AGENDA ITEM BACKGROUND TO: GOVERNING BOARD DATE FROM: PRESIDENT August 1, 2011 SUBJECT: Ratification: Construction Change Orders REASON FOR BOARD CONSIDERATION ENCLOSURE(S) ITEM NUMBER Page 1 of 2 ACTION BACKGROUND: In accordance with Board Policy 4155, the attached change orders over $25,000 and less than 10% of the original contract value are submitted for Governing Board ratification. Continued on page 2 FISCAL IMPACT: $26,028 from the project contingency fund for each project. RECOMMENDATION: It is recommended that the Governing Board ratify the construction change orders provided as an attachment. Administrator Initiating Item: Joe Nugent Victoria Lewis Academic and Professional Matter If yes, Faculty Senate Agreement Senate President Signature Yes No Yes No Final Disposition Approved Ratification: Construction Change Orders: cont. Project Green Tech Center Change order # Contractor Dilbeck Amount Description PCO 016 786 PCO 030 589 PCO 029 PCO 023 8,582 659 10,615 Total Change Order Green Technology Center Project Allied Health Sidewalk Reconfiguration Change order # PCO 001 PCO 007 Replace sewer line to existing building damaged during site work, not shown on the plans. Adding a roof vent where tile ends. This was not in the drawings and is required. The interior paint was changed to meet new indoor air quality regulations which reduce the amount of off gassing allowed. Welding detail was missing requiring the metal deck to be welded. Contractor CenCon Amount Description The retaining wall specified in the plans would not be compliant with unforeseen conditions around the footing for the existing stairs. We need to have a larger retaining wall with a deeper and wider footing 14,041 with more steel reinforcement. The ramp was orginally specified to be 3' wide. We increased the width 1,372 to 4' wide to allow for a beeter flow of foot traffic. Allied Health 15,413 Total Change Order TOTAL 26,028 Note: These change orders are reflected in the Facilities Master Plan (FMP) Status Report.