TOWNSHIP OF BERNARDS SEWERAGE AUTHORITY OPERATOR’S REPORT January 2008 Meeting December 2007 Report FLOWS Total Flow Average Flow Maximum Flow Minimum Flow 71,855,000 2,318,000 4,392,000 1,407,000 Gallons Gallons Gallons Gallons OPERATION Suspended Solids Dry Weight NJDEP Limit Influent 1321 Kg Effluent 25 Kg Net 1296 Kg Suspended Solids In Effluent 3.2 Mg/l 280 Kg/Day 85% 30 Mg/l CBOD Influent Effluent Net CBOD in Effluent 98.1 % Removed Dry Weight 828 23 805 2.9 Kg Kg Kg Mg/l Phosphorus Dry Weight Influent Effluent Net Phosphorus in Effluent 22.5 15.4 7.1 2.0 Kg Kg Kg Mg/l NJDEP Limit 97.2 % Removed 75.7 Kg/Day 85% 8 Mg/l NJDEP Limit 31.6 % Removed 5.2 Mg/l Remarks Hypochlorite Used: 762 Gal. Sulfur Dioxide Used: 721 Lb. Influent pH: 7.6 S.U. Effluent pH: 7.5 S.U. Total Precipitation 9.25 Inches Comments This month we TV’d 23 Roads (Annin Road, Battle Hill Road, Beechwood Road, Belle Grove Court, Berkeley Circle, Cameron Court, Cedar Creek Drive, Conkling Street, Courtier Street, Cross Road, Evergreen Place, Flintlock Court, Kinnan Way, Lexington 1 Road, Morrison Street, North Alward Avenue, North Brook Avenue, Ridge Street, Schindler Drive, Stone Hedge Drive North & South, Washington Avenue, & William Street). Located manholes for Hatch Mott MacDonald on Acken Road, Allen Road, Culberson Road. Verizon repaired Madisonville Road alarm lines. Cleaned Annin Road & Valley Road wet well. Checked syphons. Installed riser ring in manhole HBW-22-02 on North Brook Avenue. Repaired manhole SM-00-02 with Rapid Seal wrap system. Demeter Electric replaced the cross arms on the main electric pole at the plant. Exercised plant and station generators. Painted boiler room floor. Started painting blower room.. We continue to meet permit parameters without any problems. SAFETY Safety inspection performed by PMK / EJIF Monthly fire extinguisher checks completed. Attended NJUA Safety meeting. PROJECTS Plant Electrical System Analysis Contract – CDI: Generator and transfer switch information supplied to service companies for service quotations. Juniper Way Pump Station – Under construction- CFM; T&M Associates: No report SCADA System – Morehouse Engineering: Sub-committee meeting 1-17-08 I&I - Preconstruction meeting with Jo-Med on 1-15-08 Signature 2