement of the building occurred in September and October 2012. Bid proposals for the renovation work were received on November 27, 2012. The contract for the renovation work has been awarded to Kent Construction of Gilroy, CA, in the amount of $3,491,895. 185 The total Building 800 project construction costs are estimated to be $5,495,702. There are three funding sources for the project: $1,952,530—federal Title III Science Technology Engineering and Mathematics (STEM) grant from the Department of Education to fund design and partial construction. $ 250,000—A gift of from the Peggy and Jack Baskin Foundation was received in the amount of 894,495 in August 2012. $250,000 of the gift will be used to offset the additional construction costs of the project. $3,293,172—Measure D bond. $5,495,702 Total estimated project costs A pre-construction meeting was held on December 19, 2012 and the general contractor, Kent Construction, commenced on the Demolition work mid-December, 2012. Current Status Update: Sub grade plumbing and electrical work on the interior of the building is complete. Rough framing and mechanical ducting is in process. The project is currently 4 days behind schedule but the contractor is confident that the time will be recovered over the next few weeks. Building 600 Bio/Chem Classroom Renovation Project: The Dental Hygiene Program previously occupied the west end of building 600 prior to relocating to the new Health Wellness Building in 2010. This space will be designated as Biology and Chemistry classroom and laboratory space and is currently in the program planning and design phase of the project. An engineer’s estimate of the construction cost is expected mid-January and the project budget and schedule will be updated once the information is collected. Current Status Update: An informal bid was conducted in order to begin hazardous abatement of the area. Notice to Proceed B13-04 Bldg. 600 Hazmat Abatement Old Dental Hygiene Clinic was awarded to Coast wide Environmental in the amount of $64,375. There were only two contractors that submitted proposals for this work. The other contractor, Parc Environmental, submitted a proposal in the amount of $92,072.50. Building 100 IT Main Distribution Frame (MDF) Project: The 100 building basement is the central distribution and location of DATA and communication systems for all of upper campus. This space is exposed to outside elements, such as weather and rodents due to the open entrance vault and this is detrimental to the systems housed in this space. This project will relocate data cabling, telecommunication lines and equipment and the reconstruct wall sections where necessary to prevent loss of essential college systems operations. Building 100 Office Remodel Project: There are numerous functions in the 100 that require reconfiguration in order to serve student needs and improve access specific to the counseling and the transfer center. This project consists of creating an open counter at the east entrance which will require the relocation and reconfiguration of other office and conference spaces. 186 Building 100 HVAC Project: The 100 building has been home to various administrative functions over the course of time and thus has had considerable redistribution of activities. Very few areas of the building floor plan resemble original construction layout except for the over 50 year old dysfunctional HVAC system. This project will address the much needed reconfiguration of the existing duct work as well as the heating and cooling needs of the main floor and IT MDF equipment room below. Awards of Informal Bids under the Uniform Construction Cost Accounting System (UCC): By adopting the Uniform Public Construction Cost Accounting System, the Board authorized the President or his/her designee to enter into agreements with low bidders using the informal bidding process with the provision that the successful awards would be presented to the Board as an information item. This system enables the District to 1) informally bid projects under $175,000 to prequalified contractors, 2) more efficiently and effectively manage small to medium sized projects, and 3) contract with local contractors who are deemed “qualified” bidders. 