BERNARDS TOWNSHIP SEWERAGE AUTHORITY MEETING MINUTES OCTOBER 11, 2011 CALL TO ORDER The chairperson called the meeting to order at 6:30 PM. Those assembled saluted the flag and the chairperson read the open public meeting statement in accordance with the law. ROLL CALL Present: Absent: Also Present: Carpenter, Gaziano, Malay, Spitzer Pavlini Director Timko, Collections Supervisor Plesnarski, Hatch Mott MacDonald Consultant Wohlleb, Attorney Belardo EXECUTIVE SESSION-RESOLUTION #1176 Motioned by Carpenter seconded by Spitzer to approve Resolution #1176 be approved and the meeting temporarily adjourned to executive session at 6:33 PM. The meeting resumed in open session at 6:40 PM. CORRESPONDENCE None PUBLIC COMMENT None APPROVAL OF MINUTES Approval of the Minutes of 9/13/2011 was tabled until the meeting of 11/29/2011. Roll Call Aye: Nay: Motion: Carpenter, Gaziano, Malay, Spitzer Carried CONSENT AGENDA The items listed within the consent agenda portion of the meeting have been referred to the Authority for reading and study, a copy placed on the bulletin board of the meeting room and are considered routine and will be enacted by one motion of the Authority with no separate discussion. If separate discussion is required, the item may be removed from the agenda by the Authority action and placed on the regular agenda under new business. a. b. c. d. e. f. g. h. Resolution #1177 – Annin Road Generation Project Budget Transfer Resolution #1178- Annin Road - Bid Award-ALM Electric Resolution #1179 – Annin Road Construction Management Services-HMM Resolution #1180-FST Building - Bid Award-JoGi Construction Resolution #1181-FST Building Construction Management Services-HMM Resolution #1182-Raw Sewage Pumps – Electrical Design and Construction Resolution #1183-Raw Sewage Pumps Construction Management Services-HMM Resolution #1184-Climber Screen Construction Management Services Motioned by Spitzer, seconded by Malay, to approve the Consent Agenda. Roll Call Aye: Carpenter, Gaziano, Malay, Spitzer Nay: Motion: Carried ACTION/DISCUSSION a. Discussion-Rate Stabilization Policy b. Consulting Engineer’s Report BTSA ENGINEER’S REPORT October 2011 Meeting DEVELOPERS PROJECTS: AUTHORITY PROJECTS: Belt Filter Press Construction The final inspection from the building department and installation of the reversible motor starter was scheduled for Thursday, October 6th. Spectraserve is coordinating with Komline and Fluid Dynamics to correct the communication problem between the filter press and one of the pumps and to correct the discrepancy between the filter press and the polymer speed control. The missing spare parts have been ordered. Lock rekeying is in process. Red line markups of design plans should be completed on October 6th. Malfunctioning lights will be addressed on October 6th. The original punch list had 29 items on it; we are down to 6 some of which are partially complete. Annin Road Pumping Station Standby Power Bids were received on September 21st. Award of project is expected at October 11th meeting. HMM has submitted a proposal for construction phase professional engineering services. Raw Sewage Pump Replacement Bids were received on September 21st. Award of project is expected at October 11th meeting. HMM has submitted a proposal for construction phase professional engineering services. Final Settling Tank Building Leak Repairs Bids were received on September 21st. Award of project is expected at October 11th meeting. HMM has submitted a proposal for construction phase professional engineering services. Inlet Climber Screen Replacement HMM submitted a proposal for construction phase professional engineering services. Quarterly Flow Report HMM is currently preparing the quarterly flow report for the 3rd quarter, 2011. 