Air Force Operation and Maintenance, Active Forces Budget Activity: Training and Recruiting Activity Group: Accession Training Detail by Subactivity Group: Facilities Sustainment, Restoration and Modernization I. Description of Operations Financed: Facilities Sustainment, Restoration and Modernization (FSRM) activities include demolition, sustainment and restoration and modernization accomplished by contract and by an in-house workforce. FSRM activities maintain base infrastructure and personnel support functions at the United States Air Force Academy (USAFA). Objectives are to sustain mission capability, quality of life, workforce productivity, and preserve the USAFA's physical plant. USAFA infrastructure support encompasses a variety of systems, services, and operations The most significant categories receiving this support are sustainment and restoration and modernization of: Real Property Aircraft Maintenance Complexes Aircraft Runways Roads Dormitories II. Force Structure Summary: Supports Facilities Sustainment, Modernization and Renovation of facilities at the United States Air Force Academy. 378 Air Force Operation and Maintenance, Active Forces Budget Activity: Training and Recruiting Activity Group: Accession Training Detail by Subactivity Group: Facilities Sustainment, Restoration and Modernization III. Financial Summary ($s in Thousands): FY 2001 A. Program Elements: Facility Sustainment Restoration and Modernization Demolition Total FY 2000 Actuals Budget Request Appn Current Estimate FY 2002 Estimate $45,242 912 271 $46,425 $62,586 2,069 0 $64,655 $54,403 2,028 0 $56,431 $53,931 2,018 0 $55,949 $28,332 32,102 0 $60,434 B. Reconciliation Summary: Baseline Funding Congressional Adjustments (Distributed) Congressional Adjustments (Undistributed) Adjustments to Meet Congressional Intent Congressional Adjustments (General Provisions) Subtotal Appropriated Amount Rescission Program Changes (CY to CY only) Subtotal Baseline Funding Reprogrammings Price Changes Functional Transfers Program Changes Current Estimate Change FY 01/01 Change FY 01/02 $64,655 0 0 -7,000 -1,224 $56,431 -$185 -1,203 $55,043 906 0 0 0 $55,949 $55,949 379 1,261 0 3,224 $60,434 Air Force Operation and Maintenance, Active Forces Budget Activity: Training and Recruiting Activity Group: Accession Training Detail by Subactivity Group: Facilities Sustainment, Restoration and Modernization C. Reconciliation of Increases and Decreases ($s in Thousands): FY 2001 President's Budget Request ....................................................................................................................... $64,655 1. Congressional Adjustments ................................................................................................................................... $-8,224 a) Distributed Adjustments ....................................................................................................... $0 b) Undistributed Adjustments ................................................................................................... $0 c) Adjustments to meet Congressional Intent ........................................................................... $-7,000 i) Facility Investment Strategy ............................................................................................ $-7,000 d) General Provisions ................................................................................................................ $-1,224 i) DWCF Rate Stabilization (Sec 8085, P.L. 106-259, FY 2001 Appn Act ) .................... $-906 ii) Headquarters and Administrative Activities (Sec 8165, P.L. 106-259, FY 2001 Appn Act) $-314 iii) Consulting and Advisory Services (Sec 8163, P.L. 106-259, FY 2001 Appn Act) ....... $-4 FY 2001 Appropriated Amount (subtotal) .............................................................................................................. $56,431 Government-Wide Rescission (Section 1403, P.L. 105-554) ............................................................................... -$185 2. Program Increases and Decreases ......................................................................................................................... $-1,203 a) Transfers ............................................................................................................................... 380 $0 Air Force Operation and Maintenance, Active Forces Budget Activity: Training and Recruiting Activity Group: Accession Training Detail by Subactivity Group: Facilities Sustainment, Restoration and Modernization b) Program Decreases ............................................................................................................... $-1,203 i) One-time Costs ................................................................................................................ 