Clause
Document Number
FLOW CHART / CONTROL PLAN
Effective Date Revision No.
03/19/2013
A
Responsible Organization
QY10
Approved by
Quality
Tim Donkin
If QY-10 is listed as part of the Purchase Order (PO), prior to First Article Inspection (FAI) or First
Piece Inspection (FPI) a Process Flow Chart/Control Plan (FP/CP) is to be developed using L-3
CPS’s Work Sheet and Instructions. Suppliers may utilize their company standard form provided all
areas required by L-3 CPS form are addressed. The request for FPI will not be processed without
the Flow Chart/Control Plan completed in its entirety in accordance with instructions.
The purpose of FC/CP is to provide a logical pictorial representation of the manufacturing process
flow and process control points. The Supplier develops and maintains FC/CP. For any updates to
the FC/CP prior approval by L-3 CPS is required. This document can be used as an aid for work
station development, identifying process control points, defining the methods being used at these
control points, and must include all Key Product Characteristics such as KPC/QARs/QAPs and all
out sourcing identification.
A walk through of the manufacturing process to include a review of the FC/CP and work instructions
should be anticipated as a means to validate process requirements. The FC/CP will be used as part
of the Process/Product Validation at FAI / FPI and on future L3-CPS audits. See instructions on last
page of the Flow Chart / Control Plan Work Sheet located at the L-3 CPS website address:
www.L-3com.com/cps
Summary
•
•
•
•
•
•
•
FC/CP must contain sufficient detail to depict the Manufacturing Process
FC/CP completed work sheet required as part of PO requirement or QY-2 submittal
Develop appropriate Work & Inspection Instructions
Supplier ensures that the FC/CP is accurate
L-3 CPS/Supplier evaluation of FC/CP to actual process
Submit QY-10 Work Sheet with FAI / FPI request to your respective SQA regional lead
For any proposed updates to the FC/CP prior approval by L-3 CPS is required.
History of Changes
Revision
Number
A
Revision
Date
03/19/2013
Revision Summary
Initial Release ECN-00053
The holder of this printed document is responsible for verifying that it is the current version.