MIS3535 Progress Report Project Team #: Flanagan 3 - Doyle 4 Team Members: PMs: Brett Leftwich, Anthony Ferro, Jessica Cracchiolo, Bakari Malik, James Long, Joshua Danehower BAs: Michael Belli, Lamar Dixon, Harold Rosemond, Eugene Sumin Reporting Period From: 10/13/14 Overall Project Status: To: 10/17/14 On Track Deliverables: 1. 2. 3. 4. 5. 6. 7. 8. 9. 1. 2. 3. 4. 5. 6. Work Completed: Task Name Date Completed Interview Questions Initial Scope Document Project Schedule draft Budget draft Interview 3 Questions Project Charter Project Statement Justinmind Exercises Project Schedule 9/24 9/24 9/24 9/24 10/6 10/8 10/8 10/7 10/13 Work in Progress: Task Name Planned End Date Resources Assigned Work Breakdown Structure Project Budget Quality Management Plan Risk Management Plan Communications Plan Change Management Plan 10/24 10/27 10/27 10/24 10/24 10/24 Brett and Anthony Jim Brett and Jim Bakari and Josh Josh Jess and Anthony Summary Notes Need help with constraints Needs more clarity Needs more direction 1 MIS3535 7. Learning Justinmind 8. Team scope document Work Schedule to begin: Task Name 1. Business Rules 2. ERD Diagramming 3. Presentation planning 10/21 10/25 All BAs All BAs and PMs Planned Start Date 10/20 10/20 11/24 Project Issues Descriptions Actions 1. Microsoft Project PMs need to invest more time into MS Project training 2. Communication Communication has improved amongst BA’s and PM’s. Communication has slightly improved amongst Harold and the BA’s but not the PM’s 3. Collaboration Work division and communication needs to be addressed 4. Missing BA Harold Rosemond has started to communicate with BAs but has still failed to communicate with PMs Project Risks: Description Actions 1. Deliverable drafts not getting completed on time 2. Not enough communication between BAs & PMs 3. No preparation in MS Project Stress urgency Schedule more meetings Start MS Project training Meetings 1. 2. 3. 4. Meeting that have taken place: Description Date / Time Attendees Project status meeting Scope Meeting w/ Professor Project Status Meeting BA meeting 10/16 10/15 10/17 10/17 Anthony, Bakari, Eugene All BAs Jess and all BAs Mike, Eugene, Lamar Planned Meetings: Description Date / Time Attendees 10/20 10/23 10/24 All PMs All BAs, Bakari, James All BAs and selected PM’s 1. PM Meeting 2. Justinmind Meeting 3. Project Status Meeting 2