University of North Florida ADMINISTRATION & FINANCE Departmental Status Report for Space Committee Meeting Director: Department: Date: Zak Ovadia Campus Planning Design & Construction July 6th, 2011 I. SELECTED ACTIVE PROJECTS NOTE ALL SCHEDULES ARE TENTATIVE 1. Student Wellness & Sports Education Center Phase I: This project entails the programming, design and construction of a Student Wellness and Sports Education Center (Est. 116,000 GSF). Phase I in roughly 65,000 GSF. Tentative Schedule: Consultant Selection Complete Programming Complete RFQ for Design Complete Consultant Selection Complete Program Verification Complete Schematic Design Complete Design Development Complete Select CM Complete Const. Documents Complete Construction January 2011 – MAY 2012. Changes from last month: Construction GMP is on target at $16.4 Million. Project is on schedule for May 2012. 2. Programming for Buildings 50, 3 and 4: This project entails the programming, of three buildings for backfilling and restacking once the Biology Department moves to the new Biological Sciences Building in 2012. Tentative Schedule: Consultant Selection Complete Programming March 2011 Changes from last month: No changes this month. 3. Science and Humanities Building (Biological Sciences - TBD): It is anticipated that the building will be roughly 118,000 GSF on three levels. The building will be located adjacent to the Social Sciences Building (51). Tentative Schedule: Consultant Selection Complete Programming Complete Program Verification Complete Schematic Design Complete Design Development Complete Const. Documents March 2010 Select CM Complete Construction August 2010 to February 2012 Changes from last month: No Changes from Last Month. Project is on schedule. 4. COE&HS Building with DRC, VCS, VCL and OCT: Zak Ovadia 1 Project to build a 2 story addition to the College of Education & Human Services of approximately 15,000 GSF. Tentative Schedule: Consultant Selection Complete Programming underway Program Verification underway Schematic Design underway Design Development August 2010 Const. Documents September 2010 Select CM October 2010 Construction January 2011 to October 1st Changes from last month: No changes from last month. Project on schedule. 5. Science & Engineering Building Remedial Work: Corrective measures to mitigate building envelope deficiencies. Tentative Schedule: Consultant Selection Complete Programming N/A Program Verification N/A Schematic Design TBD Design Development TBD Const. Documents September 2010 Select CM Complete Construction Dec. 2010 – Dec. 2011 Changes from last month: No Changes from last month. 6. Sanctuary and Meditation Center: Design and Construction of sanctuary building of approximately 3,500 square feet to serve as a venue for group meditation or events. Tentative Schedule: Programming Complete Conceptual Permitting Complete RFQ for Consultants Complete Short-listing & Interv. Complete Program Verification Complete Schematic Design Complete Design Development TBD Construction Docs. TBD Construction TBD Changes from last month: No change from last month. Zak Ovadia 2 7. New Food Service Facility and General Purpose Building: Design and Construction of a replacement food service facility to replace Osprey Café. Preliminary needs call for a three or four-story building. Tentative Schedule: Programming August 2010 Conceptual Permitting TBD RFQ for Consultants Completed Short-listing & Interv. Completed Program Verification Completed Schematic Design February, 2011 Design Development March 2011 – April 2011 Select CM Complete Construction Docs. May 2011 – August 2011 Demolition May 2011 Construction July 2011 to August 2012 Changes from last month: Demolition of existing building complete. Work on Boardwalk continues. Project Substantial Completion scheduled for August 2012. Completed Projects: Zak Ovadia Campus-wide Master Planning New Fine Arts Buildings and Art Gallery JJ Daniel Hall Renovations Building 9 Restacking of Building to Accommodate Arts & Sciences needs Toilet Facilities for Recreation Fields 3