35 AGENDA ITEM BACKGROUND TO: GOVERNING BOARD DATE FROM: PRESIDENT SUBJECT: December 5, 2011 Ratification: Construction Change Orders REASON FOR BOARD CONSIDERATION ACTION ITEM NUMBER ENCLOSURE(S) Page 1 of 2 A.3 BACKGROUND: In accordance with Board Policy 4155, the attached change orders over $25,000 and less than 10% of the original contract value are submitted for Governing Board ratification. Continued on page 2 FISCAL IMPACT: $11,069.78 from project contingency. RECOMMENDATION: It is recommended that the Governing Board ratify the construction change orders provided as an attachment. Administrator Initiating Item: Joe Nugent Victoria Lewis Academic and Professional Matter If yes, Faculty Senate Agreement Senate President Signature Yes No Yes No Final Disposition Approved 36 Ratification: Construction Change Orders: cont. Project Green Tech Center Change order # Contractor Dilbeck Amount Description PCO #037R1 6,380 DSA required additional Skylight supports due to their size and weight. PCO #038R1 PCO #043 PCO #044 1,650 DSA required additional Window supports due to their size and weight. Delete sound strobe at overhead door, not needed -776 Delete type R fixtures, not required -3,256 Change Outside light fixtures to solid color to match the outside building color 821 Unforeseen condition Remove & Offhaul concrete cap over old utilities in Trafton Street too allow for lime treatment 1,912 The plans did not call for Waterproof membrane at shower walls & floor. 532 There are ceiling cord reels in the shop which did not have conduits or circuits called out on the plans. 2,607 Added and 30"x30" access door for future access to allow for maintenance to service the equipment. 400 Added a Fire Alarm Annuciator to work with our existing fire alarm panel. 800 PCO #045 PCO #046 PCO #049 PCO #050 PCO #054 PCO #057 Green Technology Center Project Building 1300 HVAC Change order # 11,070 Total Change Order Contractor Geo. Wilson Amount 0 Total Change Order Building 1300 Project Building 1100 HVAC Change order # Description Contractor Della Mora Amount Description Note: These change orders are reflected in the Facilities Master Plan (FMP) Status Report.