71834 Procurement Plan I. General Remarks 1. Country: Senegal 2. Project: Electricity Sector Support Project (ESSP) 3. Procurement Plan from July 2012 to December 2013 4. Dates of IDA approval: - Original Plan: May 28, 2012 - First Revision: June 8, 2012 - Second Revision: … N/A … 5. Publication Date for the General procurement Notice: … [Pending] … II. Procurement of Goods, Works, and Non-Consulting Services 1. Procurement subject to prior-review by IDA, as considered in Appendix 1 of the Procurement Guidelines. 1 2 Procurement methods 3 Threshold for Prior-review (US$) All contracts bidded under ICB and LIB and all contracts with estimated value above or equal to 500.000 US$ 1. ICB and LIB(Goods) 2. NCB (Goods) 3. ICB (Works) 4. NCB (Works) 5. ICB (Non consulting services) All contracts bidded under ICB and LIB and all contracts with estimated value above or equal to 500.000 US$ NCB (Non consulting services) All contracts subject to IDA prior-review All contracts subject to IDA prior-review All contracts bidded under ICB and LIB and all contracts with estimated value above or equal to 5.000.000 US$ All contracts subject to IDA prior-review 4 Comments ICB and LIB used for all contracts with estimated value above or equal to 500.000 US$ NCB could be used for goods with contract estimated value below or equal to 500.000 US$ ICB and LIB used for all contracts with estimated value above or equal to 5.000.000 US$ NCB could be used for works with contract estimated value below or equal to 5.000.000 US$ ICB and LIB used for all contracts with estimated value above or equal to 500.000 US$ NCB could be used for Non consulting services with estimated Shopping (goods) Shopping (works) Shopping (Non consulting services) Direct Contracting All contracts subject to IDA prior-review All contracts subject to IDA prior-review value below or equal to 500.000 US$ Shopping could be used for contract with estimated value below or equal to 50.000 US 2. List of contracts, including associated procurement method and key milestones. 2.1. Goods 1 2 Ref No Contract (Description) 1 Supply of 150,000 pre-paid split meters 3 Estimated Cost (US$000s) 4 11,680 ICB Procurement Method 5 Prequalification (Y/N) 6 Domestic Preference (Y/N) 7 Review by Bank (Prior/Post) N N Prior 8 9 Expected Bid- Comments Opening Date (optional) 03/06/2013 03/06/2013 2 Supply of cases for pre-paid meters 3,370 ICB N N Prior 3 Supply of cables and other accessories for the installation of pre-paid meters 2,500 ICB N N Prior 03/06/2013 4 Supply of 10,000 smart meters 2,000 ICB N N Prior 03/20/2013 5 Supply of cases for smart meters 900 ICB N N Prior 6 Supply of vehicles for the teams supervising the installations of meters. 350 NCB N N Post 03/20/2013 02/13/2013 US$16.0 million financed by IDA and US$3.0 million by GoS 7 Supply of IT equipment for SPE and SENELEC 45 Shopping N N Post 8 Supply of office material for SPE and SENELEC 45 Shopping N N Post 3 Estimated Cost (US$000s) 4 5 Prequalification (Y/N) 6 Domestic Preference (Y/N) 7 Review by Bank (Prior/Post) 12/05/2012 12/05/2012 2.2. Works 1 2 Ref No Contract (Description) 1 Reinforcement and modernization of HV substations 13,000 ICB N N Prior 2 Reinforcement and modernization of HV lines 5,000 ICB N N Prior 3 Voltage upgrade from 6.6 to 30 kV for selected distribution 14,000 lines and substations ICB N N Prior 02/06/2013 4 Distribution Network expansion within Greater Dakar ICB N N Prior 02/16/2013 5,000 Procurement Method 8 9 Expected Bid- Comments Opening Date (optional) 05/08/2013 05/08/2013 IDA NO subject to disclosure of ESIA/RAP and possibly compensation IDA NO subject to disclosure of ESIA/RAP and possibly compensation IDA NO subject to ESMP acceptable to IDA IDA NO subject to ESMP (financed by GoS) acceptable to IDA 5 Supply and Installation of remote circuit breakers for 15 1,000 substations 6 Extension of the distribution network to isolated loads in secondary centers NCB N N Post 02/13/2013 05/22/2013 4,500 ICB N N Prior 3 Estimated Cost (US$000s) 4 5 Prequalification (Y/N) 6 Domestic Preference (Y/N) 7 Review by Bank (Prior/Post) 10,000 ICB N N Prior 700 ICB N N Prior 483 NCB N N Post 04/03/2013 483 NCB N N Post 04/03/2013 484 NCB N N Post 04/03/2013 IDA NO subject to disclosure of ESIA/RAP and possibly compensation 2.3. Non-Consulting Services 1 2 Ref No Contract (Description) 