187 Facilities Master Plan Major Projects Through March 29, 2013 Projects In Process Health and Wellness Equipment Planned Substantial Completion Date Spring 2011 Building 300 Renovation Equipment Fall 2010 Watsonville Green Technology Center Fall 2011 Watsonville GTC Equipment Building 800 Renovation Funding Source Original Project Budget Adjusted Project Budget Paid to Date Encumbered to Date Balance (unencumbered) Contingency 1,185,000 1,185,000 973,880 33,522 177,598 118,500 85% Measure D Total Project State Capital Outlay Funds Measure D Total Project EDA Funds Foundation Measure D Total Project 1,105,493 2,290,493 931,000 931,000 1,862,000 3,365,000 100,000 7,100,000 10,565,000 1,105,493 2,290,493 931,000 931,000 1,862,000 3,365,000 100,000 7,148,000 10,613,000 1,095,004 2,068,883 758,913 758,913 1,517,826 3,365,000 100,000 7,057,250 10,522,250 9,898 43,419 0 0 0 0 0 6,517 6,517 592 178,190 172,087 172,087 344,174 0 0 84,233 84,233 110,549 229,049 93,100 93,100 186,200 336,500 10,000 714,800 1,061,300 -152,600 100% 92% 82% 82% 82% 100% 100% 99% 99% 400,000 437,000 335,062 6,875 95,063 43,700 78% 1,952,530 1,500,000 3,452,530 1,952,530 3,293,172 250,000 5,495,702 748,041 620,596 0 1,368,638 992,371 1,959,658 0 2,952,028 212,118 712,918 250,000 1,175,036 195,253 329,317 25,000 549,570 34,998 89% 78% 0% 79% 248,283 313,283 302,151 7,560 3,572 31,328 9,490 99% Measure C Measure D Total Project 1,915,130 845,605 2,760,735 1,915,130 395,605 2,310,735 1,219,773 4,410 1,224,183 297,588 0 297,588 397,769 391,195 788,964 191,513 39,561 231,074 37,569 79% 1% 66% Spring 2013 Total Project Fall 2013 STEM Grant Funds Measure D Donation Total Project VAPA Remediation Building 600 Remodel Fall 2013 Bond Measure D only 1,000,000 1,200,000 121,943 106,050 972,007 120,000 Smart Classrooms Fall 2013 Bond Measure D only 243,587 323,587 239,082 41,939 42,566 32,359 Campus Signage DSA Closeout Building 100 IT MDF TBD TBD Fall 2013 Bond Measure D only Bond Measure C only Bond Measure D only 323,291 61,337 247,720 323,291 61,337 247,720 275,093 48,953 0 0 0 0 48,198 12,384 247,720 Building 100 Office Remodel Spring 2014 Bond Measure D only 115,670 115,670 0 0 Building 100 HVAC Spring 2014 Bond Measure D only 371,295 371,295 0 23,941,941 25,965,113 18,024,064 Total Projects in Process 3/29/2013 Paid + Enc as % of Proj Budget State Capital Outlay Funds Summer 2012 Fall 2013 Building 800 Moves Change Orders to date Bond Measure D only Total 1 of 2 19% 506 87% 32,329 6,134 24,772 0 85% 80% 0% 115,670 11,567 0 0% 0 371,295 37,130 0 0% 3,461,977 4,479,071 2,596,511 -70,037 83% 188 Major Completed Projects Health and Wellness Center and Sitework VAPA Construction VAPA Equipment Spring 2011 Complete Complete State Capital Outlay Funds 10,490,000 10,490,000 10,490,000 0 0 Measure C Measure D Project Total 121,741 15,067,134 25,678,875 121,741 15,072,637 25,684,378 121,741 15,060,397 25,672,138 0 6,958 6,958 0 5,282 5,282 State Capital Outlay Funds 20,357,000 20,357,000 20,357,000 Measure C Measure D Project Sub-total 5,345,114 51,909,024 77,611,138 5,345,114 51,893,312 77,595,426 5,345,114 51,893,312 77,595,426 State Capital Outlay Funds 1,136,000 1,136,000 1,136,000 0 1,126,453 2,262,453 79,873,591 1,051,000 33 1,166,000 2,217,033 107,769,499 1,126,453 2,262,453 79,857,879 1,051,000 33 1,116,963 2,167,996 107,710,253 1,126,453 2,262,453 79,857,879 1,051,000 33 1,116,963 2,167,996 107,698,013 0 0 0 0 0 0 0 5,282 Measure D Project Sub-total Total Project State Capital Outlay Funds Building 300 Renovation Completed Projects 3/29/2013 Fall 2010 Measure C Measure D Project Total 2 of 2 1,078,021 100% 583,784 100% 131,186 1,792,991 100% 100% 0 0 0 0 0 0 0 0 6,958 0 0 0