MIS3535 Progress Report Project Team #: Flanagan 3 - Doyle 4 Team Members: PMs: Brett Leftwich, Anthony Ferro, Jessica Cracchiolo, Bakari Malik, James Long, Joshua Danehower BAs: Michael Belli, Lamar Dixon, Harold Rosemond, Eugene Sumin Reporting Period From: 9/29/14 Overall Project Status: To: 10/3/14 On Track Deliverables: 1. 2. 3. 4. 1. 2. 3. 4. 5. 6. 7. 8. 9. Work Completed: Task Name Date Completed Summary Notes Interview Questions Initial Scope Document Project Schedule draft Budget draft 9/24 9/24 9/24 9/24 Need help with constraints Needs more clarity Needs more direction Work in Progress: Task Name Planned End Date Resources Assigned Interview Questions #3 Work Breakdown Structure Project Charter Project Statement Quality Management Plan Risk Management Plan Communications Plan Change Management Plan Project Schedule 10/7 9/29 10/3 10/3 10/10 10/10 10/3 10/6 10/3 All BA’s Brett Jess Anthony Brett and Jim Bakari and Josh Josh Jess and Anthony Jim and Bakari 1 MIS3535 Work Schedule to begin: Task Name 1. JustinMind prototyping 2. Business Rules 3. ERD Diagramming 4. Presentation planning Planned Start Date 10/1 10/13 10/20 11/24 Project Issues Descriptions 1. Microsoft Project 2. Communication 3. Collaboration 4. Lack of Urgency Actions PMs need to invest more time into MS Project training Communication between BAs and PMs needs to improve through a sense of urgency Work division and communication needs to be addressed PM’s will address the conflict and stress urgency in all forms of communication with the BA’s Project Risks: Description Actions 1. Deliverable drafts not getting completed on time 2. Not enough communication between BAs & PMs 3. No preparation in MS Project Stress urgency Schedule more meetings Start MS Project training Meetings 1. 2. 3. 4. 5. 6. 7. Meeting that have taken place: Description Date / Time Attendees Pre-Interview Meeting Kick off Meeting Scope Meeting Project Status Meeting Project Status Meeting Scope Meeting PM meeting 9/24 9/10 9/9 9/17 9/29 10/1 10/3 Josh D & Alls BA’s All BA’s and selected PM’s All BA’S and selected PM’s All BA’s and selected PM’s All BA’s and PM’s All BA’s and PM’s All PM’s Planned Meetings: Description Date / Time Attendees 10/6 10/8 All BA’s and PM’s All BA’s and PM’s 1. Interview 3 Prep 2. Project Status 2