1) Realignment of Funds ......................................................................................... The FY 2001 Flying Hour Program reprice, based on the CY 2000 AFCAIG consumption factors, resulted in an overall shortfall which Air Force cash flowed from other Air Force Operation and Maintenance programs. After careful consideration of the alternatives, funds were realigned from this Sub Activity Group. While we recognize the detrimental impact on this Sub Activity Group, this one-time realignment was necessary to ensure continued aircrew readiness and safety of flight, and will be restored in subsequent years. $-823 $-823 ii) Program Reductions ........................................................................................................ 1) Civilian Pay Adjustment ................................................................................... The decrease represents revised civilian pay funding requirements based on updated assessment of actual workyear costs to reflect the impact of changes such as FY 2000 locality pay. $-380 $-380 FY 2001 Baseline Funding (subtotal) ....................................................................................................................... $55,043 3. Reprogrammings ................................................................................................................................................... $906 a) WCF Transfer (Sec 8005, P.L. 106-259, FY 2001 Appn Act ) ...................................... $906 Revised FY 2001 Estimate......................................................................................................................................... $55,949 4. Price Change ......................................................................................................................................................... $1,261 5. Transfers ................................................................................................................................................................ $0 381 Air Force Operation and Maintenance, Active Forces Budget Activity: Training and Recruiting Activity Group: Accession Training Detail by Subactivity Group: Facilities Sustainment, Restoration and Modernization 6. Program Increases ................................................................................................................................................. $11,269 a) Annualization of New FY 2001 Program ............................................................................. $0 b) One-time FY 2002 Costs ...................................................................................................... $1,008 i) Restoration of Flying Hour Reprice Realignment ........................................................... When the FY 2001 Flying Hour Program was repriced using the CY2000 AFCAIG factors, the resultant shortfall was cash flowed from other Air Force Operation and Maintenance programs. Funds realigned from this Sub-Activity Group in FY 2001 have been restored in full for FY 2002. $823 ii) Rescission Restoration .................................................................................................... Restoral of FY01 Government-Wide Rescission $185 c) Program Growth in FY 2002 ................................................................................................ $10,261 i) Civilian Separation Incentive ......................................................................................... Civilian separation incentives are authorized by Section 4436 of P.L. 102-484. These costs reflect the incremental funds required in FY 2002 over and above salary savings to implement endstrength reductions programmed due to A-76 and workforce restructuring actions. DoD activities may pay up to $25,000 for separation incentives plus 15% of basic pay to OPM. The current policy is to offer incentives before a person is involuntarily separated. $3,985 ii) Competitive and Privatization Savings............................................................................ This increase results from a change in approach to competitive sourcing and the cancellation of A-76 studies for programs such as Precision Measurement Equipment Laboratory (PMEL) and Corrosion Control.. $3,115 382 Air Force Operation and Maintenance, Active Forces Budget Activity: Training and Recruiting Activity Group: Accession Training Detail by Subactivity Group: Facilities Sustainment, Restoration and Modernization ii) FSRM Program Adjustment ............................................................................................ Adjustments were made, within FSRM Activity Groups, to realign funding in order to ensure an equitable programming outlook for all commands. $1,613 iii) Facility Sustainment ........................................................................................................ This increase realigns funding to the sustainment level, which will allow only necessary day-to-day recurring maintenance of real property facilities and infrastructure. Current funding only supports emergency and critical repair work. The impact of deferred maintenance is reduced productivity in maintenance shops, along the flight line and in office areas. $1,548 7. Program Decreases ................................................................................................................................................ a) Program Decreases in FY 2002 ............................................................................................ i) AF Offset ......................................................................................................................... The Air Force must meet readiness and mission requirements and was forced to use FSRM funding to meet these higher needs. FSRM funding is below the sustainment level. $-8,045 $-8,045 FY 2002 Budget Request ........................................................................................................................................... 383 $-8,045 $60,434 Air Force Operation and Maintenance, Active Forces Budget Activity: Training and Recruiting Activity Group: Accession Training Detail by Subactivity Group: Facilities Sustainment, Restoration and Modernization IV. Performance Criteria and Evaluation Summary: FY 2000 FY 2001 FY 2002 $626 81 240 321 $811 81 240 321 $2,599 3 107 110 A. Administration and Support Planning and Design Funds ($000) ......................................... Military E/S ............................................................................. Civilian E/S ............................................................................. Total E/S.............................................................................. 384 Air Force Operation and Maintenance, Active Forces Budget Activity: Training and Recruiting Activity Group: Accession Training Detail by Subactivity Group: Facilities Sustainment, Restoration and Modernization V. Personnel Summary Active Military End Strength (Total) Officer Enlisted Civilian End Strength (Total) U.S. Direct Hire Foreign National Direct Hire Total Direct Hire Foreign National Indirect Hire Active Military Average Strength (Total) Officer Enlisted Civilian FTEs (Total) U.S. Direct Hire Foreign National Direct Hire Total Direct Hire Foreign National Indirect Hire FY 2000 FY 2001 FY 2002 Change FY 01/02 81 3 78 81 3 78 3 0 3 -78 -3 -75 240 240 0 240 0 240 240 0 240 0 107 107 0 107 0 -133 -133 0 -133 0 81 3 78 81 3 78 43 2 41 -38 -1 -37 239 239 0 239 0 240 240 0 240 0 174 174 0 174 0 -66 -66 0 -66 0 385 Air Force Operation and Maintenance, Active Forces Budget Activity: Training and Recruiting Activity Group: Accession Training Detail by Subactivity Group: Facilities Sustainment, Restoration and Modernization VII. OP-32 Line Items: FOREIGN 101 103 107 308 401 411 412 415 417 502 503 505 506 771 915 920 922 923 924 989 998 FACILITIES SUSTAINMENT, RESTORATION & MODERNIZATION EXECUTIVE GENERAL SCHEDULE WAGE BOARD SEPARATION INCENTIVES TRAVEL OF PERSONS DFSC FUEL ARMY MANAGED SUPPLIES/MATERIALS NAVY MANAGED SUPPLIES/MATERIALS DLA MANAGED SUPPLIES/MATERIALS LOCAL PROC DWCF MANAGED SUPL MAT ARMY DWCF EQUIPMENT NAVY DWCF EQUIPMENT AIR FORCE DWCF EQUIPMENT DLA DWCF EQUIPMENT COMMERCIAL TRANSPORTATION RENTS (NON-GSA) SUPPLIES & MATERIALS (NON-DWCF) EQUIPMENT MAINTENANCE BY CONTRACT FACILITY MAINTENANCE BY CONTRACT MEDICAL SUPPLIES OTHER CONTRACTS OTHER COSTS TOTAL FACILITIES SUSTAINMENT, RESTORATION & MODERNIZATION FY 2000 CURRENCY ACTUAL 9,187 1,208 0 266 219 18 6 290 301 2 1 28 26 3 51 3,330 15 31,278 0 196 0 RATE DIFF 46,425 FOREIGN PRICE PROGRAM FY 2001 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 GROWTH 406 57 0 5 138 -1 1 13 5 0 0 2 1 0 1 53 0 501 0 3 0 GROWTH 288 -339 0 -54 -243 31 9 443 472 23 7 380 365 -3 -40 -1,680 20 8,643 1 14 2 ESTIMATE 9,881 926 0 217 114 48 16 746 778 25 8 410 392 0 12 1,703 35 40,422 1 213 2 0 1,185 8,339 55,949 386 CURRENCY PRICE RATE DIFF. PROGRAM FY 2002 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 GROWTH 437 40 0 4 -1 -1 -1 3 13 -1 0 44 2 0 0 29 1 688 0 4 0 GROWTH -3,790 320 3,985 13 46 -36 -12 -575 -609 -16 -6 -318 -262 0 47 91 -23 668 -1 587 3,115 ESTIMATE 6,528 1,286 3,985 234 159 11 3 174 182 8 2 136 132 0 59 1,823 13 41,778 0 804 3,117 0 1,261 3,224 60,434