11. TOWNSHIP OF BERNARDS SEWERAGE AUTHORITY OPERATOR’S REPORT October Meeting 2011 Report September 2011 Report FLOWS Total Flow 79,721,000 Gallons Average Flow Maximum Flow Minimum Flow 2,657,000 7,586,000 1,766,000 Gallons Gallons Gallons OPERATION Suspended Solids Dry Weight NJDEP Limit Influent 1722 Kg Effluent 58 Kg Net 1664 Kg Suspended Solids In Effluent 5.1 Mg/l 280 Kg/Day 85% 30 Mg/l CBOD 96.6 % Removed Dry Weight Influent Effluent Net CBOD in Effluent 903 15 888 2.4 Kg Kg Kg Mg/l NJDEP Limit 98.3 % Removed 75.7 Kg/Day 85% 8 Mg/l Phosphorus Dry Weight NJDEP Limit Influent Effluent Phosphorus in Effluent 26.2 Kg 1.7 Kg 0.18 Mg/l 5.0 Mg/l Remarks Hypochlorite Used: 1075 Gals. Sulfur Dioxide Used: 651 Lbs. Alum Used: 4840 Gals. Influent pH: 7.3 S.U. Effluent pH: 7.2 S.U. Total Precipitation 10.4 Inches Comments This period the NJDEP visited the plant to check plant status after Hurricane Irene. Monitored generators at Juniper Way and Fieldstone Drive due to week long power outage caused by Hurricane Irene. Cleaned plant from overflow. Cleaned wetwell gratings at East Oak, Stonehouse, & South Maple pump stations. TV’d storm sewer on Van Cortland Way. Pumping Services replaced RAS #1 controller. Tightened Madisonville Pump #1 dresser coupling. Unclogged pump #2 at Crown Court. Pulled Crown Court and South Maple comminutor gear boxes. Changed carbon at Juniper Way. Checked syphons. Responded to odor complaint at 11 Linden Drive. Checked manholes, no problems or odor detected. Responded to odor complaint at 3132 Valley Road. Cleanouts buried and no odor present. Responded to call from 25 Stonehouse Road (Basking Ridge Electric) to locate the shut-off valve for their pressure sewer. Riser pipe clogged with debris. Used vactor to clean riser and then close valve for them. Changed oil in 6” pumps. We continue to meet permit parameters without any problems. SAFETY Monthly fire extinguisher, lighting, safety shower checks completed. Attended Bernards Safety Committee meeting. Completed Tier 1 SPCC plan. Storm drain inspection performed. Lost time accident free for 18 days. PROJECTS I&I : No report Madisonville Road: Station on line. Waiting for old station demo. Belt Filter Press: Working on punch list. East Oak Pump Station: Waiting on new door and acoustical blinds for generator. Solar Field: Noveda and SATCON met to troubleshoot metering issues Fieldstone Drive Pump Station: Started digging to install wet well. Climber Screen: Awarded at September meeting . BERNARDS TOWNSHIP SEWERAGE AUTHORITY Resolution #1185 Approval of the Bill List Dated: October 11, 2011 BE IT RESOLVED, that this bill list dated 10/11/2011 be audited, and if found correct, be paid. Amounts listed as PY Unencumbered Bills will be transferred from Unrestricted Net Assets to the current liability line Accounts Payable Accounts Payable Current - Operating Accounts Payable Current – Capital $ 108,733.61 $ 186,093.66 Prior Year Bills-Capitol 2010 Total Prior Year Bills-Capital $ 50,000.00 Payroll - Current - S&W Payroll - Current - FICA $ 58,957.59 $ 4,420.40 Total Payroll $ $ 50,000.00 63,377.99 Sub-Total $ 408,205.26 Total $ 408,205.26 10. Resolution #1185 - Approval of Bill List Dated: October 11, 2011 Motion by Malay, seconded by Carpenter, to approve the Bill List Dated October 11, 2011 ROLL CALL AYE: Carpenter, Gaziano, Malay, Spitzer NAY: ABSTAIN: MOTION: Carried 11. Member/Staff Comments Timko noted the auction raised $13,000. Township IT Director Kyriacou is working on SCADA system. Belardo advised nothing further to report regarding contractor DCM. Plesnarski noted DCM had removed their last piece of equipment from the plant on 9/12/2011. ADJOURNMENT Motioned by Carpenter, seconded by Spitzer, to adjourn at 7 PM. All in flavor. Motion carried. Respectfully submitted, Lorraine J De Grande