AGENDA ITEM BACKGROUND TO: GOVERNING BOARD DATE FROM: PRESIDENT September 12, 2011 SUBJECT: Ratification: Construction Change Orders REASON FOR BOARD CONSIDERATION ENCLOSURE(S) ITEM NUMBER ACTION Page 1 of 3 A.3 BACKGROUND: In accordance with Board Policy 4155, the attached change orders over $25,000 and less than 10% of the original contract value are submitted for Governing Board ratification. Continued on page 2 FISCAL IMPACT: $17,118 from the project contingency funds for each project. RECOMMENDATION: It is recommended that the Governing Board ratify the construction change orders provided as an attachment. Administrator Initiating Item: Joe Nugent Victoria Lewis Academic and Professional Matter If yes, Faculty Senate Agreement Senate President Signature Yes No Yes No Final Disposition Approved Ratification: Construction Change Orders: cont. Project Green Tech Center Change order # Contractor Dilbeck Amount Description PCO 001 Staff was able to obtain four light fixtures from the City of Watsonville. -1,686 This is the credit for not purchasing the base bid light fixture. PCO 007 The infiltration chamber (a filtering system to remove dirt, solid particals, grease and oil from rain water runoff in the parking lot) was required to be installed lower than originally planned to allow proper 2,230 slope for all catch basins. PCO 024 Staff and the architect changed some of the door hardware to new products not available at original bid time to significantly reduce -4,649 installation cost. PCO 027 Extra charges for gas line trenching from the building to the meter not 727 in the original scope of work. PCO 031 Additional charges for unforeseen conditions with lime treating the site. In three locations the existing shallow utilities needed to be 1,765 handworked and required extra pavement. PCO 033 During value engineering, the roof material on the upper roof and the eyebrows of Building A was changed to composite shingles from tile. In reviewing the look of the building while roofing materials were being added, staff recommend replacing the eyebrow composite 879 shingles with tile. PCO 034 During value engineering, the brick pavers in the sidewalk along Union Street were removed from the project. These pavers would match the streetscape that is in front of our existing building. Staff recommends putting these back in the project to keep the streetscape consistant. The City of Watsonville requested we reconsider keeping them in the 15,125 project as well. Green Technology Center 14,390 Total Change Order Ratification: Construction Change Orders: cont. Project Allied Health Sidewalk Reconfiguration Change order # Contractor Cen Con Amount Description PCO 003 We changed the top of the ramp area to allow better access to the court yard 3,580 between the buildings for service vehicles. PCO 004 Additional equipment and labor to remove an unforseen condition-excessive cement--during the required relocation of a storm drain. Included in this is authorization for over time to pour the retaining walls prior to the holiday weekend. The stair footing would have been exposed for 5 days in 1,863 an unsafe condition had we not done this. PCO 008 Due to unforeseen conditions with the sidewalk, the forms required last 1,499 minute adjustments just prior to pouring the cement to be compliant. PCO 009 The District received a large change order for adjusting 4 manhole covers and related demolition for paving the ADA accessible parking spaces and the ramps servicing the parking spaces. We removed this work from the contractor's scope of work after receiving a quote from another paving contractor to complete the work saving over $15,677 (the amount of the -12,904 change order). Allied Health Project Sesnon Road Repaving Change order # PCO 001 Sesnon Road Total All Change Orders -5,962 Total Change Order Contractor Earthworks Amount Description The original plan specified two different processes to be used for the road resurfacing. We simplified this to be a 6" section in all traffic areas and a 2" 8,690 section in all parking areas. 8,690 Total Change Order 17,118 Note: These change orders are reflected in the Facilities Master Plan (FMP) Status Report.