Regional Railroad Waiting Room System project – Phase 1 Addendum #1 Specification Modifications: 1. Section 01010, article 1.08 A. 3. Change first sentence to read “Prior to working at other Stations, the Contractor shall install and test equipment at two Stations, as prototypes of the equipment and installation work.” Add the following after the first sentence “One of these Stations shall be a fiber equipped Station, and the other shall be a non-fiber equipped Station. The actual Stations chosen for this prototype work shall be selected by SEPTA’s Project Manager.” 2. Section 13700, article 2.01 O. Change “iSTAR PRO Access Controller, No substitutions” to iSTAR Ultra Access Controller, No substitutions”. Sub-item 1., change “Software House iSTAR PRO, Eight Reader model” to “Software House iSTAR Ultra, Eight Reader ACM equipped model.” Sub-item a., change “128 MB memory” to “Provide PSX power supply to support battery backup.” Sub-item c., change “Include large iSTAR PRO enclosure for electronics.” To “Include large iSTAR Ultra wall mount enclosure for electronics.” 3. Section 13700, article 2.01 P. Change “Software House iSTAR PRO Input and Output Modules, No substitutions” to “Software House iSTAR Ultra Input and Output Modules, No substitutions”. Subitem 1. a. Change to read “Provide Software House iSTAR Ultra expansion modules and accessories as needed to connect, power and control all devices shown on the contract drawings.” Sub-item b. Change first sentence to read “Provide Software House iSTAR Ultra large metal enclosure with tamper switch to accommodate circuit boards and accessories.” 4. Section 13700, article 2.01 S. Add item; “4. Conduct system design review meetings with SEPTA as deemed necessary by SEPTA, to select C-Cure 9000 system design features and including workstation configurations.” 5. Section 16060, article 3.06 A. 2. Add “c. Communications Case: 5 ohms.”. 6. Section 16700, article 2.08 A. Add “3. Provide four SFP fiber optic modules for each OTN network switch. SEPTA will provide the Contractor with a table to identify which type of SFP module is to be provided for each switch port. The type of SFP module required can vary by Station OTN network switch and by SFP port. Following is a list of the different types with OTN Systems part numbers: V30813-S19-A1: Optical GigE SFP 850nm Multi Mode module – SX (550 m / 0.34 mi) V30813-S20-A1: Optical GigE SFP 1310nm Single Mode module – LX (10 km / 6.2 mi) V30813-S34-A1: Optical GigE SFP 1310nm Single Mode module – EX (40 km / 24.8 mi) Specifications and Drawings Modifications Page 1 of 2 Regional Railroad Waiting Room System project – Phase 1 Addendum #1 V30813-S35-A1: Optical GigE SFP 1550nm Single Mode module – ZX (70 km / 43.5 mi)” 7. Section 16773, article 2.09 A. Replace “Tyco Integrated Solutions” with “Tyco Integrated Security”. Replace “Phone 610-635-1467” with “Telephone 484-868-4988”. Add a line immediately below the telephone number as follows “email ATysh@Tyco.com”. Drawings Modifications 1. General drawing revisions to accommodate changes noted above for each of the impacted stations. 2. Clarification of communications cabinet color requirements – silver powder coat for all locations other than Lansdowne, Roslyn, Elkins Park and North Wales which will be Bainbridge Green. 3. Revisions to communications cabinet\rack power distribution systems including, but not limited to: connection of 48VDC rectifier modules to dedicated 20A outlets, connection of LVR (non-fiber locations) to AC power integrating new LVR PS, elimination of UPS for non-fiber locations and connection of Cellular route and Cable modem to battery backed DC distribution. 4. Revisions to communications cabinet\rack fiber and copper connection plans including but not limited to: integration of OTN switch fiber modules connection modules, revisions to copper switch connection plans to relocate LVR connections at non-fiber locations (in preparation for future fiber conversion). 5. Included provisions for contractor to supply 96 port fiber patch panel at non-fiber locations for future installation by others. 6. Relocation of existing AXIS 219 analog video server to the new communications cabinet at Fox Chase. 7. See attached schedules for additional information on drawing changes. Specifications and Drawings Modifications Page 2 of 2