EIB 20603 SUPPLY CHAIN MANAGEMENT TASK 3: INVENTORY MANAGEMENT GROUP: _4_ Student Name Id No. Muhammad Zahier Bin Mohamad Yunos 62214119468 Nur Syazwina Binti Kamarul Azhar 62214119370 Nur Najihah Binti Abdul Karim 62212119157 Syarah Nadiah Binti Rosli 62212119570 Nur Aishah Binti Adnan 62212119064 QUESTION: Problem A construction company uses 15,000 bags of cement per year. The ordering cost is RM 50 per order and the annual carrying cost is RM 150 per unit. The lead time is 4 days. The company operates 250 days in a year. A) Find the EOQ B) Determine the reorder point (ROP) C) Calculate the ordering cost D) Calculate the carrying cost E) Calculate the TAIC F) Determine the no. of orders placed per year G) Determine the reorder cycle ANSWER: