Designer/Contractor JV- Apron Services Projects- A Winning Case The KAIA project Case Study Introduction The purpose of this presentation is to demonstrate : • How early Engineer( designer/ Contractor coordination and cooperation can overcome the difficulties encountered • Highlight unforeseen and foreseen difficulties and challenges encountered in the KAIA project Introduction AME- DEP JV KAIA back Ground and Scope of Work Project Constraints Project Deliverables Project Procurement Plan Systems Design Conclusion Designer / Contractor JV • • • • AME Background DEP Background AME-DEP JV and history of cooperation DEP Role in KAIA:DEP is doing design – shop dwgs – technical procurement submittals – construction management and cost control Project Background and Scope of Work • • • • Client : GACA Main Contractor : Saudi Bin Ladein Group – SBG Apron Subcontractor – Al Mabani AGC Apron Services Subcontractor – AME/DEP Project Background and Scope of Work Scope of Work: 1. Potable water treatment plants and potable water piping network from Tech. rooms to pits. 2. Blue water treatment plants and blue water piping from Tech. rooms to toilet pits. 3. Vacuum receiver plants and piping network. 4. PCA air handling units and corresponding under-gound ducting and PCA pits 5. Glycol chilled water plant rooms and networks. 6. GPU 400 Hz system and pits Project Background and Scope of Work Aprons 17-18-19 and PTB Area in scope Project Deliverables • • • • • • • • • Material Submittals Design and shop drawings Method statements Monthly Progress Reports O & M manuals As Built Drawings Testing and Commissioning Reports Training Warranties Project Constraints The main constraints challenging AME at this project are the following: 1. The short project duration which is by any standards is very tight for the scope of work at hand . 2. The different layers of upstream parties, mainly the CM and designers , and at a second level Main Contractor and Subcontractors 3. The Various unforeseen changes from the original tender design due to site conditions / project updated requirements / cost and time constraints 4. The delays in design / approvals / material Project Constraints 5. The difficulty of direct communication between many of the parties due to contractual constraints 6. The peculiarity of some of the specified items such as: • Vacuum drainage system • Glycol sub cooling method • SS PCA Duct for mobile ACU 7. The interface with other contract packages which could increase the number of unforeseen problems. Why a Designer on Board is a Winning Case 1. The Complexity of the modern airport systems makes it necessary to do every bit of study and calculations and drawings to achieve a coordinated installation 2. To get seamless relations with the CM which is himself is an engineer 3. The various changes in design during construction due to site conditions requires a designer on board during the construction to find the proper solutions 4. When a Designer is in direct contact with the specialists / suppliers the design will be more customized and more understanding to the equipment strengths and weaknesses. Examples of Unforeseen Difficulties 1. 2. 3. 4. Changes in the Client Requirements Suppliers uncontrolled supply delays Site level changes and various obstructions Differences in Contract requirements interpretations Project Procurement Plan AME has prepared a procurement plan relating to time and cash flow to suit the project schedule and technical requirements. The basic elements of this plan are : 1. 2. 3. 4. Establishing a basket of reputable suppliers Providing proper material submittals for approval Identifying long lead items and placing orders on time Delivering the material on site as per project schedule H-Project Manpower Histogram I-Communication Plan • -- t 16 The Solution….Apron Services Note: Fuel Trucks shown Removed (Hydrant Fueling) 90 KVA PCAir PCAir 90 KVA H2O Blue H20 Lavatory MARS GATES • • • • Multi Aircraft Ramp System Systems Design Vacuum System 19 Systems Design Vacuum System Systems Design Toilet Pit Systems Design Vacuum Lines Profile Systems Design Glycol Chilled Water System Systems Design Glycol System Configuration Systems Design PCA Unit Installation Detail PW Reel Pit Access PCA Hoses Valves PCAir and Potable Water Pits 26 Central Glycol Plants – Thermal Design – Civil works design and installation – Distribution Network – Responsible for Performance – Chiller Supply 2 Systems Design Potable Water System Systems Design Potable Water System Systems Design Blue Water System Systems Design Valve Chamber Detail Systems Design Service Pits (400 Hz) 32 Systems Design The GPU Approach PBB Mounted Reels or……Pits 33 Conclusion An early designer intervention and close cooperation with the specialist / contractor is a key factor in the project success Thank You