MAGTAP 18 Month PP-rev 14 Aug 129847 90166 Procurement Plan I. 1. 2014 General Project information: Country: Mozambique Borrower: Government of Mozambique Project Name: Mining and Gas Technical Assistance Project (MAGTAP) Loan/Credit No.: 5199-MZ - Project ID P129847 Project Implementing Agency: Ministry of Mineral Resources (Project Management Unit- PMU) 3. 3. 4. Bank’s approval Date of the procurement Plan: November, 2013 Date of General Procurement Notice: 30 of September, 2013 Date of Procurement Plan Updated: 14 of August of 2014 Period covered by this procurement plan: 18 months from June 2013 – December 2014 II. Goods and Works and non-consulting services. 2. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement. Procurement Method Prior Review Threshold Comments ICB and LIB (Goods) NCB (Goods and Nonconsultant Services) > USD 500,000 3 Shopping (Goods) < USD 50,000 3. ICB (Works) N/A 4. NCB (Works) < USD 500, 000 5. Shoping (Works) < USD 50,000 All First two contracts will be subject to prior review by the bank First two contracts will be subject to prior review by the bank N/A First two contracts will be subject to prior review by the bank First two contracts will be subject to prior review by the bank 1. 2. < USD 500,000 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Reference to (if any) Project Operational/Procurement Manual: A Project Implementation Manual covering both Financial Operations and Procurement and other procedures has been presented by MIREM and approved by the WB as per the requirements for project effectiveness. 4. Any Other Special Procurement Arrangements: N/A 5. Procurement Packages with Methods and Time Schedule 1 MAGTAP 18 Month PP-rev 14 Aug 1 Ref. No. 2 Contract (Description) Goods G4 – A5.6 – I 4 Procuremen t Method 5 Prequalif ication (yes/no) 6 Dome stic Prefe rence (yes/n o) 7 Review by Bank (Prior/Post) 8 Expected BidOpening Date Coreshed & related equipment NCB No No Prior Nov-14 G6-B2.2 – I IT infrastructure for INP NCB No No Post Nov-14 G7-B3.3 – I IT infrastructure for ENH NCB No No Prior June-15 G8-C2.3 – I NCB No No Post Ago-14 NCB No No Post Out-14 G11 – V - I Equipment to general inspectorate & provincial offices Equipment for environmental monitoring Vehicles & Motorbikes ICB No No Prior G12 – E – I IT Equipment for PMU/EITI Shopping No No Post G13 – E – I IT Network for PMU Shopping No No Post G13i – E – I/D Shopping No No Post - DC No No Prior - Concluded G15 – V - I Office and furniture & Equipment ENH Seismic data Interpretation Software License renewal Motorbikes & Bikes Subject to moving office Concluded NCB No No Post Sep-14 G16- V – I/D Office furniture & Equipment NCB No No Post Out-14 G17 – V – I/D IT Equipment NCB No No Post Out-14 G18 – V – I Camping Equipment and Material Radio Communication Equipment A/C Equipment for Mining Cadastre Offices Accounting Software for PMU NCB No No Post Nov-14 Shopping No No Post Ago-14 Shopping No No Post - Shopping No No Post - Non-Consultant Services NC1- A5.1 – I Geological mapping & geochemical surveying ICB No No Prior NC2-A5.1 – I ICB No No Prior - Shopping No No Post - G10-C6.5 – I G14-B3.3(iv) –I G19 – A3.4 – I G20 – A1.3 – I G21 – E – I NC3-E – I Airborne geophysical survey Project Website Design and Implementation 3 Estimated Cost (USD) 2014 - 9 Comments Office construction started/2013 Office construction comp Nov/2013 Under Evaluati Concluded Nov-14 Under Evaluation Under evaluation Jun-15 Concluded Under Evaluation 2 MAGTAP 18 Month PP-rev 14 Aug 2014 1. Selection of Consultants 2. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Procurement Method 1. 2. 3 Competitive Method (Firms) Single Source (Firms & Individual Consultant) Individual Consultant Prior Review Threshold (US$) Comments 200,000 ALL 100,000 3. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $200,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 Ref. No. 2 Description of Assignment C1 –A1.1 – I Update Cadastral Procedures C2 – A1.3 – I Technical Assistance to provincial cadaster offices ASM Development program strategy Supervision of Geoscientific Infrastructure Development Programme Review of EMEM Mandate on Mining Concession and Institutional review and reengineering Transaction advisory services for mining & related infrastructure Geological and Geophysical/ GIS data management and interpretation Financial/technical evaluation of LNG Area 1 and legal support Development of Business Process for ENH Logistics Transaction advisory services for gas & related infrastructure