Investigations - Victorian Government Solicitor`s Office

advertisement

ICT Projects in government

Challenges for procurement and contract management

26 April 2012

Your speakers:

Sue Nolen

Assistant Victorian Government

Solicitor

VGSO

Erin Barlow

Manager, Investigations, Victorian

Ombudsman's Office

Isabel Parsons

Special Counsel

VGSO

Key Challenges

Sue Nolen

Key Challenges and reflections on the Ombudsman’s report

• Procurement risks: reliance on vendor’s capacity to deliver, and viable subcontracts

• Legislative requirements, public accountability

• Managing stakeholders’ requirements and project governance

The Victorian Ombudsman’s investigation into ICT-enabled projects

Erin Barlow, A/Principal Investigator

Session overview

ICT report

• Background

• Scope

• Objectives and methodology

• Conclusion

• Recommendations

Questions

Background

What is ICT? What is ICT-enabled?

History of ICT failures: state, national and international level

Ombudsman and Auditor-General reports on ICT

Little signs of lessons learnt

Ombudsman and Auditor-General agreed to investigate

April 2011: Ombudsman commenced own motion investigation

Conducted in consultation with the Victorian Auditor-General’s Office.

Scope

Examined 10 ICT-enabled projects:

Link (Victoria Police)

HealthSMART (Department of Health) myki (Transport Ticketing Authority)

Registration and Licensing – RandL (VicRoads)

Client Relationship Information System – CRIS (Department of Human Services)

Ultranet (Department of Education and Early Childhood Development)

Integrated Courts Management System – ICMS (Department of Justice)

Property and Laboratory Management – PALM (Victoria Police)

HRAssist (Victoria Police)

Housing Integrated Information Program – HIIP (Office of Housing).

Investigation

Objectives:

– determine whether the projects were over-budget and/or delayed and the reasons for this

– determine whether the ICT systems met the needs for which they were designed

– determine who should take responsibility for project failures

– determine what lessons can be learned.

Methodology:

– investigators reviewed public documentation on ICT project failings/learnings

– investigators met with or interviewed over 100 people

– investigators conducted site visits to child protection, housing and education offices; hospitals; and the Supreme Court

– investigators reviewed extensive documentation relating to planning, procurement, project delivery and training.

Conclusions

Every one of the projects failed to meet expectations; most failed to meet delivery timelines; and all ran over budget.

The latest estimated cost is significantly more than budgeted. Current estimate: $2.74 billion.

– The budget for DHS’s CRIS project increased by 272 per cent.

– If Link were to be completed it would cost over three times the original budget.

There has also been significant wastage:

– VicRoads spent $50 million on RandL over three years – at the time of the report, the project had not made it past the design phase and was yet to receive funding for project delivery.

– Victoria Police spent $59 million on Link over five years – the project has now been cancelled and this money is lost.

The additional money spent on these projects represents many foregone hospital beds, trains, police and child protection workers .

Five common themes

Leadership, accountability and governance

Roles and responsibilities for ICT-enabled projects were often not clearly defined, acknowledged and accepted.

Senior officers appeared reluctant to make critical decisions about projects.

Many of the project steering committees did not have the requisite expertise.

Many of the projects would have benefited from the Department of Treasury and Finance

(DTF) taking a more pro-active role.

The effectiveness of DTF’s Gateway Review process was limited by its reliance on agencies engaging in and being supportive of the process, which often was not the case.

There was limited publicly available information about the ‘high-value and high-risk’ process and some witnesses from DTF and departments remained unclear about it.

Five common themes

Planning

In some cases, optimism bias led to costs and timelines being based upon hope, rather than evidence or comparisons with similar projects and in spite of advice from experts and vendors.

Agencies often gave the government no choice other than to invest in the agency’s preferred option and failed to provide government with adequate advice to make an informed decision.

Business cases for many of the projects were not updated throughout the life of the projects. In some cases, they were not read by key people.

Insufficient attention was given to managing or mitigating risks.

Five common themes

Funding

Agencies felt the need to create ‘big vision’ projects to capture the government’s attention, which increased complexity and risk.

In some cases the Budget and Expenditure Review Committee (BERC) only partially funded projects, but agencies failed to revise the scope of the project to fit within the allocated budget.

Public announcement of major project funding decisions prior to business case development resulted in business cases being rushed and projects being ‘shoe-horned’ into the published funding ceiling.

The costs and timelines of comparative projects were sometimes ignored.

Projects funded internally have not been subject to the same level of scrutiny as BERC-funded projects.

Agencies were unable to identify the cost of significant projects with any accuracy.

Five common themes

Probity and procurement

Agencies appeared to pay limited regard and expended minimal funds on probity advice and audit.

Agency and probity practitioner responses to conflict of interest sometimes failed to recognise the importance of the perception of a conflict of interest.

Agencies tended to purchase off-the-shelf systems and customise them to such a degree that the benefits were lost to government.

The evidence suggests government should explore new procurement methods for ICTenabled projects.

Large vendors are well-versed and experienced in contract negotiations, putting relatively inexperienced government staff at a disadvantage.

Five common themes

Project management

Several agencies failed to act with enough urgency to address potential problems and in doing so allowed the issue to escalate.

