Project Status:
Charlotte-Mecklenburg Storm Water
Services and engineering consultant,
US Infrastructure of Carolina, Inc.,
continue work on the real estate
and permitting phase. During the
permitting phase, the project team
will obtain the required water
quality permits from Federal and
State agencies.
Next Steps:
After the real estate and permitting
phases are complete, the bid
phase will begin. During this
phase, the final design plans will be
circulated to qualified contractors
for a competitive bidding process.
After City Council approval, the
construction contract will be awarded
to the lowest responsible bidder.
For more information:
Please contact
William Harris, Project Manager
wtharris@charlottenc.gov
704-353-1147
stormwater.charmeck.org
Lyon Court Storm Drainage Improvement Project
Engineering & Property Management
Storm Water Services Division
600 East Fourth Street
Charlotte, North Carolina 28202
Investing in Infrastructure
The City must replace pipes, storm drains and other structures when they
deteriorate or become too small to handle increases in stormwater. Investing
in infrastructure protects public safety, guards private property, improves water
quality and enhances quality of life.
The Lyon Court Storm Drainage Improvement Project goals are to reduce flooding
of streets and structures, as well as reduce stream bank erosion by improving the
storm drainage infrastructure within the project area.