Legal Capacity Building for MIREM Legal Advisers Technical assistance/capacity building of the planning & economics directorate (resident advisor) Communications strategy Strategic Environmental and Social Assessment C3 – A3.2 – I C4 –A5.1 – I C5 – A6 – I C6 – A7 – I C7 – B2.4 – I C8-B3.1& B3.2 – I C9-B3.4 – I C10-B4 – I C11 –C1.2 – D C12-C3.1 – D C13-C3.2 – D C14 - C6.1 – I 3 Estimate d Cost (USD) 4 Selecti on Method 5 Review by Bank (Prior/Post) 6 Expected Proposals Submissio n Date SSS Prior Nov-14 QCBS Prior Nov-14 QCBS QCBS Prior Prior Out-14 - QCBS Prior Nov-14 QCBS Prior Nov-14 QCBS Prior Mar-15 QCBS Prior - QCBS Prior Mar-15 QCBS Prior - QCBS Prior Mar-15 QCBS Prior Sep-14 IC QCBS Prior Prior - 7 Comments Under Evaluation Under Evaluation Completed Concluded Negotiation s 3 MAGTAP 18 Month PP-rev 14 Aug C16 – C6.3 – I C17-D3.1 – D C18-E – I C19-E – I C20-E – I C21-E – I C22-E – I C23-E – I C24-E – I C25-E – I C27-B1 – I C28-B2.4(i) –I C29B3.1/B3.2 – I C30B3.3(iii) – I C31-B3.4 – I C32-C4.3 –I C33 – B3.3.(iv) – I C34-A7 – I C35-E – I C36-E – I C37-C1 – D C38 – A7 – I C39 – C2.2 –I C40 – C2.2 –I C41 – C1 – D C42 – D3 – I C43 – C3.2 –I C44 – C6.7 –I C45 – C6.7 –I C46-A5.3 – I C47-A5.5 – Resettlement guidelines for mining and gas (by MIREM Environment Unit) Review and Operation contingency Plan for oil spill Project coordinator Procurement Consultant Financial Management Consultant Procurement Consultant-II Procurement Assistant Accounting Assistant Environmental consultant Social Consultant Mozambique Gas Master Plan – 3rd Contract Review & Evaluation of LNG Project Development Plan (INP) Financial Advisory Services for ENH LNG Project-Initial phase 2014 IC Prior Nov-14 QCBS Prior Nov-14 IC IC IC SSS IC IC IC IC SS Prior Prior Prior Prior Prior Prior Post Post Prior Nov-14 Nov-14 - Completed Completed Completed Completed Completed Completed CQS Prior - IC Prior - Negotiation s Negotiation s ENH-LNG Marketing Advisory IC Prior - Preparation of Scope for Assistance to ENH Logistics Design IT Infrastructure for MIREM Design IT Infrastructure for ENH IC Post - IC IC Prior Post Nov-14 - SSS IC IC Prior Prior Prior - IC Prior Nov-14 QCBS Prior Nov-14 QCBS Prior Dec-14 IC Prior Out-14 QCBS Prior Dec-14 QCBS Prior Dec-14 QCBS Prior Out-14 IC Prior - Negotiation IC Prior - Negotiation s IC Post Apr-15 QCBS Prior Out-14 Review of Tantalum Project Mining Specialist Gas Specialist Review of Environmental Regulations applicable to Mining Sector Review of Mining Contract Model Development of Mining and Gas inspectors function and Guidelines Development of standards procedures for technical safety regulation Technical review and capacity building to IPEME Development of Environment Guidelines for oil (onshore and offshore) and mining activities Skill based HR Development for ENH Review of Social Action Policy for MMAS Review of Gender policy and implementation strategy for MMAS Upgrade of Seismic Stations Upgrade of Mineral Information Completed Negotiation s Negotiation s Negotiation s Concluded Concluded Concluded 4 MAGTAP 18 Month PP-rev 14 Aug I C48A5.1(iV) – I C49-A5.6 – I C50-A5.1 (V) – I C51 – A5.1(vi) – I C52-A3.1 (V) – I C53-A7 – I C54-C6.6 I C55-C3.3 D C56-C3.3 D C57-C3.3 D C58 – C7.1 C59 – A2 - I C60 – A2 - I C61 – B1.1 C62-B2.4 - I System and Library Translation into Portuguese and publication of the Explanation of the Geological Map of Mozambique Support to Geoscience and Environmental Laboratories Write a new handbook on the geology of Mozambique Mapping and inventory of thermal and mineral water occurrences in selected areas Drafting of legislation on the use and utilization of radioactive minerals and minerals with radioactive elements Evaluation of the development mining deposits of tantalum and the required facilities for its exportation Consultancy service for customization of Hydrographic Mercury Dispersion Simulation Software for DNM Consultancy service to support Data collection & statistics for DPD Training Services (Economy and Management of Oil and Gas) Training Services (Economy and Management of Solid Minerals Resources) EITI Annual Report Reevaluation of Rio Tinto Assets Coal Price Benchmark Gas Transportation Feasibility Study Review & Evaluation of Offshore LNG Project Development Plan IC Post May-15 IC Post Sep-14 QCBS Post Sep-15 QCBS Post Sep-15 QCBS Prior Nov-14 IC Prior Out-14 SSS Prior Sep-14 QCBS Prior Dec-14 IC Post Sep-14 IC Post Out-14 IC CQS QCBS QCBS QCBS Post Post Post Prior Prior Oct-14 Sep-14 Nov-14 Dec-14 Nov-14 2014 5