There is a shortage of skilled senior project managers with relevant ICT experience in government. To compensate, agencies often appoint expensive contractors or inexperienced public sector staff.

Managing vendor and user relationships can be a complex exercise and agencies have adopted differing approaches to this problem with different degrees of success.

Approaches to training staff were varied and not always effective.

Recommendations

The framework within which agencies seek funds, manage and review projects needs to be improved.

The scale of the problem suggests that significant ICT-enabled projects should be treated as a special case at least until the bureaucracy is sufficiently experienced to handle these projects well.

The Ombudsman developed a framework that builds on current guidance and advice from the Auditor-General and DTF and provides a practical solution to many of the problems commonly encountered. The framework contains 42 recommendations based around the five common themes.

The Ombudsman also made recommendations that suggest a way forward for each of the

10 projects.

Recommendations

For all ICT-enabled projects over $20 million:

• Increasing the oversight and accountability of Ministers and secretaries.

• Enhancing the role and accountability of DTF.

• Capitalising on the value of Gateway, including making it mandatory.

• Requiring that agencies seek funding and undertake projects in stages.

• Waiting until the completion of the planning/procurement before announcing funding/timelines.

• Examining the ‘competitive dialogue’ process used in the United Kingdom for ICT procurement.

• Examining strategies to attract skilled ICT staff.

• Ensuring VGSO is briefed early and that it endorses all contracts.

Future review

These problems are not limited to the Victorian public sector.

There is no panacea.

Arrangements would benefit from a review in two years time to ensure their effectiveness, ongoing relevance and practicability.

Questions?

Legal issues for contract management in ICT Projects

Isabel Parsons

Contract management themes in the Ombudsman's Report

• Insufficient attention given to managing/mitigating risks

• Challenges with heavy customisation or leading edge/untried systems

• Failure to act with urgency to address problems/escalation

• Complexities of managing vendor and user relationships

• Reluctance of senior officers to make critical decisions

Principles of contract law

• Common law of contract - principles of formation and construction

• Implied obligations - cooperation, good faith

• Constraints on exercising rights - election to continue, estoppel

A case study: GEC Marconi Systems v

BHP Information Technology

[2003]

FCA 50

• Commonwealth procurement: Sub-contract between

BHP-IT and GEC Marconi

• Failure of DFAT to provide security device (STUBS), operation of change request CR3049 and subsequent activities

• No amendment to the sub-contract

• GEC Marconi faced significant losses on the project and sought to terminate

• Many cross claims, including against DFAT for misleading and departure conduct

Key questions in GEC Marconi case

• Had the sub-contract been varied to reflect

CR3049? (No written agreement)

• Had GEC Marconi elected to treat the contract as being on foot, rather than to terminate?

• Did GEC Marconi’s conduct amount to repudiation of its obligations under the subcontract, and was BHP-IT entitled to damages for breach?

Outcomes in GEC Marconi case

• There had been a variation to the sub-contract – terms were identified from conduct and correspondence

• GEC Marconi had elected to perform the subcontract, including the STUBS variation, and was precluded from terminating for that breach

• Court considered obligations of the parties to act in good faith

Alston v Yokogama Australia

(No. 7) [2012] SASC 49

• Construction contract case

• Considered implied duties of parties to cooperate with each other and obligation of good faith in the context of interdependencies in work to be performed

Good faith and dispute resolution

• ‘Meet and discuss in good faith with a view to resolving dispute’ (VGPB)

• ‘Use reasonable commercial efforts to resolve by negotiation’ (GITC)

• Express obligation: United Group Rail Services

Ltd v Rail Corporation NSW [2008] NSWSC

1364 and [2009] NSWCA 177

Good faith and termination for convenience

• Kellogg Brown & Root Pty Ltd v Australian

Aerospace Ltd [2007] VSC 200 – may terminate by notice in writing

• Solution 1 Pty Ltd v Optus Networks Pty Limited

& Ors [2010] NSWSC 1060 – for any reason and at any time in Optus’ absolute discretion

• Risks in using these clauses to change supplier, or to terminate for non-performance

From contract to contract management

• Don’t ‘put the contract in the bottom drawer’

• Comply with VGPB Contract Management Policy

• Follow appropriate methodology

• Adapt resources – VGPB Category Management

Materials , Gateway Review Gate 5 Readiness for Service

• VAGO 2008 ‘ Investing Smarter in Public Sector

ICT: Turning Principles into Practice ’

Change management and variations

• Have you created a new contract without really trying?

• Correspondence, change orders and conduct may vary your contract

• Deprives State of benefit of key provisions and ongoing rights

• Document this carefully, with clear reservations of rights

• Use deeds of variation

Killing projects – termination ‘early and often’

• Prior to acceptance - is this realistic?

• Is termination an option for the State –

Critical systems or services

• Termination for convenience or breach?

• State is vulnerable to lengthy, complex and costly litigation

Reaction time – keeping your options open

• For how long – stakeholder management and senior decision maker involvement is critical

• Effective contract management informs good decision making

• What happens during the delay determines whether rights are lost

• Evasive statements to contractors or lack of cooperation may lead to claims against the State

Questions?

Download