1 2 3 4 5 Supply and Installation of a new customer service management system. Supply and Installation of an information management system for smart meters Installation of pre-paid meters and related services (Thiaroye and Malika) Installation of pre-paid meters and related services (Touba) Installation of pre-paid meters and related services (Thiès, Mbour, Ouakam and Patte d’Oie) Procurement Method 8 9 Expected Comments Offer (optional) Opening Date 05/15/2013 03/20/2013 04/03/2013 6 Installation of smart meters and related services (Dakar) 210 NCB N N Post 7 Installation of smart meters and related services (other areas) 140 NCB N N Post 04/03/2013 8 Supply and installation of information management system for the smart meters 700 ICB N N Prior 10/31/2012 III. Selection and Employment of Consultants 1. Selection and Employment of Consultants, subject to prior-review by the Bank as considered in Appendix 1 of the Procurement Guidelines for the Selection and Employment of Consultants. 1. 2. 3. 4. Procurement Method Competitive selection methods (firms) Single Source Selection (firms) Competitive selection methods (individual consultants) Single Source Selection (individual consultants) Threshold for prior-review (US$) = or >US$200,000 All contracts = or >US$100,000 All contracts Comments (optional) Contracts for specific tasks such as development or update of the project implementation manual, supervision contract, monitoring and evaluation contract, auditing (financial and technical) etc. Although not specifically linked with any procurement methods, the All contracts could be subject to importance of those contracts could prior-review require Bank’s prior-review based on case-by-case consideration. a) Short list comprising entirely of national consultants. Short list of consultants for services, estimated to cost less than US$ 200,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines Consultant Services including associated procurement method and key milestones 1 2 3 4 5 6 Expected Proposals Submission Date Ref No Description of Assignment Estimated Cost Selection Method Review by Bank (Prior / Post) 1 Support to the financial restructuring of SENELEC 750 QCBS Prior 2 Tariff Study 500 QCBS Prior 3 Analytical study on introduction of LNG in Senegal’s mix 250 QCBS Prior 4 Support to IPPs’ development 500 QCBS Prior 05/08/2013 500 QCBS Prior 02/06/2013 750 QCBS Prior 500 QCBS Prior QCBS Prior 5 6 Strategic study for integration of renewable energies in the energy mix and definition of a planning and implementation strategy Definition, implementation and audit of a performance contract between the government and SENELEC 7 Organizational and managerial audit of SENELEC 8 TA for the implementation of some of the actions recommended 2,500 by the audits 01/09/2013 01/09/2013 02/06/2013 12/12/2012 01/23/2013 08/14/2013 7 Comments (optional) 9 Assistance to the completion of the work on the separation of SENELEC’s accounts 1,250 QCBS Prior 10 Strategic study on medium to long term private sector participation in SENELEC 750 QCBS Prior 11 ESMP for voltage upgrade from 6.6 to 30 kV 60 QCBS Post 12 ESIA and RAP for the interconnection of secondary isolated centers (1) 100 QCBS Post 01/16/2013 13 ESIA and RAP for the interconnection of secondary isolated centers (2) 100 QCBS Post 01/16/2013 14 Supervision of environmental safeguards 150 QCBS Post 03/27/2013 15 Supervision of the supply and installation of a new customer service management system 500 QCBS Prior 02/28/2013 16 External Audit for the project 100 QCBS Prior 17 Training program 150 CQS Post 18 TA for monitoring and evaluation 150 CQS Post 12/12/2012 05/22/2013 12/26/2012 01/16/2013 03/13/2013 03/13/2013 19 20 TA for SENELEC for supervision of Project Component 1 and 2 175 (Owner’s Engineer) 22 23 Procurement Specialist for the project implementation unit Post 11/14/2012 Individual Consultant Post 08/29/2012 120 Individual Consultant Prior 11/28/2012 80 Individual Consultant Prior 11/28/2012 120 Individual Consultant Prior Individual consultants for the 350(*) supervision of meter installations Financial Management Expert for the project implementation unit Internal auditor for the project implementation unit 21 CQS 12/05/2012 (*) US$350.000 cumulative estimated amount for about 30 Individual Consultants to be recruited at the same time