57 AGENDA ITEM BACKGROUND TO: GOVERNING BOARD DATE January 9, 2012 FROM: PRESIDENT SUBJECT: Facilities Master Plan Project Status REASON FOR BOARD CONSIDERATION INFORMATION ITEM NUMBER ENCLOSURE(S) Page 1 of 4 D.2 BACKGROUND: Major Projects under Construction (see next page) Administrator Initiating Item: Joe Nugent Victoria Lewis Academic and Professional Matter If yes, Faculty Senate Agreement Senate President Signature Yes No Yes No Final Disposition 58 Measure D Funded Facilities Master Plan Projects November 30, 2011 PROGRESS REPORT Note: Project Health and Wellness Center and Sitework Health and Wellness Equipment Building 300 Renovation Building 300 Renovation Equipment Watsonville Green Technology Center Total Measure D Funded Projects in Progress Measure D funded projects are outline in the following schedules There are references to other funding sources when the project has funding sources in addition to Measure D. E A B C D F [d+e] Planned Completion Date Fall 2011 Spring 2012 Fall 2010 Spring 2012 Spring 2012 Funding Source State Capital Outlay Funds Measure C Measure D Project Sub-total State Capital Outlay Funds Measure D Project Sub-total Total Project State Capital Outlay Funds Measure C Measure D Project Sub-total State Capital Outlay Funds Measure D Project Sub-total Total Project EDA Funds Foundation Measure D Project Total Totals are for Measure D Only Approved Paid to Date Original Project Change Orders Revised Budget Budget 11/30/2011 G [c-f] Amount Encumbered Total Committed Remaining Balance to be paid Contracts & Total Cost vs C.O. Project Total Cost Revised Budget 10,490,000 0 10,490,000 10,490,000 0 10,490,000 0 121,741 15,067,134 25,678,875 0 1,078,021 1,078,021 121,741 15,067,134 25,678,875 121,741 14,929,406 25,541,147 0 117,067 117,067 121,741 15,046,473 25,658,214 0 20,661 20,661 1,185,000 0 1,185,000 770,667 17,819 788,486 396,514 1,105,493 2,290,493 27,969,368 0 0 1,078,021 1,105,493 2,290,493 27,969,368 1,065,755 1,836,422 27,377,569 14,241 32,060 149,127 1,079,996 1,868,482 27,526,696 25,497 422,011 442,672 1,051,000 0 1,051,000 1,047,739 0 1,047,739 3,261 33 1,166,000 2,217,033 0 131,186 131,186 33 1,166,000 2,217,033 33 1,114,209 2,161,982 0 25,623 25,623 33 1,139,832 2,187,605 0 26,168 29,429 931,000 0 931,000 302,563 479,335 781,898 149,102 931,000 1,862,000 4,079,033 3,365,000 100,000 7,500,000 10,965,000 0 0 131,186 0 0 -152,600 -152,600 931,000 1,862,000 4,079,033 3,365,000 100,000 7,500,000 10,965,000 312,270 614,833 2,776,815 2,885,874 0 6,374,800 9,260,674 350,672 830,007 855,630 479,126 0 564,770 1,043,896 662,942 1,444,840 3,632,445 3,365,000 0 6,939,570 10,304,570 268,058 417,160 446,589 0 100,000 560,430 660,430 25,769,627 1,056,607 25,769,627 23,796,440 1,072,373 24,868,813 900,814 59 Major Projects under Construction Arts Education Classrooms Project This project is in the final closeout process with DSA. One change order remains to be approved by DSA. Staff will submit the complete closeout package to DSA for final certification upon receipt of final change order. Current Status Update: Waiting on final change order approval to submit for final certification from DSA. Health and Wellness Project The Allied Health project consists of two buildings totaling 57,000 square feet, and is the new home for programs such as Nursing, Radiology Technology, Medical Assisting, Dental Hygiene, Health and Wellness, and the Stroke Center. RMW is the architect and Soltek Pacific is the contractor. Construction began in May 2008 and the buildings are 100% complete. Staff is in the process of closing out the project. All remaining issues have been resolved with the contractor. Current Status Update: The majority of the equipment for the building has been purchased and installed. There are additional items to be purchased. Construction of an ADA ramp and sidewalk from parking lot J to the center of the two buildings is complete. The two ADA accessible parking spaces and adjoining ramp are complete. The installation of carpet in rooms H.W. 2212 and H.W. 2214 are expected to accomplish final acoustical corrections. The project is being closed out and unused funding is reverting back to the bond fund. Building 300 Renovation On February 1, 2010 the Governing Board approved an award of bid to Tombleson Construction of Salinas in the amount of $1,560,136 to renovate the 300 building. 12,523 square feet was remodeled and reconstructed to provide ten general purpose classrooms, two large assembly/classrooms and nine BELA division offices in spring 2010. The renovation is substantially complete. Current Status Update: The building has been occupied beginning spring semester 2011. The project is being closed out and unused funding is reverting back to the bond fund. DSA is currently processing requests for project closeout they received in the month of February 2011. The District is awaiting final closeout and certification from DSA. Some of the equipment has been purchased and installed. Watsonville Green Technology Center The District and the City of Watsonville closed escrow on the purchase of the Watsonville Library on July 15, 2008. Since then, the college has demolished the building in order to construct a 14,000 square foot Community Education Center. The District received a grant for $2.5 million from Economic Development Agency for the project, and the grant was augmented by $865,000 to help fund an upgrade to a Platinum Level LEED certified “green” building. The Division of State Architect (DSA) approved the plans in June of 2010 and EDA approved the plans and specifications in July 2010. The project went to bid in August 2010. In October, the Board approved Dilbeck and Sons as well as an augmentation to 60 the budget of $517,000. A deductive change order for the value engineering items discussed at the October Board meeting was approved at the November Board Meeting. The District has received a generous donation from the Ley Family of $100,000 for construction to add back some of the items that were placed on hold. Current Status Update: Staff is working on creating the punch List with the design team. Buildings will be substantially complete in January 2012. Data wiring and data connection to the existing campus network is in progress. Awards of Informal Bids under the Uniform Construction Cost Accounting System (UCC): By adopting the Uniform Public Construction Cost Accounting System, the Board authorized the President or his/her designee to enter into agreements with low bidders using the informal bidding process with the provision that the successful awards would be presented to the Board as an information item. This system enables the District to 1) informally bid projects under $175,000 to prequalified contractors, 2) more efficiently and effectively manage small to medium sized projects, and 3) contract with local contractors who are deemed “qualified” bidders. None this month